share_log

Namibia Critical Metals Inc. Announces Positive Preliminary Economic Assessment for the Significantly Expanded Lofdal Heavy Rare Earth Project “2B-4” With $632.7 Million Pre-Tax NPV

Namibia Critical Metals Inc. Announces Positive Preliminary Economic Assessment for the Significantly Expanded Lofdal Heavy Rare Earth Project “2B-4” With $632.7 Million Pre-Tax NPV

納米比亞關鍵金屬公司宣佈對大幅擴大的洛夫達爾重稀土項目“2B-4”進行積極的初步經濟評估,税前淨現值為6.327億美元
Accesswire ·  2022/10/03 09:20

HALIFAX, NS / ACCESSWIRE / October 3, 2022 / Namibia Critical Metals Inc. ("Namibia Critical Metals" or the "Company" or "NMI") (TSXV:NMI)(OTC Pink:NMREF) is pleased to announce the results of its Preliminary Economic Assessment ("PEA") for the Lofdal Heavy Rare Earth Project "2B-4" ("Lofdal" or the "Project") in Namibia. This PEA aims at a significantly larger annual run-of-mine and plant throughput of 2 million tonnes per year and longer mine life than the historical PEA of 2014 by mining from two sub-deposits namely "Pit 2B" and "Pit 4". Further, the processing flow sheet was simplified to a direct flotation of the run-of-mine material and expanded to include a hydrometallurgical unit producing a >98% mixed rare earth oxide as final product instead of xenotime concentrate.

哈利法克斯,NS/ACCESSWIRE/2022年10月3日/納米比亞關鍵金屬公司(“納米比亞關鍵金屬”或“公司”或“NMI”)(多倫多證券交易所股票代碼:NMI)(場外交易代碼:NMREF)高興地宣佈其對納米比亞洛夫達爾重稀土項目“2B-4”(“洛夫達爾”或“項目”)的初步經濟評估結果。本次PEA的目標是通過從兩個子礦牀即“礦坑2B”和“礦坑4”進行採礦,使礦山和工廠的年生產能力大幅增加,達到每年200萬噸,並比歷史上2014年的PEA更長的礦山壽命。此外,流程簡化為原礦原料的直接浮選,並擴大到包括一個濕法冶金單元,生產大於98%的混合稀土氧化物作為最終產品,而不是混合稀土精礦。

The Lofdal deposit has the potential for significant production of dysprosium and terbium, two of the most valuable heavy rare earth elements. The Project is being developed in joint venture with Japan Oil, Gas and Metals National Corporation ("JOGMEC") targeting a long term, sustainable supply of heavy rare earths to Japan.

洛夫達爾礦牀具有大量生產鏑和鋱的潛力,這兩種最有價值的重稀土元素。該項目正在與日本石油、天然氣和金屬公司(JOGMEC)合資開發,目標是向日本長期、可持續地供應重稀土。

Highlights:

重點:

  • Net Present Value - NPV (5) of $632.7 Million USD (pre-tax) and $391 Million USD after-tax
  • Internal Rate of Return (IRR) - 34% pre-tax and 28% after tax
  • Life of mine nominal cash flow of $1.1 billion pre-tax, $698.7 million after-tax
  • Initial Capital Costs - $207 Million USD including a 30% contingency
  • Capital Payback Period - 3.2 years after-tax
  • Approximate Average Annual Production - 2,000 tonnes TREO including 117 tonnes Dysprosium and 17.5 tonnes Terbium
  • PEA is based on mining of only 26 million tonnes resource or about 50% of the 53 million tonnes in the Mineral Resource Estimate issued in June 2021
  • Estimated 16-year mine life with 13 million tonnes of low-grade stockpile likely expanding the life of mine
  • The price for Rare Earth Oxides used: Dysprosium oxide USD$587/kg and Terbium oxide USD$2,493/kg.
  • Average basket price of USD$91/kg including third party separation costs
  • 淨現值(簡寫為NPV(5)税前6.327億美元,税後3.91億美元
  • 內部回報率(IRR)-税前34%,税後28%
  • 礦山人壽税前名義現金流11億美元,税後6.987億美元
  • 初始資本成本-2.07億美元,包括30%的應急費用
  • 資本回收期-税後3.2年
  • 大約平均年產量--2,000噸TREO,包括117噸Dy和17.5噸Tb
  • 豌豆基於僅2600萬噸資源的開採,約佔2021年6月發佈的礦產資源評估中5300萬噸資源的50%
  • 預計16年礦山壽命,1300萬噸低品位庫存可能延長礦山壽命
  • 所用稀土氧化物的價格:氧化鏑587美元/公斤,氧化鋱2493美元/公斤。
  • 包括第三方分離費用在內的平均籃子價格為91美元/公斤

Cautionary Note: The preliminary economic assessment is preliminary in nature and includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them to enable them to be categorized as mineral reserves and there is no certainty that the preliminary economic assessment will be realized. Mineral resources that are not mineral reserves do not have a demonstrated economic viability

注意事項:初步經濟評估屬初步性質,幷包括被認為在地質上過於投機而不能應用經濟考慮因素以將其歸類為礦產儲量的推斷礦產資源,而初步經濟評估能否實現並不確定。不屬於礦產儲備的礦產資源不具有證明的經濟可行性。

Darrin Campbell, President of Namibia Critical Metals stated:

納米比亞關鍵金屬公司的達林·坎貝爾表示:

"This is a major step forward in establishing Lofdal as a world-class heavy rare project and a globally significant potential supplier of Dysprosium and Terbium, the two most valuable rare earth metals. This strong economic analysis supports the continued rapid development of Lofdal and we are moving forward with the next steps including Pre-Feasibility Study of this extended mining operation over the next few months. This robust economic assessment is only on 50% of our existing resource and we believe there is still considerable upside in exploration. Currently, processing test work continues, and it is expected to further significantly improve recoveries in all processing steps which will allow the Lofdal project to become one of the major future sources of dysprosium and terbium globally."

