HOUSTON--(BUSINESS WIRE)--May 9, 2024-- NextDecade Corporation (NextDecade or the Company) (NASDAQ: NEXT) today provided an update on developmental and strategic activities for the first quarter 2024 and early second quarter 2024.

休斯顿--(美国商业资讯)--2024年5月9日--NextDecade公司(NextDecade或公司)(纳斯达克股票代码:NEXT)今天提供了2024年第一季度和2024年第二季度初的最新发展和战略活动。

CEO Commentary

首席执行官评论

"Construction of Phase 1 at the Rio Grande LNG Facility continues to progress according to plan, as we work alongside Bechtel to construct Trains 1 through 3 and their supporting infrastructure safely, efficiently, on schedule, and within budget," said Matt Schatzman, NextDecade's Chairman and Chief Executive Officer. "The Rio Grande LNG Facility has truly begun to take shape recently, as concrete foundation pours for Train 1 are ongoing, key materials such as piping and structural steel have been delivered to the site, and shoreline work and levee construction are underway. Proactive project and risk management remain key priorities as construction of Phase 1 continues to progress."

NextDecade董事长兼首席执行官马特·沙茨曼表示:“里奥格兰德液化天然气设施第一阶段的建设继续按计划进行,我们将与Bechtel合作,安全、高效、按时并在预算范围内建造1号至3号列车及其配套基础设施。”“里奥格兰德液化天然气设施最近真正开始成型,一号列车的混凝土基础浇筑正在进行中,管道和结构钢等关键材料已交付到现场,海岸线工程和堤坝建设正在进行中。随着第一阶段建设的持续进展,积极的项目和风险管理仍然是重中之重。”

"We are currently at a unique point in the Company's history as we develop and expect to FID highly attractive expansion capacity this year and next year, while safely constructing Phase 1 capacity, and preparing our organization to achieve our long-term objective of becoming a leading LNG owner and operator. We are confident that delivering on our plans will create long-term value for our stakeholders."

“我们目前正处于公司历史上的一个独特时刻,我们正在发展并预计将在今年和明年找到极具吸引力的扩张产能,同时安全地建设第一阶段的产能,并为我们的组织做好准备,以实现成为领先的液化天然气所有者和运营商的长期目标。我们相信,实现我们的计划将为我们的利益相关者创造长期价值。”

"We are focused on achieving a positive FID on Train 4 in the second half of this year. We expect TotalEnergies to exercise its option to purchase 1.5 million tonnes per annum of LNG from Train 4, and commercial discussions are progressing well with numerous additional counterparties for the remainder of the LNG necessary to support a positive FID on Train 4 this year. Additionally, we are continuing to work with Bechtel on the EPC contracting process, which we expect will enable us to finalize the EPC contract for Train 4 by the end of the second quarter of 2024. We are determined to capitalize on the robust market opportunity to unlock the value of our fully permitted, brownfield expansion capacity, and we are strongly committed to do so in a way that maximizes value to our shareholders."

“我们的重点是在今年下半年在4号列车上实现积极的外国直接投资。我们预计TotalEnergies将行使选择权,每年从4号列车购买150万吨液化天然气,商业讨论进展顺利,还有许多交易对手购买支持今年4号列车正向外国直接投资所需的剩余液化天然气。此外,我们将继续与Bechtel就EPC合同程序进行合作,我们预计这将使我们能够在2024年第二季度末之前敲定4号列车的EPC合同。我们决心利用这个强劲的市场机会,释放我们完全允许的棕地扩张产能的价值,我们坚定地致力于以最大限度地提高股东价值的方式做到这一点。”

Significant Recent Developments

近期重大进展

Construction

施工

Under the EPC contracts with Bechtel Energy Inc. (Bechtel), Phase 1 progress is tracked for Train 1, Train 2, and the common facilities on a combined basis and Train 3 on a separate basis. As of March 2024:

根据与Bechtel Energy Inc.(Bechtel)签订的EPC合同,将合并跟踪1号火车、2号列车和公共设施的第一阶段进展情况,并单独跟踪3号列车的进度。截至 2024 年 3 月:

