VANCOUVER, British Columbia, April 23, 2024 (GLOBE NEWSWIRE) -- Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to provide a Q1 2024 construction progress update for its Terronera Project in Jalisco state, Mexico. A photo gallery presentation accompanies this news release and can be found here or on the Company website at Terronera Project Progress Photos. All dollar ($) references in this news release are United States dollars.
The Terronera project made significant progress in the first quarter, as concrete work was nearly complete on the Upper Plant Platform and erection of structural steel advanced for areas including crushing, coarse-ore storage, grinding, flotation, and thickening. Mechanical installation of major equipment continued to advance on schedule and the project remains on track for commissioning in Q4 2024.
"Site activities ramped up rapidly, as overall construction surpassed the halfway milestone," commented Don Gray, Chief Operating Officer. "We've been very pleased with progress of structural steel erection and major equipment installation including the semi-autogenous grinding ("SAG") and ball mills, apron feeders and flotation cells. Our procurement and materials management planning has been effective in keeping pace with site construction. We've been able to install many components upon immediate arrival to site, while making use of the limited laydown area. Underground mine development continues advancing very well, and we anticipate initial ore access in Q2. We are exceptionally pleased with the progress our Terronera team is making and remain committed to successfully completing and operating Endeavour's next core asset."
Q1 2024 Construction and Development Highlights
As of March 31, 2024, site works and activities included:
Safety – A strong onsite safety focus has enabled a notable 60% reduction in the lost-time injury frequency rate since Q2 2023, during a substantial increase in the workforce. Ongoing initiatives such as mandatory certification for working-at-heights, frequent field audits and inspections, rescue-team training, and regular emergency drills continue.
Progress – Overall project progress reached 53% completion, with more than $158 million (1) of the project's budget spent to date. Project commitments total $225 million (1,2) which is 83% of the $271 million capital budget.
Engineering – Efforts have been transitioning over to construction support. Detail design was completed for the Tailing Storage Facility ("TSF"), Portal 2 waste dump, and Lower Platform excavation.
Mine Development – During the quarter, over 1,000 metres of underground mine development was completed, bringing the total to over 3,200 metres. Mine crews continue working in Portal 1, 2, and 4 declines with excavations well advanced for the explosives magazines and the main pump-station sump system.
Upper Platform Plant Site – Surface mill and infrastructure construction is 56% complete and progressing on schedule. Concrete work is 83% complete, and structural steel erection is 80% complete.
Primary Crusher – Structural and mechanical construction was initiated on the conveyor and apron feeder support steel, and the apron feeder was placed in position.
Course Ore Stockpile and Reclaim ("COS") Tunnel – Two apron feeders were installed in the COS tunnel along with structural steel support, which opened the area to install the SAG feed conveyor.
Grinding – All major SAG and Ball Mill components were assembled. The high-pressure hydraulic pump was used for mounting the main bearings (spherical roller bearings), and all four bearings were installed under vendor supervision. Structural steel and pump installations continued.
Flotation – All flotation cell tanks were set in place and installation of the drive decks and structural steel installation continued. Several drive decks were assembled on the ground and lifted as complete units for each flotation cell tank. The regrind mill was set in place.
Tailing Thickener – The floor foundation and wall concrete were completed and erection of steel commenced together with the installation of the thickener tank floor.
Lower Facilities Platform and TSF – Excavation for the TSF embankment key trench was nearly 60% complete, and the lower platform area was nearly 45% complete, with the excavated material suitable to use in the TSF key trench and as embankment fill. Concrete work on the lower platform is anticipated to start in Q2.
Procurement – Bulk materials procurement purchase orders have been released and lead times are aligned with the current schedule. The Procurement team has focused on critical path purchases, such as electrical components and transfer chutes, and reducing bulk material lead times to increase schedule float.
Onsite Personnel – The workforce increased to 150 employees and over 400 contractor workers.