這是將洛夫達爾打造成世界級重稀土項目的重要一步,也是兩種最有價值的稀土金屬--鏑和鋱的全球重要潛在供應商。這一強有力的經濟分析支持了Lofdal的持續快速發展,我們正在推進下一步行動,包括在未來幾個月對這一擴大采礦作業進行初步可行性研究。這一強勁的經濟評估只對我們現有資源的50%進行了評估,我們相信勘探仍有相當大的上行空間。目前,加工測試工作仍在繼續,預計將進一步顯著提高所有加工步驟的回收率,這將使洛夫達爾項目成為未來全球主要的鏑和鋱來源之一。“

Lofdal deposit

洛夫達爾存款

The Lofdal Heavy Rare Earths deposit represents a district-scale (20 km x 10 km) heavy rare earth element (HREE) mineralisation in subvolcanic hydrothermal alteration zones. While high grade zones (>0.2% HREE) occur locally, the majority of the deposit resembles tens of meters wide and kilometer-long zones of low grade HREE-mineralisation with an average grade of about 0.1% HREE.

洛夫達爾重稀土礦牀代表了次火山熱液蝕變帶中的區域規模(20公里x 10公里)重稀土元素(HREE)礦化。雖然高品位帶(>0.2%重稀土元素)出現在局部,但大多數礦牀類似於數十米寬和千米長的低品位重稀土礦化帶,平均品位約為0.1%重稀土元素。

In order to develop the Lofdal project into a long-term producer of HREE, the Company focussed recent processing test work on cost-efficient technologies to upgrade lower grade material aiming at effects of economy of scale in a potential large-scale mining operation.

為了將洛夫達爾項目發展為重稀土的長期生產商,本公司最近的加工測試工作集中在低成本技術上,以升級較低品位的材料,以期在潛在的大規模採礦作業中產生規模經濟效應。

The Company mined a total of 34,500 tonnes of mineralised material from a starter pit in the central Area 4 deposit in October 2021 (Press release 29 November 2021). A 500 tonne sample was taken from the mineralized zone at a depth between 12 and 15 metres in order to minimize effects of surface related oxidation. The material was blended to provide homogenized samples which are representative of the wider deposit at a grade of about 0.187% TREO for bulk sample test work.

本公司於2021年10月從中部第4區礦牀的起始礦坑共開採了34,500噸礦化物質(新聞稿,2021年11月29日)。為了儘量減少表面氧化的影響,從12至15米深的礦化帶採集了500噸樣品。將這種材料混合,以提供代表更廣泛礦體的均質樣品,品位約為0.187%TREO,用於大宗樣品測試工作。

Summary of Mining Results

挖掘結果摘要

The proposed mining method is conventional open pit mining. Mineralised rock and waste would be drilled, blasted, loaded by hydraulic shovels and hydraulic excavators into off-highway dump trucks, and hauled to the processing plant. The basis for the pit design work was the mineral resource block model that was developed by MSA as part of Mineral Resource Estimate (see NI-43-101 Technical Report and press release dated June 30,2021).

提出的開採方法為常規露天開採。礦化的巖石和廢料將被鑽探、爆破,用液壓鏟子和液壓挖掘機裝載到駭維金屬加工附近的自卸卡車上,然後運往加工廠。礦坑設計工作的基礎是MSA開發的礦產資源區塊模型,作為礦產資源評估的一部分(見NI-43-101技術報告和2021年6月30日的新聞稿)。

The proposed mining method is the development of a slot in front of the mineralised zone at each level. The centralized slot will enable waste mining on one side while mining mineralised material on the other side. This methodology will also facilitate separating mineralised material from waste material. The target ROM feed to the processing plant is 2,000,000 tonnes per annum. The plant feed is mineralised material with a TREO >= 0.1%. In the current schedule the production ramps up to this over 4 years. Mineralised material with TREO >=0.05% and <0.1% is sent to a stockpile so it may be processed at a later stage if economics allow.

建議的採礦方法是在每一水平的礦化帶前開發一個礦槽。集中式礦槽將允許一邊開採廢物,另一邊開採礦化材料。這種方法還有助於將礦化物質從廢物中分離出來。該加工廠的目標只讀存儲器飼料為每年2,000,000噸。植物飼料是TREO>=0.1%的礦化物質。在目前的計劃中,產量將在4年內提高到這一水平。TREO>=0.05%的礦化物質和

The combined Life of Mine of the two pits is 16 years. Due to the nature of the deposit, the resultant pits are narrow and deep. No backfilling is contemplated.

兩礦合計使用壽命為16年。由於礦牀的性質,由此產生的礦坑又窄又深。不考慮回填。

An assumed maximum pit slope angle of 63° is applied to all slopes other than the low wall side, which follows the orebody and is at approximately 50°. With the inclusion of the ramp system the overall highwall slope in Pit 4 is approximately 55°.

除跟隨礦體且約為50°的低牆邊外,所有斜坡均假定最大坑坡角為63°。包括坡道系統在內,4號坑的整體高牆坡度約為55°。

During the PFS stage, a switch to underground mining will be considered for more cost-efficient mining of the lower levels in the current pit shell as well as to expand mining towards deeper parts of the resource.