  • The overall project completion percentage for Trains 1 and 2 and the common facilities of the Rio Grande LNG Facility was 18.2%, which is in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 54.9% complete, procurement was 34.4% complete, and construction was 1.9% complete.
  • The overall project completion percentage for Train 3 of the Rio Grande LNG Facility was 6.9%, based on preliminary schedules, which is also in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 5.2% complete, procurement was 16.7% complete, and construction was 0.0% complete.
  • 1号和2号列车以及里奥格兰德液化天然气设施公用设施的总体项目完成百分比为18.2%,符合EPC合同规定的时间表。在该项目完成百分比中,工程完成了54.9%,采购完成了34.4%,施工完成了1.9%。
  • 根据初步时间表,里奥格兰德液化天然气设施3号列车的总体项目完成率为6.9%,这也符合EPC合同规定的时间表。在该项目完成百分比中,工程完成了5.2%,采购完成了16.7%,施工完成了0.0%。

Financial

金融

  • In January 2024, the Company's wholly-owned subsidiary NextDecade LNG, LLC entered into a credit agreement that provides for a $50 million senior secured revolving credit facility with additional capacity of $12.5 million to cover interest. Borrowings under the revolving credit facility may be used for general corporate purposes, including development costs related to Train 4 at the Rio Grande LNG Facility. Borrowings bear interest at SOFR or the base rate plus an applicable margin as defined in the credit agreement. The revolving credit facility and interest term loan mature at the earlier of two years from the closing date or 10 business days after a positive FID of Train 4.
  • In February 2024, Rio Grande LNG, LLC (Rio Grande) issued and sold $190 million of senior secured notes in a private placement transaction to finance a portion of Phase 1. The senior secured notes were issued on February 9, 2024 and resulted in a reduction in the commitments outstanding under Rio Grande's existing bank credit facilities for Phase 1. These senior secured notes will be amortized over a period of approximately 18 years beginning in mid-2029, with a final maturity in June 2047. The senior secured notes bear interest at a fixed rate of 6.85% and rank pari passu to Rio Grande's existing senior secured financings.
  • 2024年1月,该公司的全资子公司NextDecade LNG, LLC签订了一项信贷协议,规定提供5000万美元的优先担保循环信贷额度,并额外提供1,250万加元的容量以支付利息。循环信贷额度下的借款可用于一般公司用途,包括与里奥格兰德液化天然气设施4号列车相关的开发成本。借款的利息按SOFR或基准利率加上信贷协议中规定的适用利息。循环信贷额度和利息定期贷款自截止日起两年内或4号列车FID为正数后的10个工作日到期,以较早者为准。
  • 2024年2月,里奥格兰德液化天然气有限责任公司(里奥格兰德)通过私募交易发行并出售了1.9亿美元的优先担保票据,为第一阶段的一部分提供资金。优先担保票据于2024年2月9日发行,导致里奥格兰德州现有银行信贷额度第一阶段的未偿承付款减少。这些优先担保票据将从2029年年中开始分期约18年,最终到期日为2047年6月。优先担保票据的利息固定利率为6.85%,排名靠前 pari passu 转到里奥格兰德现有的优先担保融资。

Rio Grande LNG Facility

里奥格兰德液化天然气设施

NextDecade is constructing and developing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel in south Texas. The site is located on 984 acres of land which has been leased long-term and includes 15,000 feet of frontage on the Brownsville Ship Channel. The Rio Grande LNG Facility has received necessary approvals and authorizations required for construction, including those from the Federal Energy Regulatory Commission (FERC) and the Department of Energy (DOE), which allow for development, construction, and operation of up to five trains and 27 MTPA of LNG exports.

