Ascot Reports Second Quarter 2023 Results and Provides Construction Update on the Premier Gold Project

Ascot Reports Second Quarter 2023 Results and Provides Construction Update on the Premier Gold Project

Ascot公佈了2023年第二季度業績,並提供了Premier Gold項目的施工最新情況
GlobeNewswire ·  2023/08/14 07:00

VANCOUVER, British Columbia, Aug.  14, 2023  (GLOBE NEWSWIRE) -- Ascot Resources Ltd. (TSX: AOT; OTCQX: AOTVF) ("Ascot" or the "Company") is pleased to announce the Company's unaudited financial results for the three months and six months ended June 30, 2023 ("Q2 2023"), and also to provide a construction update on the Company's Premier Gold Project ("PGP" or the "project"), located on Nisga'a Nation Treaty Lands in the prolific Golden Triangle of northwestern British Columbia. For details of the unaudited condensed interim consolidated financial statements and Management's Discussion and Analysis for the three and six months ended June 30, 2023, please see the Company's filings at  or on SEDAR+ ().

溫哥華,不列顛哥倫比亞省,2023年8月14日-(環球通訊社)愛思高資源有限公司(TSX:AOT;OTCQX:AOTVF)(“阿斯科特“或”公司)欣然公佈本公司截至2023年6月30日止三個月及六個月的未經審計財務業績(“2023年第二季度),並提供該公司黃金專案的最新施工情況(“PGP“或”專案“),位於NIS上G《國家條約》位於不列顛哥倫比亞省西北部多產的金三角地區。關於截至2023年6月30日的三個月和六個月的未經審計簡明中期綜合財務報表和管理層的討論和分析的詳情,請參閱公司提交的檔案,網址為:或SEDAR+()。

Derek White, President and CEO, commented, "Construction activity at the Premier Gold Project continued to increase in the second quarter, with much progress being made on the critical outdoor and earthworks areas, including the tailings storage facility and new water treatment plant. As of Q2 2023, detailed engineering and major procurement are substantially complete, and project construction excluding mine development is at 48%.

總裁兼首席執行官德里克·懷特評論說,“Premier Gold Project的建築活動在第二季度繼續增加,在關鍵的戶外和土方工程領域取得了很大進展,包括尾礦儲存設施和新的水處理廠。截至2023年第二季度,詳細工程和主要採購基本完成,不包括礦山開發的專案建設佔48%。

Additionally, at the corporate level we have made steady progress on important agreements including the signing of a 3-year mining contract with Procon, the US$15 million equipment lease facility with CAT Financial, and the US$14 million convertible facility with Nebari.

此外,在公司層面,我們在重要協定上取得了穩步進展,包括與Procon簽署了為期3年的採礦合同,與CAT Financial簽署了價值1,500萬美元的設備租賃設施,與內巴裡簽署了價值1,400萬美元的可轉換設施。

The 2023 exploration program has been steadily progressing, with encouraging results encountered in both the drilling program and the IP geophysics program. We anticipate starting to release exploration results in the coming weeks as we receive them."

2023年勘探方案穩步推進,鑽井方案和IP地球物理方案都取得了令人鼓舞的成果。我們預計在收到勘探結果後,將在未來幾周內開始發佈。“

All amounts herein are reported in $000s of Canadian dollars ("C$") unless otherwise specified.

報告中的所有金額均以加元為單位(“加元“)除非另有說明,否則。

Q2 2023 AND RECENT HIGHLIGHTS

2023年第二季度和最近的亮點

  • The earthworks contract for the tailings storage facility was signed in March 2023 and the contractor was mobilized to the site in April 2023. Tailings pond de-watering was completed in June 2023 and the construction of the tailings storage facility commenced.

  • On April 20, 2023, the Company closed a previously announced non-brokered private placement (the "Offering"). The Offering raised total gross proceeds of $4,050 and consisted of 5,000,000 common shares of the Company, which qualify as "flow-through shares" within the meaning of the Income Tax Act (Canada) (the "FT Shares"), at a price of C$0.81 per FT Share. The proceeds from the Offering will be used to fund the 2023 exploration program at PGP.