在PFS階段,將考慮改用地下采礦,以更具成本效益地開採目前礦坑殼層的較低水平,並將採礦擴大到資源的更深部分。

Summary of Processing Results

處理結果摘要

Flotation test program

浮選試驗程序

The metallurgical bulk sample test program was amended to include flotation tests directly on the fresh, low-grade sample, by-passing initially planned XRT and XRF sorting which would result in additional losses. Iron removal by magnetic separation was moved to post flotation on a smaller concentrate stream reducing CAPEX and OPEX with minimal losses.

冶金大樣測試計劃被修改為包括直接對新鮮、低品位樣品進行浮選測試,繞過最初計劃的XRT和XRF分選,這將導致額外的損失。將磁選除鐵轉移到浮選後的較小精礦流上,以最小的損失降低了資本支出和運營成本。

Flotation test work was carried out at SGS Canada Inc. in Lakefield, Ontario, and at UVR-FIA GmbH in Freiberg, Germany. Both institutions, cumulatively conducted over 120 individual flotation tests using several types of collectors, depressants and considered thrifting of physical flotation conditions.

浮選測試工作在安大略省萊克菲爾德的SGS加拿大公司和德國弗萊貝格的UVR-FIA GmbH進行。這兩個機構使用幾種類型的捕收劑和抑制劑,累計進行了120多個單獨的浮選試驗,並考慮節省物理浮選條件。

The impact of high intensity conditioning ahead of flotation yielded clearly improved flotation performance.

浮選前的高強度調質對浮選效果有明顯的改善。

Best flotation results in regard to upgrade, recoveries and operating costs were achieved using moderate dosages of the collector Florrea 3900 and Calgon as depressant. Cleaner flotation concentrates from positive test runs produced at an overall mass pull of 2.7-3.9% with a product grade of 4-6% TREO and a recovery of up to 70% TREO. More importantly, the high value Heavy Rare Earth Elements, mainly hosted in xenotime, showed significantly better recoveries (58-75% HREO) than the Light Rare Earth Elements (49-58% LREO). Flotation tests on finer grind material reached up to 75.2% recovery for the Heavy Rare Earths Oxides which represents a significant upside potential currently tested.

使用適中劑量的捕收劑弗洛裏亞3900和卡爾貢作為抑制劑,在提質、回收和運營成本方面取得了最佳的浮選效果。更清潔的浮選精礦是在總體質量拉動為2.7-3.9%、產品品級為4-6%TREO、回收率高達70%TREO的情況下進行的。更重要的是,高值重稀土元素的回收率(58-75%HREO)明顯好於輕稀土元素(49-58%LREO)。對細磨材料的浮選試驗表明,重稀土氧化物的回收率高達75.2%,這是目前測試的一個顯着的上行潛力。

After defining the optimal flotation conditions, bulk flotation tests were conducted in quadruplicate to produce a flotation concentrate for downstream hydrometallurgical testing. Four bulk flotation tests demonstrated repeatable flotation performances on the low-grade feed material.

在確定了最佳浮選條件後,進行了四份混合浮選試驗,以生產用於下游濕法冶金試驗的浮選精礦。四次浮選試驗表明,低品位進料的浮選效果是可重複的。

Significant upside potential also remains in further optimizing flotation conditions.

在進一步優化浮選條件方面,仍有顯著的上行潛力。

Hydrometallurgical test work and results

濕法冶金試驗工作及結果

The mineral concentrate produced by bulk flotation was used for downstream hydrometallurgical testing. Four bulk flotation tests demonstrated repeatable flotation performances on the low grade direct run-of-mine feed material. The cleaner flotation from the bulk test runs produced a concentrate grade TREO ranging from 4.7 - 6%. This flotation concentrate marks the third such concentrate tested at the laboratories of SGS in Lakefield, Ontario, to determine the potential for producing a marketable rare earth product with minimal impurities. The previous hydrometallurgical test work at SGS had demonstrated the acid bake route is preferred due to lower reagent costs and higher recovery of the heavy rare earths compared to the caustic crack route.

將散裝浮選生產的礦物精礦用於下游濕法冶金試驗。四次浮選試驗表明,低品位直接給礦的浮選效果是可重複的。散裝試驗的精礦浮選產生了4.7-6%的精礦品位。該浮選精礦標誌着SGS在安大略省萊克菲爾德的實驗室測試的第三個此類精礦,以確定生產雜質最少的適銷對路稀土產品的潛力。SGS之前的濕法冶金試驗工作表明,與腐蝕性裂解路線相比,酸性焙燒路線是首選的路線,因為與腐蝕性裂解路線相比,試劑成本更低,重稀土的回收率更高。

A total of three acid bake and water leach tests were completed throughout the current test program to investigate the dissolution of rare earth elements (REE) and the behaviour of gangue minerals through the addition of sulphuric acid at elevated temperatures (300°C) and at a range of acid dosages (1-1.5 t/t concentrate basis). Under previously determined optimum conditions (2021 test program at SGS Canada), these tests showed very good REE recoveries with 96% for yttrium, 95% for dysprosium and 94% for terbium.

在當前的測試計劃中,總共完成了三次酸焙燒和水浸試驗,以研究稀土元素(REE)的溶解以及在高温(300°C)和一定酸量範圍(1-1.5噸/噸精礦)下添加硫酸對脈石礦物的行為。在之前確定的最佳條件下(SGS加拿大的2021年測試計劃),這些測試顯示出非常好的稀土回收率,Y的回收率為96%,鏑的回收率為95%,Tb的回收率為94%。

Results of the impurity removal and crude REE precipitation tests on the leached solutions corroborated chemistries with the previous test programs on the two flotation concentrates with low co-precipitation of RE's in the impurity removal stage (between 1-9% as compared to between 1-15% in previous) with similar precipitation of impurities. While the results are positive, there remains room to optimise these processes regarding OPEX and CAPEX as well as recoveries in continuous pilot plant testing during pre-feasibility study.