NextDecade正在德克萨斯州南部布朗斯维尔船舶航道北岸建造和开发里奥格兰德液化天然气设施。该场地位于984英亩的土地上,该土地已长期租用,包括布朗斯维尔船舶航道的临街面积 15,000 英尺。里奥格兰德液化天然气设施已获得建设所需的必要批准和授权,包括联邦能源监管委员会(FERC)和能源部(DOE)的批准和授权,允许开发、建造和运营多达五列列车和每年2700万吨的液化天然气出口。

Phase 1 (Trains 1-3)

第 1 阶段(列车 1-3)

Phase 1 at the Rio Grande LNG Facility is under construction. Phase 1 includes three liquefaction trains with a total nameplate capacity of 17.61 MTPA of LNG production, two 180,000 cubic meter full containment LNG storage tanks, and two jetty berthing structures designed to load LNG carriers up to 216,000 cubic meters in capacity. Phase 1 also includes associated site infrastructure and common facilities including feed gas pretreatment facilities, electric and water utilities, two totally enclosed ground flares for the LNG tanks and marine facilities, two ground flares for the liquefaction trains, roads, levees surrounding the entire site, and warehouses, administrative, operations control room, and maintenance buildings.

里奥格兰德液化天然气设施的第一阶段正在建设中。第一阶段包括三列液化列车,总标称容量为每年17.61万吨的液化天然气产量,两个18万立方米的全封闭液化天然气储罐,以及两个设计用于装载容量高达21.6万立方米的液化天然气运输船的码头停泊结构。第一阶段还包括相关的场地基础设施和公用设施,包括原气预处理设施、电力和供水设施、两个用于液化天然气储罐和海事设施的全封闭地照明弹、用于液化列车的两个地面照明弹、道路、整个场地周围的堤坝,以及仓库、行政、运营控制室和维护大楼。

As of March 2024, progress on Trains 1 through 3 is in line with the schedule under the EPC Contracts. The civil works program has continued to progress via the deep soil mixing program, as Train 1 deep soil mixing is approaching completion and rigs are preparing to move to Train 2 for production and Train 3 for testing. Concrete foundation pours for Train 1 are underway. Delivery of key materials to site has begun, including large bore above-ground pipe and structural steel. Additionally, LNG tank piling has progressed significantly, berth 1 piling work commenced, and levee construction continues.

截至2024年3月,1号至3号列车的进展符合EPC合同规定的时间表。随着1号列车深层土壤混合接近完成,钻机正准备移至2号列车进行生产,3号列车进行测试,土木工程项目继续通过深层土壤混合计划取得进展。1号列车的混凝土基础浇筑正在进行中。关键材料已开始运送到现场,包括大口径地上管道和结构钢。此外,液化天然气储罐的打桩工作取得了显著进展,1号泊位的打桩工作已经开始,堤坝建设仍在继续。

Bechtel has made meaningful progress on procurement for Phase 1, with a focus on completing purchase orders for critical and high-value items early in the construction process. As of March 2024, Bechtel has issued approximately 90% of the total purchase orders for Trains 1 and 2 based on dollar value and approximately 84% of the total purchase orders for Train 3 based on dollar value.

Bechtel在第一阶段的采购方面取得了有意义的进展,重点是在施工过程的早期完成关键和高价值物品的采购订单。截至2024年3月,Bechtel已根据美元价值签发了1号和2号列车总采购订单的约90%,按美元价值签发了约占3号列车总采购订单的84%。

NextDecade holds equity interests in the Phase 1 joint venture that entitle it to receive up to 20.8% of the distributions of available cash during operations.

NextDecade持有第一阶段合资企业的股权,这使其有权在运营期间获得高达20.8%的可用现金分配。

Final Investment Decision on Train 4 and Train 5

火车4和5号列车的最终投资决定

NextDecade is targeting a positive FID and the issuance of a full notice to proceed (NTP) to Bechtel for Train 4 and its related infrastructure at the Rio Grande LNG Facility in the second half of 2024. Achieving a positive FID on Trains 4 and 5, the fully permitted expansion capacity at the Rio Grande LNG Facility will be subject to, among other things, finalizing and entering into EPC contracts, entering into appropriate commercial arrangements, and obtaining adequate financing to construct each train and related infrastructure.

NextDecade的目标是在2024年下半年对里奥格兰德液化天然气设施进行积极的外国直接投资,并向Bechtel发出一份全面的通知(NTP),以便在里奥格兰德液化天然气设施进行4号列车及其相关基础设施。在4号和5号列车上实现积极的外国直接投资,里奥格兰德液化天然气设施的全部允许扩建能力将取决于EPC合同的敲定和签订、适当的商业安排以及获得足够的资金来建造每列列车和相关基础设施。

The Company has undertaken certain pre-FID activities for Train 4, including the FEED and EPC contract processes with Bechtel, which the Company expects will enable the finalization of the EPC contract for Train 4 by the end of the second quarter of 2024.