Community Relations – Supporting the local municipality continues to be a major commitment. A new miner training program for local community members was established to provide training and employment. The Company also sponsored English and computer skills for local communities.
Environmental – Environmental and social assessment initiatives continue according to schedule as outlined under the Equator Principal requirements for project loan financing.
Next Steps and Planning
The Terronera Project is on track for commissioning in Q4 2024.
For Q2 2024, surface construction will continue focusing on mechanical installations and initial electrical work for the crushing, coarse-ore stockpile, grinding, flotation and tailing thickener areas. Excavation of the Lower Platform is anticipated to be complete in the coming months. Concrete work is expected to be initiated for the LNG and power generation and concentrate and tailing filtration. Concentrate and tailing filtration structural, mechanical, and electrical installations will commence in early Q3.
Mine development in Portal 1, 2 and 4 declines will continue with first ore development anticipated in Q2. Initial long-hole mining is planned for Q3 followed by cut-and-fill mining; ore will be stockpiled for mill ramp up. Development activities at La Luz are anticipated to begin in Q2 with portal construction and ramp advance to ore access anticipated in Q4. The critical path remains the TSF and lower platform construction and advancing underground mine, where development is meeting expectations.
Visit , our dedicated project website, to stay informed on the ongoing development at Terronera. Explore updates, learn about our commitment to environmental stewardship, and discover the positive impacts on local communities.
カナダブリティッシュコロンビア州バンクーバー、2024年4月23日(GLOBE NEWSWIRE) - Endeavour Silver Corp.(以下「Endeavour」または「本社」)(NYSE:EXK; TSX:EDR)は、メキシコのハリスコ州のTerroneraプロジェクトの2024年Q1建設進捗状況についての更新を提供できることを喜んでいます。フォトギャラリープレゼンテーションは、このニュースリリースとTerronera Project Progress Photosの会社のウェブサイトで見つけることができます。このニュースリリースのすべてのドル($)の参照は、米ドルです。
上のプラントプラットフォームにおけるコンクリート作業がほぼ完了し、破砕、粗鉱庫貯蔵、研削、浮遊および厚化を含む領域の構造鋼の組み立てが進みました。主要機器の機械的な設置はスケジュール通りに進み、プロジェクトは2024年第4四半期の稼働に向けて進んでいます。