對浸出溶液進行的雜質去除和粗重稀土沉澱試驗的結果證實了兩個浮選精礦的化學結果,這兩個浮選精礦在除雜階段稀土共沉澱率較低(之前為1-15%),但雜質沉澱相似。雖然結果是正面的,但在預可行性研究期間,有關OPEX和CAPEX的這些流程以及在連續中試測試中的回收仍有優化的空間。

The addition of a hydrometallurgical plant at Lofdal would create further jobs in the southern Kunene Region of Namibia and provide a marketable product for export. The rare earth oxalate product with thorium and uranium levels below 3 ppm would be acceptable for import into Japan without restrictions or penalties.

在洛夫達爾增加一個濕法冶金廠將在納米比亞庫內內南部地區創造更多的就業機會,併為出口提供適銷對路的產品。稀土草酸鹽產品的釷和鈾含量低於3ppm,可以不受限制或處罰地進口到日本。

Table 6 - Total Capital Costs Summary (US$)
Direct Mining Costs1 -
Direct Mine Site Processing Costs 117,577,231
Direct Tailings Storage Facility Costs 13,628,361
SUB TOTAL INITIAL CAPITAL COSTS 131,205,593
Sustaining Capital Mining -
Sustaining Capital Processing 6,010,090
Sustaining Capital Tailings Storage Facility 5,432,266
Mine Closure Costs 5,000,000
Indirect Costs 18,560,082
Contingency 40,873,816
TOTAL CAPITAL COSTS 207,081,846
表6-總資本成本摘要(美元)
直接採礦成本1 -
直接礦場處理成本 117,577,231
直接尾礦儲存設施成本 13,628,361
初始資本成本小計 131,205,593
持續的資本挖掘 -
持續資本處理 6,010,090
可持續資本尾礦儲存設施 5,432,266
礦場關閉成本 5,000,000
間接成本 18,560,082
偶然性 40,873,816
總資本成本 207,081,846

1Mining will be conducted via contractor, all contractor capital recovery is reflected in the mining operating costs.

1採礦將通過承包商進行,所有承包商的資本回收都體現在採礦運營成本上。

Market Analysis - Pricing

市場分析-定價

A price deck has been developed for the Lofdal project based on an internal review of pricing as well as peer reports (Mkango Resources LTD DFS July, 2022, and Search Minerals PEA June, 2022) which in turn were developed based on third party independent market forecast analysis.

基於對定價的內部審查以及同行報告(Mkango Resources Ltd.DFS,2022年7月和Search Minerals PEA,2022年6月),已經為Lofdal項目制定了價格套餐,這些報告又是基於第三方獨立市場預測分析制定的。

The projected REO distribution for Lofdal concentrates is also presented in Table 7. The projected basket price is US$103.64.

表7還列出了洛夫達爾精礦的預計REO分佈。預計一籃子價格為103.64美元。

Table 7 - Pricing US$/Kg
Pricing Forecast for REE Pricing Used for Analysis Distribution
La2O3 $ -

9.2%

Ce2O3 $ -

16.0%

Pr2O3 $ 201.00

1.7%

Nd2O3 $ 212.00

6.3%

Sm2O3 $ 5.00

2.2%

Eu2O3 $ 36.00

1.1%

Gd2O3 $ 109.00

4.3%

Tb2O3 $ 2,493.00

0.9%

Dy2O3 $ 587.00

6.2%

Ho2O3 $ 290.00

1.3%

Er2O3 $ 64.00

3.8%

Yb2O3 $ 20.00

3.5%

Lu2O3 $ 947.00

0.5%

Y2O3 $ 17.00

42.4%

Tm2O3 $ 500.00

0.6%

Average Basket Value1 $ 103.64
表7-定價:美元/公斤
稀土元素的定價預測 用於分析的定價 分佈
三氧化二鑭 $ -

9.2%

Ce2O_3 $ -

16.0%

Pr2O_3 $ 201.00

1.7%

Nd2O_3 $ 212.00

6.3%

氧化Sm2O3 $ 5.00

2.2%

三氧化二Eu $ 36.00

1.1%

Gd2O3 $ 109.00

4.3%

三氧化二銻 $ 2,493.00

0.9%

Dy2O_3 $ 587.00

6.2%

HO2O_3 $ 290.00

1.3%

Er2O_3 $ 64.00

3.8%

Yb2O_3 $ 20.00

3.5%

三氧化二陸鋰 $ 947.00

0.5%

Y2O_3 $ 17.00

42.4%

三氧化二鈦 $ 500.00

0.6%

平均籃子價值1 $ 103.64

1Pricing used before refining charges of $12/kg TREO

1煉油前的定價為12美元/公斤TREO

Economic Analysis

經濟分析

The economic analysis assumes that the Project will be 100% equity financed and uses parameters relevant as of September 2022, under conditions likely to be applicable to project development and operation and analyzes the sensitivity of the Project to changes in the key Project parameters. All costs have been presented in United States Dollars (US$) and wherever applicable conversion from South African Rand (ZAR) has utilized an exchange ratio (ZAR/US$) of 16.07.