  • On May 11, 2023, the Company announced the 2023 exploration program at PGP. The program consists of an initial 10,000 metres of surface drilling and will include exploration drilling for resource expansion as well as in-fill drilling of initial mining areas at the Big Missouri and Premier deposits. The exploration drilling will focus on extending the Day Zone at Big Missouri and the Sebakwe Zone north of the Premier mill. Up to an additional 4,000 meters of drilling have been budgeted and will be deployed towards surface and underground drilling depending on results of the initial 10,000 metres. The 2023 exploration program commenced on June 21, 2023.

  • On June 27, 2023, the Company closed a previously announced US$14 million subordinated convertible credit facility (the "Convertible Facility") with Nebari Gold Fund 1, LP ("Nebari"). The full proceeds from the Convertible Facility were used to repay principal, accrued interest and fees of Ascot's existing subordinated convertible credit facility with Beedie Investments Ltd. ("Beedie").

  • On July 31, 2023, the Company entered into a master lease agreement with Caterpillar Financial Services ("CAT Financial") for an equipment lease facility up to US$15 million on an uncommitted basis for surface mining equipment and construction equipment. The lease terms of the equipment are 4 to 5 years at an interest rate of the Canadian Dollar Offered Rate plus 4.25%.

  • On August 8, 2023, the Company entered into a contract with Procon Mining & Tunnelling Ltd. for underground mining services for an initial term of 3 years with option to renew for two consecutive 1-year periods.

  • 尾礦儲存設施的土方工程合同於2023年3月簽署,承包商於2023年4月被動員到現場。尾礦庫脫水於2023年6月完成,尾礦庫存儲設施開始建設。

  • 2023年4月20日,本公司完成了此前宣佈的一項非經紀私募(以下簡稱“招股”)。是次發行籌集總收益4,050美元,包括5,000,000股本公司普通股,符合《加拿大所得稅法》(加拿大)所指的“流通股”(“FT股”),每股FT股份的價格為0.81加元。此次發行所得資金將用於PGP 2023年的勘探專案。

  • 2023年5月11日,公司宣佈了2023年在PGP的勘探計劃。該計劃包括最初10,000米的地面鑽探,並將包括為擴大資源而進行的勘探鑽探,以及大密秀克裡州和Premier礦藏初始礦區的充填鑽探。勘探鑽探的重點將是擴大大密秀克裡州的Day區和Premier Mill以北的Sebakwe區。已編入多達4 000米的額外鑽探預算,並將根據最初10 000米的鑽探結果部署用於地面和地下鑽探。2023年勘探計劃於2023年6月21日開始。

  • 2023年6月27日,本公司完成了與Nebari Gold Fund 1,LP(“Nebari”)之前宣佈的1,400萬美元的附屬可轉換信貸安排(“可轉換貸款”)。可轉換貸款的全部收益用於償還Ascot與Beedie Investments Ltd.(“Beedie”)現有的附屬可轉換信貸貸款的本金、應計利息和費用。

  • 於2023年7月31日,本公司與卡特彼勒金融服務公司(“卡特彼勒金融”)訂立一項總租賃協定,就露天採礦設備及建築設備的未承諾基礎上最高達1,500萬美元的設備租賃設施。設備的租賃期限為4至5年,利率為加元報價利率加4.25%。

  • 2023年8月8日,公司與Procon礦業和隧道有限公司簽訂了一份地下采礦服務合同,初始期限為3年,並有權連續兩次續簽1年。

PROJECT CONSTRUCTION

專案建設

In January 2023, the Company closed a project financing package consisting of US$110 million as a deposit in respect of gold and silver streaming agreements (the "Stream") and a strategic equity investment (the "Strategic Investment") of C$45 million, a portion of which is structured as Canadian Development Expenditures flow through shares, such that the total gross proceeds to the Company were C$50 million. Upon securing the new project financing, Ascot re-mobilized various contractors to progress activities for the remainder of construction scope for the Project. At the start of Q2 2023, there were approximately 118 employees and contractors working at the project site, and by the end of the quarter on June 30, 2023, there were over 180 people working at site.