「全体的な建設が半分を超えるように、現場の活動は急速に拡大しました。」とCOOのDon Grayはコメントしています。 「構造鋼の設置、SAGおよびボールミル、エプロンフィーダー、およびフローテーションセルを含む主要機器の設置については非常に満足しています。調達と資材管理の計画は、現場建設とのペースを維持するのに有効でした。限られたレイダウンエリアを利用しながら、到着直後に多くの部品を取り付けることができました。地下鉱山の開発は非常に順調に進んでおり、2024年第2四半期に初期鉱石アクセスを見込んでいます。当社のTerroneraチームが進めているプログレスに非常に満足しており、Endeavourの次のコアアセットを成功裏に完成・運営することに尽力しています。」
2024年Q1の建設と開発のハイライト
2024年3月31日現在、現場作業および活動は以下を含みました。
安全性 - 現場での強力な安全重視により、労働者数の大幅な増加に伴い、喪失時間の減少割合がQ2 2023から60%減少しました。高所作業の強制認証、頻繁なフィールド監査、救助チームのトレーニング、定期的な緊急ドリルなどの取り組みが継続されています。
進捗状況 - 全体的なプロジェクトの進捗率は53%に達し、プロジェクトの予算のほぼ$158 million(1)が今までに使われました。プロジェクトのコミットメントは、$ 271 millionの資本予算の83%に相当する$ 225 million(1,2)です。
エンジニアリング - 取り組みは建設支援に移行しています。テーリングストレージ施設(「TSF」)、ポータル2の廃棄物投棄場、および下層プラットフォームの発掘の詳細な設計が完了しました。
鉱山開発 - 四半期に地下鉱山の開発が1,000メートル以上完了し、トータルで3,200メートル以上になりました。鉱山クルーは、爆薬マガジンと主要ポンプステーション排水槽システムの発掘が進んでおり、ポータル1、2、および4の下降を継続しています。
上部プラットフォームプラントサイト - 表面精米およびインフラ建設は56%完了し、スケジュール通りに進んでいます。コンクリート作業は83%完了し、構造鋼の設置は80%完了しました。
主要クラッシャー - コンベヤーおよびエプロンフィーダーサポートスチールの構造物および機械設計が開始され、エプロンフィーダーは位置に取り付けられました。
コース鉱石貯蔵庫および回収(「COS」)トンネル - COSトンネルに2つのエプロンフィーダーが設置され、SAGフィードコンベヤーを取り付けるために構造用鋼のサポートが開放されました。
研磨 - すべての主要SAGおよびボールミルコンポーネントが組み立てられました。高圧油圧ポンプは、主軸受(球面ローラーベアリング)を取り付けるために使用され、4つの軸受がすべてベンダーの監督下で取り付けられました。構造物用鋼およびポンプの設置が続きました。
フローテーション - すべてのフローテーションセルタンクが設置され、ドライブデッキと構造用鋼の設置が続きました。いくつかのドライブデッキは地上で組み立て、各フローテーションセルタンクに完全なユニットとして持ち上げられました。再精磨ミルが設置されました。
テーリングシックナー - 床の基礎および壁のコンクリートが完成し、設置用の鋼鉄の建て込みとシックナータンクの床の設置が始まりました。
下部プラットフォームおよびTSF - TSF堤のキートレンチの発掘がほぼ60%完了し、下層プラットフォーム領域がほぼ45%完了し、掘削された材料はTSFキートレンチおよび築堤用の充填材料として適しています。下層プラットフォームのコンクリート作業は第2四半期に開始される予定です。
調達 - 大量資材調達の購入オーダーがリリースされ、リードタイムが現在のスケジュールに合わせられています。調達チームは、電気部品や転送シュートなどのクリティカルパスの購入に焦点を当て、バルクマテリアルのリードタイムを短縮してスケジュールのフォートを増やしました。
現場人員 - 労働者数が150人を超え、請負業者労働者が400人以上になりました。
コミュニティ関係 - 地元自治体の支援を継続することは重要な取り組みです。地元コミュニティメンバーのための新しい鉱夫トレーニングプログラムが設立され、トレーニングや雇用を提供しています。会社は、英語とコンピューターのスキルを地元コミュニティで後援しています。
環境 - プロジェクトローンの融資に関するイクオター原則の要件に従って、環境および社会的評価イニシアチブがスケジュール通りに続けられています。
次のステップと計画
テロネラプロジェクトは2024年第4四半期の稼働を予定しています。
2024年第2四半期にも、砕石、粗鉱床ストックパイル、研磨、浮遊し尾液の分離装置が中心になる機械設備と初期の電気作業について、地上の建設が続きます。地下の下層プラットフォームの発掘作業は、数か月以内に完了する見通しです。LNGと発電、濃縮物と尾液のろ過に関しては、コンクリート工事が開始される予定です。濃縮物と尾液のフィルター構造、機械、電気設備の設置は、第3四半期の初めに始まります。
ポータル1、2、4 デクラインの鉱山開発は、第2四半期に最初の鉱石掘削が予想され、第3四半期には初期の長孔掘削が計画され、次に切り盛り掘削が行われ、鉱石をミルレンプに向けたストックパイルに積み上げます。La Luzでの開発活動は、第2四半期にポータルの建設と鉱石アクセスのためのランプの進化が期待されています。臨界経路は、TSFと下層プラットフォームの建設と地下鉱山の進展であり、開発は期待通りに進んでいます。
Terroneraの進行状況を常にモニターするために、専用のプロジェクトウェブサイトをご覧ください。最新情報を確認し、環境保護への取り組み、地元コミュニティに与えるポジティブな影響について学びましょう。