經濟分析假設項目將100%獲得股權融資,並在可能適用於項目開發和運營的條件下使用截至2022年9月的相關參數,並分析項目對關鍵項目參數變化的敏感性。所有費用均以美元(美元)列示,在適用情況下,從南非蘭特(ZAR)換算出來的匯率(ZAR/美元)為16.07。

Mining and treatment data, capital cost estimates and operating cost estimates have been put into a base case financial model to calculate the IRR and NPV based on calculated Project after tax cash flows. The scope of the financial model has been restricted to the Project level and as such, the effects of interest charges and financing have been excluded.

開採和處理數據、資本成本估計和運營成本估計已納入基本情況財務模型,以計算項目税後現金流量為基礎的內部收益率和淨現值。財務模式的範圍僅限於項目一級,因此,利息收費和融資的影響被排除在外。

For the purposes of the PEA, the evaluation is based on 100% of the Project cash flows before distribution of profits to the equity owners. Both pre-tax and after-tax cash flows have taken 5% royalty payments into account.

就PEA而言,在將利潤分配給股權所有者之前,評估是基於項目現金流的100%。税前和税後現金流都考慮了5%的特許權使用費支付。

At a discount rate of 5% the Project is anticipated to yield a pre-tax IRR of 34% with a NPV of US$632,739,693, and an after tax IRR of 28% with a NPV of US$390,982,730. Cumulative cash flows are US$1,110,393,637 pre-tax and US$698,691,741 after tax over the sixteen year LOM (Table 1).

按5%的貼現率計算,預計該項目的税前內部收益率為34%,淨現值為632,739,693美元,税後內部收益率為28%,淨現值為390,982,730美元。在16年的LOM中,累計現金流為1,110,393,637美元税前和698,691,741美元税後(表1)。

The Project is expected to pay back initial capital within the first 3.2 years.