该公司已经为4号列车开展了某些预开发活动,包括与Bechtel签订的FEED和EPC合同流程,该公司预计,这将使4号列车的EPC合同能够在2024年第二季度末之前敲定。

The Company continues to advance commercial discussions with multiple potential counterparties and expects to finalize commercial arrangements for Train 4 in the coming months to support an FID on Train 4 in the second half of 2024.

该公司继续推进与多个潜在交易对手的商业讨论,并预计将在未来几个月内敲定4号列车的商业安排,以支持2024年下半年在4号列车上进行外国直接投资。

The Company expects to finance construction of Train 4 utilizing a combination of debt and equity funding. The Company expects to enter into bank facilities for the debt portion of the funding. In connection with consummating the Rio Grande Phase 1 equity joint venture, the Company's equity partners each have options to invest in Train 4 equity, which, if exercised, would provide approximately 60% of the equity funding required for Train 4. Inclusive of these options, NextDecade currently expects to fund 40% of the equity commitments for Train 4 and to have an initial economic interest of 40% in Train 4, increasing to 60% after its equity partners achieve certain returns on their investments in Train 4. The Company expects to complete the financing process for Train 4 after the EPC contract and commercial arrangements are finalized.

该公司预计将利用债务和股权融资相结合的方式,为4号列车的建设提供资金。该公司预计将为融资的债务部分提供银行贷款。在完善里奥格兰德第一阶段股权合资企业方面,该公司的股权合伙人均可选择投资4号列车的股权,如果行使该股权,将提供4号列车所需股权资金的约60%。包括这些期权在内,NextDecade目前预计将为4号列车的40%的股权承诺提供资金,并在4号列车中拥有40%的初始经济利益,在其股权合作伙伴对4号列车的投资获得一定回报后,将增加到60%。该公司预计将在EPC合同和商业安排最终确定后完成4号列车的融资流程。

The Company expects to begin the EPC contracting process for Train 5 after a positive FID on Train 4. TotalEnergies also holds an LNG purchase option for 1.5 MTPA for Train 5, and the Rio Grande Phase 1 equity partners have options to invest in Train 5 equity which are materially equivalent to their options to participate in Train 4 equity.

该公司预计将在4号列车获得积极的外国直接投资后开始5号列车的EPC合同程序。TotalEnergies还持有5号列车每年150万吨的液化天然气购买期权,里奥格兰德州第一阶段的股权合作伙伴可以选择投资5号列车股权,这与他们参与4号列车股权的期权基本等同。

Investor Presentation

投资者演讲

NextDecade has posted an updated investor presentation to its website concurrently with this release. A copy of this release and the investor presentation can be found on its website at www.next-decade.com.

NextDecade已在本新闻稿的同时在其网站上发布了最新的投资者演示文稿。本新闻稿和投资者演示文稿的副本可在其网站上找到 www.next-decade

About NextDecade Corporation

关于 nextDecade

NextDecade Corporation is an energy company accelerating the path to a net-zero future. Leading innovation in more sustainable LNG and carbon capture solutions, NextDecade is committed to providing the world access to cleaner energy. Through our subsidiaries Rio Grande LNG and NEXT Carbon Solutions, we are developing a 27 MTPA LNG export facility in South Texas along with one of the largest carbon capture and storage projects in North America. We are also working with third-party customers around the world to deploy our proprietary processes to lower the cost of carbon capture and storage and reduce CO2 emissions at their industrial-scale facilities. NextDecade's common stock is listed on the Nasdaq Stock Market under the symbol "NEXT." NextDecade is headquartered in Houston, Texas. For more information, please visit www.next-decade.com.