於2023年1月,本公司完成一項由1.1億美元作為金銀分流協定保證金(“溪流”)及4,500萬加元戰略股權投資(“戰略投資”)的專案融資方案,其中部分為加拿大發展開支流經股份的結構,使本公司的總收益為5,000萬加元。在獲得新的專案融資後,ASCOT重新動員了各種承包商,以推進專案剩餘建設範圍的活動。2023年第二季度初,約有118名員工和承包商在專案現場工作,到2023年6月30日季度末,現場工作人員超過180人。

Progress key performance indicators ("KPI") and budget
At the end of Q2 2023, overall construction excluding mine development was 48% complete, with engineering at 99% and procurement at 99%. The Project remains on schedule and budget for first gold production in the first quarter of 2024. Capital costs, including mining, incurred as of June 30, 2023 were $200 million. As of June 30, 2023, the remaining project construction capital required to complete construction and achieve the first gold pour is approximately $110 million including mining but excluding certain pre-operating costs and working capital. This is slightly higher than the most recent total project budget of $300 million to achieve first gold production reported in the Company's News Release dated December 12, 2022. The modest cost increase is attributable to a slight delay of several weeks to achieve initial gold production, which arose as the Company progressed the detailed commissioning schedule. However, the target for initial gold production in Q1 of 2024 is unchanged. The company is assessing the working capital requirements as the project progresses from commissioning to production and ramp up phases, and is evaluating various potential financing options should additional funding be required.

進展關鍵績效指標(“KPI”)和預算
於2023年第二季度末,不計礦山開發的整體建設完成48%,工程完成99%,採購完成99%。該專案仍按計劃和預算在2024年第一季度生產第一批黃金。截至2023年6月30日,包括採礦在內的資本成本為2億美元。截至2023年6月30日,完成建設和實現第一次倒金所需的剩餘專案建設資本約為1.1億美元,包括採礦,但不包括某些前期運營成本和營運資本。這略高於公司在日期為2022年12月12日的新聞稿中報道的實現首次黃金生產的最新專案預算總額3億美元。成本小幅上升是由於在本公司進行詳細的投產時間表時,實現初步黃金生產的時間略有延遲數周。然而,2024年第一季度的初始黃金產量目標沒有變化。隨著專案從投產到投產和投產階段的進展,該公司正在評估營運資金需求,並正在評估各種潛在的融資選擇,如果需要額外資金的話。

Safety
The Project continues to have an excellent safety record with 633,224 hours of work to date and zero lost time incidents. The total recordable incident frequency has been reduced from 1.28 at the end of Q1 2023, to 0.95 by the end of Q2 2023. However, with the increased activity on site and additional work areas, the number of incidents has increased including property damage, first aid injuries, and near misses. Reporting activity has been encouragingly high, and the Company will continue to work on proactive safety training and measures to reduce overall incidents at the Project site.

安全問題
該專案繼續保持著良好的安全記錄,迄今已工作633224小時,沒有發生任何損失時間事件。總的可記錄事件頻率已從2023年第一季度末的1.28次減少到2023年第二季度末的0.95次。然而,隨著現場活動的增加和更多的工作區域,事故的數量也有所增加,包括財產損失、急救受傷和險些錯過預期。報告活動一直很高,令人鼓舞,公司將繼續致力於積極主動的安全培訓和措施,以減少專案現場的總體事故。

Processing Plant
Mechanical work continued in the mill during Q2 2023; various trommels, dust collection and chute infrastructure were installed around the SAG and Ball mills. The Intensive Leach Reactor was assembled. Electricians continued installing electrical cabinetry, pulling wire, installing cable trays, and working in the mine control centre room. Piping installation at the mill is approximately 50% complete. The tailings thickener and cyanide destruction tank outside the mill was also substantially completed in the quarter. Concrete and structural steel contractors also have been restarted and their scope updated for the mill completion.