該項目預計將在頭3.2年內收回初始資本。

Sensitivity Analysis

靈敏度分析

Pre Tax NPV at Range of Operating Costs

Discount

60%

70%

80%

90%

100%

110%

120%

130%

140%

5%

$1004.5M

$911.6M

$818.6M

$725.7M

$632.7M

$539.8M

$446.8M

$353.9M

$261.0M

7%

$822.6M

$744.0M

$665.4M

$586.8M

$508.3M

$429.7M

$351.1M

$272.5M

$193.9M

8%

$745.8M

$673.3M

$600.8M

$528.3M

$455.8M

$383.3M

$310.8M

$238.4M

$165.9M

9%

$676.9M

$609.9M

$542.9M

$475.9M

$408.9M

$341.9M

$274.9M

$207.9M

$140.9M

10%

$615.0M

$552.9M

$490.9M

$428.8M

$366.8M

$304.8M

$242.7M

$180.7M

$118.6M

Pre-Tax NPV At Range of Capital Costs

$ 124.2 $ 145.0 $ 165.7 $ 186.4

$207.1M

$ 227.8 $ 248.5 $ 269.2 $ 289.9
Discount

60%

70%

80%

90%

100%

110%

120%

130%

140%

5%

$708.0M

$689.2M

$670.4M

$651.5M

$632.7M

$613.9M

$595.1M

$576.3M

$557.5M

7%

$580.9M

$562.8M

$544.6M

$526.4M

$508.3M

$490.1M

$471.9M

$453.7M

$435.6M

8%

$527.3M

$509.4M

$491.6M

$473.7M

$455.8M

$437.9M

$420.1M

$402.2M

$384.3M

9%

$479.2M

$461.6M

$444.1M

$426.5M

$408.9M

$391.3M

$373.7M

$356.1M

$338.5M

10%

$436.0M

$418.7M

$401.4M

$384.1M

$366.8M

$349.5M

$332.2M

$314.9M

$297.6M

Pre-Tax NPV at Basket Price Levels

Discount

$70

$75

$80

$85

$92

$95

$100

$105

$110

5%

$240.1M

$330.8M

$421.5M

$512.3M

$632.7M

$693.7M

$784.4M

$883.2M

$965.9M

7%

$177.2M

$253.7M

$330.2M

$406.7M

$508.3M

$559.7M

$636.2M

$719.4M

$789.2M

8%

$150.9M

$221.3M

$291.8M

$362.3M

$455.8M

$503.2M

$573.6M

$650.3M

$714.6M

9%

$127.4M

$192.5M

$257.5M

$322.5M

$408.9M

$452.6M

$517.6M

$588.4M

$647.7M

10%

$106.5M

$166.6M

$226.8M

$286.9M

$366.8M

$407.2M

$467.4M

$532.8M

$587.6M

Pre-Tax NPV at Varying Recovery Ranges

Discount

43%

48%

53%

57%

59%

61%

64%

69%

74%

5%

$178.0M

$320.1M

$462.2M

$575.9M

$632.7M

$689.6M

$774.9M

$917.0M

$1059.1M

7%

$124.8M

$244.6M

$364.5M

$460.3M

$508.3M

$556.2M

$628.1M

$747.9M

$867.7M

8%

$102.6M

$213.0M

$323.4M

$411.7M

$455.8M

$500.0M

$566.2M

$676.6M

$787.0M

9%

$82.9M

$184.8M

$286.6M

$368.1M

$408.9M

$449.6M

$510.8M

$612.6M

$714.5M

10%

$65.3M

$159.5M

$253.7M

$329.1M

$366.8M

$404.5M

$461.0M

$555.2M

$649.4M

按經營成本計算的税前淨現值

折扣

60%

70%

80%

90%

100%

110%

120%

130%

140%

5%

$1004.5M

$911.6M

$818.6M

$725.7M

$632.7M

$539.8M

$446.8M

$353.9M

$261.0M

7%

$822.6M

$744.0M

$665.4M

$586.8M

$508.3M

$429.7M

$351.1M

$272.5M

$193.9M

8%

$745.8M

$673.3M

$600.8M

$528.3M

$455.8M

$383.3M

$310.8M

$238.4M

$165.9M

9%

$676.9M

$609.9M

$542.9M

$475.9M

$408.9M

$341.9M

$274.9M

$207.9M

$140.9M

10%

$615.0M

$552.9M

$490.9M

$428.8M

$366.8M

$304.8M

$242.7M

$180.7M

$118.6M

按資本成本計算的税前淨現值

$ 124.2 $ 145.0 $ 165.7 $ 186.4

$207.1M

$ 227.8 $ 248.5 $ 269.2 $ 289.9
折扣

60%

70%

80%

90%

100%

110%

120%

130%

140%

5%

$708.0M

$689.2M

$670.4M

$651.5M

$632.7M

$613.9M

$595.1M

$576.3M

$557.5M

7%

$580.9M

$562.8M

$544.6M

$526.4M

$508.3M

$490.1M

$471.9M

$453.7M

$435.6M

8%

$527.3M

$509.4M

$491.6M

$473.7M

$455.8M

$437.9M

$420.1M

$402.2M

$384.3M

9%

$479.2M

$461.6M

$444.1M

$426.5M

$408.9M

$391.3M

$373.7M

$356.1M

$338.5M

10%

$436.0M

$418.7M

$401.4M

$384.1M

$366.8M

$349.5M

$332.2M

$314.9M

$297.6M

一籃子價格水平的税前淨現值

折扣

$70

$75

$80

$85

$92

$95

$100

$105

$110

5%

$240.1M

$330.8M

$421.5M

$512.3M

$632.7M

$693.7M

$784.4M

$883.2M

$965.9M

7%

$177.2M

$253.7M

$330.2M

$406.7M

$508.3M

$559.7M

$636.2M

$719.4M

$789.2M

8%

$150.9M

$221.3M

$291.8M

$362.3M

$455.8M

$503.2M

$573.6M

$650.3M

$714.6M

9%

$127.4M

$192.5M

$257.5M

$322.5M

$408.9M

$452.6M

$517.6M

$588.4M

$647.7M

10%

$106.5M

$166.6M

$226.8M

$286.9M

$366.8M

$407.2M

$467.4M

$532.8M

$587.6M

不同復甦區間的税前淨現值

折扣

43%

48%

53%

57%

59%

61%

64%

69%

74%

5%

$178.0M

$320.1M

$462.2M

$575.9M

$632.7M

$689.6M

$774.9M

$917.0M

$1059.1M

7%

$124.8M

$244.6M

$364.5M

$460.3M

$508.3M

$556.2M

$628.1M

$747.9M

$867.7M

8%

$102.6M

$213.0M

$323.4M

$411.7M

$455.8M

$500.0M

$566.2M

$676.6M

$787.0M

9%

$82.9M

$184.8M

$286.6M

$368.1M

$408.9M

$449.6M

$510.8M

$612.6M

$714.5M

10%

$65.3M

$159.5M

$253.7M

$329.1M

$366.8M

$404.5M

$461.0M

$555.2M

$649.4M

Recommendations

建議

This PEA was based on the Mineral Resource Estimate produced by The MSA Group in 2021. Significant upside potential exists down dip of Area 4 and Area 2B as well as along the several kilometer long strike extensions of the mineralization in Areas 2 and 5. Therefore, with further exploration the run-of-mine and/or life time of the Lofdal mine could be significantly increased.

這份PEA是基於MSA集團2021年編制的礦產資源評估。4區和2B區以及2區和5區的礦化沿幾公里長的走向延伸存在顯著的上行潛力。因此,隨着進一步的勘探,洛夫達爾礦的原礦產量和/或壽命可能會大幅增加。

Sorting of the run-of-mine material was excluded from this PEA. However, historical and recent test work at TOMRA showed several approaches for an optimization of the Lofdal mine. Further studies will focus on three run-of-mine streams which will entail (1) higher grade material directly supplied to the flotation circuit while (2) lower grade material will run through a low filter XRT sorting with an upgrade factor expected in the range 2.0-2.5, and (3) very low grade (stockpile) material which will be XRT sorted with a high filter aiming at upgrades factors in the range 3.5-4 with relatively low recoveries around 50%. The latter will also source about 13 Mt of stockpile material which is not included in the current PEA.

原礦材料的分類不在本PEA的範圍內。然而,TOMRA的歷史和最近的測試工作表明,有幾種方法可以優化洛夫達爾礦。進一步的研究將集中在三個原礦流程上,這將需要(1)直接供應給浮選迴路的高品位材料,而(2)低品位材料將通過低過濾XRT分選,升級係數預計在2.0-2.5之間,以及(3)極低品位(庫存)材料將通過XRT分選,目的是針對3.5-4範圍內的提升係數,相對較低的回收率約50%。後者還將採購約13公噸庫存材料,這些材料不包括在當前的PEA中。

While completing this PEA, further flotation tests are continuing at SGS aiming at further optimization of flotation. Specifically, grind size and collector dosage optimization bears significant upside for better recoveries and lower OPEX.

在完成這一PEA的同時,SGS正在繼續進行進一步的浮選試驗,以進一步優化浮選。具體地説,磨礦粒度和捕收劑用量的優化對於更好的回收率和更低的OPEX具有顯著的優勢。

QUALIFIED PERSONS AND 43-101 TECHNICAL REPORT

合格人員和43-101技術報告

A NI 43-101 compliant report entitled Preliminary Economic Assessment on the Lofdal Heavy Rare Earths 2B-4 Project, Namibia ("the Report") will be filed on SEDAR within 45 days. SGS Canada Inc. is the principal author under the supervision of Michael Archer who is a Qualified Person in accordance with NI 43-101 - Standards of Disclosure for Mineral Projects.

