Endeavour Silver Provides Q1 2024 Construction Progress Update on Terronera; Construction Progress Reaches 53% Completion

Endeavour Silver Provides Q1 2024 Construction Progress Update on Terronera; Construction Progress Reaches 53% Completion

Endeavor Silver 提供了 Terronera 的 2024 年第一季度施工进度最新情况;施工进度达到 53%
GlobeNewswire ·  04/23 17:00

VANCOUVER, British Columbia, April  23, 2024  (GLOBE NEWSWIRE) -- Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to provide a Q1 2024 construction progress update for its Terronera Project in Jalisco state, Mexico. A photo gallery presentation accompanies this news release and can be found here or on the Company website at Terronera Project Progress Photos. All dollar ($) references in this news release are United States dollars.

不列颠哥伦比亚省温哥华,2024年4月23日(环球新闻专线)——奋进银业公司(“奋进号” 或 “公司”)(纽约证券交易所代码:EXK;多伦多证券交易所股票代码:EDR)很高兴提供其位于墨西哥哈利斯科州的Terronera项目的2024年第一季度施工进度最新情况。本新闻稿附有照片库演示,可以在此处或公司网站的Terronera项目进度照片上找到。本新闻稿中提到的所有美元($)均为美元。

The Terronera project made significant progress in the first quarter, as concrete work was nearly complete on the Upper Plant Platform and erection of structural steel advanced for areas including crushing, coarse-ore storage, grinding, flotation, and thickening. Mechanical installation of major equipment continued to advance on schedule and the project remains on track for commissioning in Q4 2024.

Terronera项目在第一季度取得了重大进展,上部工厂平台的混凝土工程已接近完成,包括破碎、粗矿储存、研磨、浮选和增稠等领域的钢结构安装也已接近尾声。主要设备的机械安装继续按计划推进,该项目仍有望在2024年第四季度进行调试。

"Site activities ramped up rapidly, as overall construction surpassed the halfway milestone," commented Don Gray, Chief Operating Officer. "We've been very pleased with progress of structural steel erection and major equipment installation including the semi-autogenous grinding ("SAG") and ball mills, apron feeders and flotation cells. Our procurement and materials management planning has been effective in keeping pace with site construction. We've been able to install many components upon immediate arrival to site, while making use of the limited laydown area. Underground mine development continues advancing very well, and we anticipate initial ore access in Q2. We are exceptionally pleased with the progress our Terronera team is making and remain committed to successfully completing and operating Endeavour's next core asset."

首席运营官唐·格雷评论说:“随着整体施工超过中途里程碑,现场活动迅速增加。”“我们对钢结构安装和主要设备安装的进展感到非常满意,包括半自磨机(“SAG”)和球磨机、停机坪给料机和浮选池。我们的采购和物料管理计划有效地跟上了场地建设的步伐。我们能够在立即到达现场后安装许多组件,同时充分利用有限的布置区域。地下矿山开发继续取得良好进展,我们预计第二季度将首次获得矿石。我们对Terronera团队取得的进展感到非常满意,并将继续致力于成功完成和运营Endeavor的下一个核心资产。”

Q1 2024 Construction and Development Highlights

2024 年第一季度建设与开发亮点

As of March 31, 2024, site works and activities included:

截至2024年3月31日,场地工程和活动包括:

  • Safety – A strong onsite safety focus has enabled a notable 60% reduction in the lost-time injury frequency rate since Q2 2023, during a substantial increase in the workforce. Ongoing initiatives such as mandatory certification for working-at-heights, frequent field audits and inspections, rescue-team training, and regular emergency drills continue.

  • Progress – Overall project progress reached 53% completion, with more than $158 million (1) of the project's budget spent to date. Project commitments total $225 million (1,2) which is 83% of the $271 million capital budget.

  • Engineering – Efforts have been transitioning over to construction support. Detail design was completed for the Tailing Storage Facility ("TSF"), Portal 2 waste dump, and Lower Platform excavation.

  • Mine Development – During the quarter, over 1,000 metres of underground mine development was completed, bringing the total to over 3,200 metres. Mine crews continue working in Portal 1, 2, and 4 declines with excavations well advanced for the explosives magazines and the main pump-station sump system.

  • Upper Platform Plant Site – Surface mill and infrastructure construction is 56% complete and progressing on schedule. Concrete work is 83% complete, and structural steel erection is 80% complete.

    • Primary Crusher – Structural and mechanical construction was initiated on the conveyor and apron feeder support steel, and the apron feeder was placed in position.

    • Course Ore Stockpile and Reclaim ("COS") Tunnel – Two apron feeders were installed in the COS tunnel along with structural steel support, which opened the area to install the SAG feed conveyor.

    • Grinding – All major SAG and Ball Mill components were assembled. The high-pressure hydraulic pump was used for mounting the main bearings (spherical roller bearings), and all four bearings were installed under vendor supervision. Structural steel and pump installations continued.

    • Flotation – All flotation cell tanks were set in place and installation of the drive decks and structural steel installation continued. Several drive decks were assembled on the ground and lifted as complete units for each flotation cell tank. The regrind mill was set in place.

    • Tailing Thickener – The floor foundation and wall concrete were completed and erection of steel commenced together with the installation of the thickener tank floor.

  • Lower Facilities Platform and TSF – Excavation for the TSF embankment key trench was nearly 60% complete, and the lower platform area was nearly 45% complete, with the excavated material suitable to use in the TSF key trench and as embankment fill. Concrete work on the lower platform is anticipated to start in Q2.

  • Procurement – Bulk materials procurement purchase orders have been released and lead times are aligned with the current schedule. The Procurement team has focused on critical path purchases, such as electrical components and transfer chutes, and reducing bulk material lead times to increase schedule float.