加工廠
2023年第二季度,磨機繼續進行機械工作;SAG和球磨機周圍安裝了各種滾筒、除塵和溜槽基礎設施。密集的LEACH反應堆已經組裝完畢。電工們繼續安裝電氣櫃,拉鋼絲,安裝電纜橋架,並在礦井控制中心房間工作。工廠的管道安裝大約完成了50%。該廠外的尾礦濃縮機和氰化物銷毀罐也在本季度基本完工。混凝土和結構鋼承包商也已重新啟動,其範圍也已更新,以完成磨坊。

Tailings Storage Facility ("TSF") and Cascade Creek Diversion Channel ("CCDC")
The earthworks contract for the TSF and CCDC was signed in March 2023 and the contractor was mobilized to the site in April 2023. In order to de-water the tailings facility for the required earthworks, an additional temporary water treatment plant ("WTP") was mobilized to site and commissioned in May 2023. Despite minor issues with initial ramp up, at the end of May the plant was operating at full capacity and in combination with other discharge points, the TSF was discharging near the permitted rate of 20,000 m3 per day. By the end of June 2023, dewatering was completed and the temporary WTP was demobilized. Drilling and blasting were started on the CCDC in May, with a target of one blast of 7,000 to 8,000 m3 every other day. To date, geological monitoring hasn't noted potentially acid generating ("PAG") material, and work is progressing well. Work continued at the TSF with earthworks contractors producing and placing T-zone material at the south dam, preparing the foundation at the east dam, blasting rock from the CCDC and bringing it to the crusher plant. The earthworks contractor added a night shift at the end of June to increase productivity.

尾礦儲存設施和下跌溪引水渠
TSF和CCDC的土方工程合同於2023年3月簽署,承包商於2023年4月進駐工地。為了為所需的土方工程對尾礦設施進行脫水,已調集額外的臨時水處理廠到現場,並於2023年5月投入使用。儘管最初的排汙量出現了一些小問題,但在5月底,該廠已滿負荷運行,與其他排汙點相結合,TSF的排汙量接近每天20,000立方米的許可排汙量。到2023年6月底,脫水工作完成,臨時汙水處理廠復員。今年5月,中紀委開始鑽探爆破,目標是每隔一天進行一次7000至8000立方米的爆破。到目前為止,地質監測還沒有發現潛在的產酸物質,工作進展順利。TSF的工作仍在繼續,土方承包商在南大壩生產和放置T區材料,在東大壩準備地基,從CCDC爆破岩石並將其送到破碎機廠。這家土方承包商在6月底增加了一班夜勤,以提高生產率。

Water Treatment Plant ("WTP")
Crews have also made progress on the new WTP and associated infrastructure, including the tailings thickener, lime silos, moving bed bio-reactor ("MBBR") tanks and clarifier foundation pedestals. Construction remains targeted for July and August to coincide with new WTP completion in September and subsequent commissioning.

濾水廠(“WTP”)
工作人員還在新的汙水處理廠和相關基礎設施方面取得了進展,包括尾礦濃縮機、石灰倉、移動床生物反應器(“MBBR”)池和澄清池底座。施工的目標仍然是在7月和8月,以配合9月新的WTP完工和隨後的投產。

Site Infrastructure
During Q2 2023, much work was completed on constructing the new electrical substation near the Premier mill. With the substation mostly complete, crews are now working on the 138kV power line to connect to the power grid less than 500 metres away. Crews also have been making progress on relocating the Big Missouri water pipeline from one side of the Big Missouri haul road to the other, which is expected to enhance the long-term safety and integrity of the pipeline.

站點基礎設施
在2023年第二季度,在Premier Mill附近建造新的變電站的工作已經完成。隨著變電站基本完工,工作人員現在正在138千伏的輸電線上工作,以連接到不到500米遠的電網。工作人員還在將大密秀克裡州輸水管道從大密秀克裡州運輸公路的一側搬遷到另一側的工作中取得了進展,預計這將增強管道的長期安全性和完整性。

Mine Development
After an extensive and competitive process involving six contracting companies, Ascot selected Procon Mining & Tunnelling ("Procon") for a 3-year contract to advance the underground portion of the project. Procon is headquartered in Burnaby, BC and has extensive underground mining experience in the province, including its current mining and development contract at the nearby Brucejack underground gold mine.