符合NI 43-101標準的報告,標題為納米比亞洛夫達爾重稀土2B-4項目初步經濟評價(“報告”)將在45天內提交給SEDAR。SGS加拿大公司是在Michael Archer監督下的主要作者,Michael Archer是符合NI 43-101-礦物項目披露標準的合格人員。

Sections of the Report dealing with property description and location, accessibility, climate, local resources, infrastructure and physiography, history, geological setting and mineralisation, deposit types, exploration, drilling, sample preparation, analyses and security and data verification were completed by The MSA Group under the supervision of Jeremy Witley, (BSc Hons, MSc (Eng.)) and Swinden Geoscience Consultants under the supervision of Scott Swinden, (Ph.D P.Geo), who are Qualified Persons in accordance with NI 43-101 - standards of disclosure for mineral projects.

報告中涉及物業描述和位置、可訪問性、氣候、當地資源、基礎設施和地形、歷史、地質環境和礦化、礦牀類型、勘探、鑽探、樣品製備、分析以及安全和數據核實的部分由MSA集團在Jeremy Witley的監督下完成。和Swinden地球科學顧問,由Scott Swinden(Dr.P.Geo)監督,他們是符合NI 43-101-礦產項目信息披露標準的合格人員。

The section of the Report dealing with mineral resource estimates was completed by The MSA Group under the supervision of Jeremy Witley, (BSc Hons, MSc (Eng.))

報告中關於礦產資源評估的部分是由MSA集團在Jeremy Witley的監督下完成的。

Sections of the Report, dealing with mining methods and mine capital and operating costs were completed by SGS Canada under the supervision of Bill van Breugel (BaSc Hons, P.Eng.) who is a Qualified Person in accordance with NI 43-101 - Standards of Disclosure for Mineral Projects.

報告中涉及採礦方法、礦山資本和運營成本的部分由SGS加拿大公司在比爾·範·布魯格爾(BASC Hons,P.Eng)的監督下完成。世界衞生組織是符合NI 43-101-礦產項目披露標準的合格人員。

Sections of the Report, dealing with mining design and schedules were completed by BBMC RSA under the supervision of Johann Hager (BEng Hons, MEng Mining, P.Eng.) who is a Qualified Person in accordance with NI 43-101 - Standards of Disclosure for Mineral Projects.

報告中涉及採礦設計和時間表的部分由BBMC RSA在Johann Hager(BEng Hons,Meng Mining,P.Eng.)的監督下完成。世界衞生組織是符合NI 43-101-礦產項目披露標準的合格人員。

Each of Michael Archer, Jeremy Witley, Scott Swinden, Johann Hager and Bill van Breugel have reviewed and approved the technical disclosure in this press release.

邁克爾·阿徹、傑裏米·威特利、斯科特·斯文登、約翰·海格和比爾·範·布魯格爾都審查並批准了本新聞稿中的技術披露。

Rainer Ellmies, PhD, MScGeol, EurGeol, AusIMM and Vice President of Namibia Critical Metals Inc., is the Company's Qualified Person and has reviewed and approved the geological data in this press release.

納米比亞Critical Metals Inc.的Rainer Ellmies,PhD,MScGeol,EurGeol,AusIMM和副總裁總裁是公司的合格人員,並已審查和批准了本新聞稿中的地質數據。

About Namibia Critical Metals Inc.

關於納米比亞關鍵金屬公司

Namibia Critical Metals Inc. holds a diversified portfolio of exploration and advanced stage projects in Namibia focused on the development of sustainable and ethical sources of metals for the battery, electric vehicle and associated industries. The two advanced stage projects in the portfolio are Lofdal and Epembe. The Company also holds significant land positions in areas favourable for gold mineralization.

納米比亞關鍵金屬公司在納米比亞擁有多元化的勘探和高級階段項目組合,專注於為電池、電動汽車和相關行業開發可持續和合乎道德的金屬來源。該投資組合中的兩個高級階段項目是Lofdal和Epembe。公司還在有利於金礦成礦的地區持有大量土地頭寸。

Heavy Rare Earths: The Lofdal Dysprosium-Terbium Project is the Company's most advanced project being fully permitted with a Mining Licence (ML 200) issued in 2021. The project is being developed in joint venture with Japan Oil, Gas and Metals National Corporation ("JOGMEC").

重稀土:這個洛夫達鏑-鋱該項目是公司最先進的項目,於2021年獲得採礦許可證(ML 200)的全面許可。該項目正在與日本石油、天然氣和金屬公司(“JOGMEC”)合資開發。

About Japan Oil, Gas and Metals National Corporation (JOGMEC) and the JV

關於日本石油、天然氣和金屬公司(JOGMEC)和合資企業

JOGMEC is a Japanese government independent administrative agency which seeks to secure stable resource supplies for Japan. JOGMEC has a strong reputation as a long term, strategic partner in mineral projects globally. JOGMEC facilitates opportunities with Japanese private companies to secure supplies of natural resources for the benefit of the country's economic development.

JOGMEC是日本政府的獨立行政機構,旨在確保日本穩定的資源供應。JOGMEC作為全球礦產項目的長期戰略合作伙伴而享有盛譽。JOGMEC促進了與日本私營公司的機會,以確保自然資源的供應,從而造福於日本的經濟發展。

Rare earths are of critical importance to Japanese industrial interests and JOGMEC has extensive experience with all aspects of the sector. JOGMEC provided Lynas with US$250,000,000 in loans and equity in 2011 to ensure supplies of the Light Rare Earths metals suite to the Japanese industry.