  • Onsite Personnel – The workforce increased to 150 employees and over 400 contractor workers.

  • Community Relations – Supporting the local municipality continues to be a major commitment. A new miner training program for local community members was established to provide training and employment. The Company also sponsored English and computer skills for local communities.

  • Environmental – Environmental and social assessment initiatives continue according to schedule as outlined under the Equator Principal requirements for project loan financing.

  • 安全 — 自2023年第二季度以来,在员工人数大幅增加的情况下,对现场安全的强烈关注使损失工时伤害发生率显著降低了60%。正在进行的举措仍在继续,例如强制性高空工作认证、频繁的现场审计和检查、救援队培训和定期的应急演习。

  • 进展——项目总体进度达到53%,迄今为止该项目预算的支出超过1.58亿美元(1)。项目承诺总额为2.25亿美元(1,2),占2.71亿美元资本预算的83%。

  • 工程——工作已过渡到施工支持。尾矿储存设施(“TSF”)、Portal 2垃圾堆和下层平台挖掘的详细设计已经完成。

  • 矿山开发 — 在本季度,超过1,000米的地下矿山开发完工,使总面积超过3,200米。矿工继续在 Portal 1、2 和 4 的下坡处工作,炸药库和主泵站排水系统的挖掘工作进展顺利。

  • 上层平台工厂场地——露天磨机和基础设施建设已完成 56%,正在按计划进行中。混凝土工程已完成83%,钢结构安装已完成80%。

    • 初级破碎机 — 开始在输送机和停机坪给料机支撑钢上进行结构和机械构造,并将停机坪给料机放置到位。

    • 球场矿石储存和回收(“COS”)隧道——在COS隧道中安装了两个停机坪给料机以及结构钢支架,这为安装SAG进料输送机开辟了区域。

    • 研磨 — 所有主要的 SAG 和球磨机部件均已组装完毕。高压液压泵用于安装主轴承(球面滚子轴承),所有四个轴承均在供应商的监督下安装。钢结构和泵的安装仍在继续。

    • 浮选 — 所有浮选池均已就位,驱动甲板和钢结构装置的安装仍在继续。在地面上组装了几个驱动甲板,并将其作为完整单元吊装在每个浮选电池箱中。再研磨机已经安装到位。

    • 尾矿增稠剂 — 地板基础和墙体混凝土已经完成,开始架设钢材,同时安装增稠剂储罐底板。

  • 下层设施平台和TSF — TSF路堤关键沟槽的挖掘已完成近60%,下层平台区域已完成近45%,挖掘出的材料适合在TSF关键沟槽中使用并用作路堤填料。下层平台的具体工作预计将于第二季度开始。

  • 采购 — 批量材料采购订单已经发布,交货时间与当前计划保持一致。采购团队专注于关键路径采购,例如电气元件和传输槽,并缩短散装材料的交货时间以增加进度浮动。

  • 现场人员 — 员工人数增加到 150 名员工和 400 多名承包商员工。

  • 社区关系—支持当地市政当局仍然是一项重大承诺。为当地社区成员制定了一项新的矿工培训计划,以提供培训和就业。该公司还赞助当地社区的英语和计算机技能。

  • 环境——环境和社会评估计划继续按计划进行,正如赤道本金对项目贷款融资的要求所概述的那样。

Next Steps and Planning

后续步骤和规划

The Terronera Project is on track for commissioning in Q4 2024.

Terronera项目有望在2024年第四季度投入使用。

For Q2 2024, surface construction will continue focusing on mechanical installations and initial electrical work for the crushing, coarse-ore stockpile, grinding, flotation and tailing thickener areas. Excavation of the Lower Platform is anticipated to be complete in the coming months. Concrete work is expected to be initiated for the LNG and power generation and concentrate and tailing filtration. Concentrate and tailing filtration structural, mechanical, and electrical installations will commence in early Q3.

2024年第二季度,地面施工将继续侧重于破碎、粗矿储存、研磨、浮选和尾矿增稠剂区域的机械装置和初始电气工程。下层平台的挖掘工作预计将在未来几个月内完成。预计将启动液化天然气和发电以及浓缩物和尾矿过滤的混凝土工作。浓缩物和尾矿过滤的结构、机械和电气装置将于第三季度初开始。

Mine development in Portal 1, 2 and 4 declines will continue with first ore development anticipated in Q2. Initial long-hole mining is planned for Q3 followed by cut-and-fill mining; ore will be stockpiled for mill ramp up. Development activities at La Luz are anticipated to begin in Q2 with portal construction and ramp advance to ore access anticipated in Q4. The critical path remains the TSF and lower platform construction and advancing underground mine, where development is meeting expectations.

Portal 1、2和4的矿山开发将继续下滑,预计将在第二季度进行首次矿石开发。最初的长孔开采计划于第三季度进行,随后进行挖填开采;矿石将储存起来,以备磨机扩建。La Luz的开发活动预计将于第二季度开始,预计将在第四季度建造门户并推进通往矿石通道的坡道。关键路径仍然是TSF和下层平台的建设以及地下矿山的发展,那里的开发符合预期。

Visit , our dedicated project website, to stay informed on the ongoing development at Terronera. Explore updates, learn about our commitment to environmental stewardship, and discover the positive impacts on local communities.

访问我们的专用项目网站,随时了解Terronera的持续发展。浏览最新动态,了解我们对环境管理的承诺,并发现对当地社区的积极影响。

声明:本内容仅用作提供资讯及教育之目的,不构成对任何特定投资或投资策略的推荐或认可。 更多信息
    抢沙发