NextDecade Corporation是一家能源公司,正在加速通往净零未来的道路。NextDecade引领更可持续的液化天然气和碳捕集解决方案的创新,致力于为世界提供更清洁的能源。通过我们的子公司里奥格兰德液化天然气和NEXT Carbon Solutions,我们正在南德克萨斯州开发一个每年2700万吨的液化天然气出口设施,以及北美最大的碳捕集和储存项目之一。我们还与世界各地的第三方客户合作,部署我们的专有工艺,以降低碳捕集和封存的成本并减少二氧化碳2 其工业规模设施的排放。NextDecade的普通股在纳斯达克股票市场上市,股票代码为 “NEXT”。NextDecade 总部位于德克萨斯州休斯敦。欲了解更多信息,请访问 www.next-decade

Forward-Looking Statements

前瞻性陈述

This press release contains forward-looking statements within the meaning of U.S. federal securities laws. The words "anticipate," "contemplate," "estimate," "expect," "project," "plan," "intend," "believe," "may," "might," "will," "would," "could," "should," "can have," "likely," "continue," "design," "assume," "budget," "guidance," "forecast," and "target," and other words and terms of similar expressions are intended to identify forward-looking statements, and these statements may relate to the business of NextDecade and its subsidiaries. These statements have been based on assumptions and analysis made by NextDecade in light of current expectations, perceptions of historical trends, current conditions and projections about future events and trends and involve a number of known and unknown risks, which may cause actual results to differ materially from expectations expressed or implied in the forward-looking statements. Although NextDecade believes that the expectations reflected in these forward-looking statements are reasonable, it can give no assurance that the expectations will prove to be correct. NextDecade's actual results could differ materially from those anticipated in these forward-looking statements as a result of a variety of factors, including those discussed in NextDecade's periodic reports that are filed with and available from the Securities and Exchange Commission. Additionally, any development of subsequent trains at the Rio Grande LNG Facility or CCS projects remains contingent upon execution of definitive commercial and financing agreements, securing all financing commitments and potential tax incentives, achieving other customary conditions and making a final investment decision to proceed. The forward-looking statements in this press release speak as of the date of this release. NextDecade may from time to time voluntarily update its prior forward-looking statements, however, it disclaims any commitment to do so except as required by securities laws.

本新闻稿包含美国联邦证券法所指的前瞻性陈述。“预测”、“考虑”、“估计”、“期望”、“项目”、“计划”、“打算”、“相信”、“可能”、“将”、“可能”、“应该”、“可以有”、“可能”、“继续”、“设计”、“假设”、“预算”、“指导”、“预测” 和 “目标,” 以及其他类似表述的词汇和术语旨在识别前瞻性陈述,这些陈述可能与NextDecade及其子公司的业务有关。这些陈述基于NextDecade根据当前的预期、对历史趋势的看法、当前状况以及对未来事件和趋势的预测做出的假设和分析,涉及许多已知和未知的风险,这可能导致实际结果与前瞻性陈述中表达或暗示的预期存在重大差异。尽管NextDecade认为这些前瞻性陈述中反映的预期是合理的,但它无法保证预期会被证明是正确的。由于多种因素,NextDecade的实际业绩可能与这些前瞻性陈述中的预期存在重大差异,包括向美国证券交易委员会提交并可从中获得的NextDecade定期报告中讨论的因素。此外,里奥格兰德液化天然气设施或CCS项目后续列车的任何开发仍取决于最终商业和融资协议的执行、所有融资承诺和潜在的税收优惠的担保、满足其他惯例条件以及做出最终的投资决定。本新闻稿中的前瞻性陈述是截至本新闻稿发布之日的。NextDecade可能会不时自愿更新其先前的前瞻性陈述,但是,除非证券法要求,否则它不做任何这样做的承诺。

Investors
Megan Light
mlight@next-decade.com
832-981-6583

投资者
梅根·莱特
mlight@next-decade.com
832-981-6583

Media
Susan Richardson
srichardson@next-decade.com
832-413-6400

媒体
苏珊·理查森
srichardson@next-decade.com
832-413-6400

Source: NextDecade Corporation

来源:NextDecade 公司

声明:本内容仅用作提供资讯及教育之目的,不构成对任何特定投资或投资策略的推荐或认可。 更多信息
    抢沙发