稀土對日本的工業利益至關重要,JOGMEC在該行業的各個方面都有豐富的經驗。2011年,JOGMEC向Lynas提供了250,000,000美元的貸款和股權,以確保向日本行業供應輕稀土金屬套件。

Namibia Critical Metals owns a 95% interest in the Lofdal project with the remaining 5% held for the benefit of historically disadvantaged Namibians. The terms of the JOGMEC joint venture agreement with the Company stipulate that JOGMEC provides $3,000,000 in Term 1 and $7,000,000 in Term 2 to earn a 40% interest in the Lofdal project. Term 3 calls for a further $10,000,000 of expenditures to earn an additional 10% interest. JOGMEC can also purchase another 1% for $5,000,000 and has first right of refusal to fully fund the project through to commercial production and to purchase all production at market prices. The collective interests of NMI and historically disadvantaged Namibians cannot be diluted below a 26% carried working interest upon payment of $5,000,000 to JOGMEC for the dilution protection. The JV Agreement is structured such that no NMI equity will be issued and it is totally non-dilutive to NMI shareholders. To date, JOGMEC, has approved funding Term 1 and 2 expenditures totaling $7,800,000.

納米比亞關鍵金屬公司在Lofdal項目中擁有95%的權益,其餘5%的權益為歷史上處於不利地位的納米比亞人的利益而持有。JOGMEC與公司的合資協議條款規定,JOGMEC在第一階段提供3,000,000美元,在第二階段提供7,000,000美元,以賺取洛夫達爾項目40%的權益。第三階段要求再支出1,000萬美元,以賺取額外10%的利息。JOGMEC還可以再以500萬美元的價格購買1%的股份,並有權優先拒絕為該項目提供全額資金,直至商業生產,並以市場價格購買所有產品。在向JOGMEC支付5,000,000美元用於稀釋保護後,NMI和歷史上處於不利地位的納米比亞人的集體利益不能稀釋到26%的附帶工作權益以下。合營協議的結構將不會發行任何NMI股權,且對NMI股東完全不具攤薄作用。到目前為止,JOGMEC已經批准了第一和第二階段的供資支出,總額為7800 000美元。

Other exploration projects: The Company's Exclusive Prospecting Licenses ("EPLs") prospective for gold are located in the Central Namibian Gold Belt which hosts a number of significant orogenic gold deposits including the Navachab Gold Mine, the Otjikoto Gold Mine and more recently the discovery of the Twin Hills deposit. At the Erongo Gold Project, stratigraphic equivalents to the meta-sediments hosting the recent Osino gold discovery at Twin Hills have been identified and exploration is progressing over this highly prospective area. The Grootfontein Base Metal and Gold Project has potential for magmatic copper-nickel mineralization, Mississippi Valley-type zinc-lead-vanadium mineralization and Otjikoto-style gold mineralization. Interpretation of geophysical data and regional geochemical soil sampling have identified first gold targets.

其他勘探項目:公司的獨家金礦勘探許可證(“EPL”)位於納米比亞中部金礦帶,該地區擁有許多重要的造山帶金礦,包括Navachab金礦、Otjikoto金礦以及最近發現的Twin Hills金礦。在Erongo Gold在該項目中,已經確定了與最近在Twin Hills發現的Osino金礦所在的變質沉積物相對應的地層,並在這一極具前景的地區進行了勘探。這個Grootfontein賤金屬和金該項目具有巖漿銅鎳礦化、密西西比河谷型鋅鉛釩礦化和奧吉科託式金礦化的潛力。對地球物理數據的解釋和區域化探土壤採樣確定了第一批金礦靶區。

The common shares of Namibia Critical Metals Inc. trade on the TSX Venture Exchange under the symbol "NMI".

納米比亞關鍵金屬公司的普通股在多倫多證券交易所創業板交易,代碼為“NMI”。

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

多倫多證券交易所創業板交易所及其監管服務提供商(該術語在多倫多證券交易所的政策中定義)均不對本新聞稿的充分性或準確性承擔責任。

For more information please contact -

如需更多信息,請聯繫-

Namibia Critical Metals Inc.

納米比亞關鍵金屬公司。

Darrin Campbell, President
Tel: +01 (902) 835-8760
Email: Info@NamibiaCMI.com
Web site:

達林·坎貝爾,總裁
電話:+01(902)835-8760
電子郵件:Info@納米biaCMI.com
網站:

The foregoing information may contain forward-looking information relating to the future performance of Namibia Critical Metals Inc. forward-looking information, specifically, that concerning future performance, is subject to certain risks and uncertainties, and actual results may differ materially. These risks and uncertainties are detailed from time to time in the Company's filings with the appropriate securities commissions.

上述信息可能包含與納米比亞關鍵金屬公司未來業績有關的前瞻性信息。前瞻性信息,特別是有關未來業績的前瞻性信息,可能會受到某些風險和不確定性的影響,實際結果可能與此大不相同。這些風險和不確定因素在公司向適當的證券委員會提交的文件中不時有詳細説明。

SOURCE: Namibia Critical Metals Inc.

資料來源:納米比亞關鍵金屬公司。


View source version on accesswire.com:
在accesswire.com上查看源代碼版本:

声明:本內容僅用作提供資訊及教育之目的,不構成對任何特定投資或投資策略的推薦或認可。 更多信息
    搶先評論