礦山開發
經過六家承包公司的廣泛競爭,ASCOT選擇了Procon礦業和隧道公司(“Procon”)作為一份為期3年的合同,以推進該專案的地下部分。Procon總部位於卑詩省伯納比,在該省擁有豐富的地下采礦經驗,包括其目前在附近Brucejack地下金礦的採礦和開發合同。

In 2022, work commenced on the S1 portal and approximately 907 metres of underground development was completed in the Big Missouri area before being paused for the winter. Procon will pick up from this existing development and continue the ramp and ore accesses as planned in September 2023, eventually connecting over to the Silver Coin deposit.

2022年,S1門戶開始施工,大密秀克裡地區約907米的地下開發工程在冬季暫停之前完成。Procon將從這個現有的開發專案中恢復過來,並按計劃在2023年9月繼續修建坡道和礦石通道,最終連接到銀幣礦藏。

In late summer 2023, Procon will also start a new ramp development at the Premier deposit immediately adjacent to the existing mill facilities. They will drive the initial access ramp from surface down into the Premier deposit for initial mining at the Prew zone and will eventually connect a footwall ramp over to 602 area in the Premier deposit to commence mining there.

2023年夏末,Procon還將在緊挨著現有磨坊設施的Premier礦藏開始新的坡道開發。他們將把最初的入口坡道從地表向下推入Premier礦藏,以便在Prew區進行初步開採,並最終將連接一個底部坡道至Premier礦藏的602區,在那裡開始採礦。

Recruitment
During Q2 2023, Ascot hired and onboarded a full-time recruitment professional to lead the Company's staffing efforts as it advances towards operations in 2024. Recruitment has already begun to ramp up for a number of key positions added recently, including Health, Safety, Training and Emergency Preparedness, Human Resources and Fixed Maintenance Planner.

招聘
在2023年第二季度,ASCOT聘請並聘用了一名全職招聘專業人員來領導公司在2024年開始運營時的人員配備工作。最近增加的一些關鍵職位的招聘工作已經開始加快,包括健康、安全、培訓和應急準備、人力資源和固定維護計劃員。

As recruitment efforts continue to ramp up in the coming months. The interest in Ascot is high and many good quality candidates continue to apply for open positions. Encouragingly, local interest is high, as many applications are coming from candidates in the area of Stewart and northwestern B.C.

未來幾個月,招聘工作將繼續加大力度。對阿斯科特的興趣很高,許多優秀的應聘者繼續申請空缺職位。令人鼓舞的是,當地的興趣很高,因為許多申請者來自斯圖爾特和不列顛哥倫比亞省西北部地區的候選人。

Permitting and Environmental Compliance
As a result of the project slowdown in 2022 due to the required re-financing process, a Joint Permit Amendment Application ("JPAA") will be submitted in August 2023 to change targeted conditions within the permit, mostly due to the delay of meeting the new water treatment and quality requirements from December 2022 to Q4 2023. In addition, a Mines Act Permit Amendment ("MAPA") was submitted in mid-June 2023 with respect to changing the planned location of the Premier mine portal from the southern location to an area much closer to the mill facility. All comments and information requests from the Nisga'a Lisims Government have been addressed and closed, and comments from the regulator are expected to be finalized in the coming weeks.

許可和環境合規
由於所需的再融資程式導致2022年專案放緩,將於2023年8月提交聯合許可證修訂申請(JPAA),以改變許可證中的目標條件,主要是由於滿足新的水處理和水質要求的時間從2022年12月推遲到2023年第四季度。此外,2023年6月中旬提交了一份《礦業法許可證修正案》(“MAPA”),涉及將Premier礦山門戶的規劃位置從南部改為更靠近工廠設施的區域。來自國家情報機構的所有評論和資訊請求GA‘a Lisims政府已經得到解決並關閉,監管機構的評論預計將在未來幾周內敲定。

2023 EXPLORATION PROGRAM

2023年勘探計劃

The exploration program commenced on June 21, 2023 when a drill rig was mobilized to the Prew zone of the Premier deposit. The first nine drill holes have been completed and have intercepted visual sulfide mineralization very close to expected depth and corresponding stope locations. Visible gold was intercepted in at least one of the drill holes. It appears that the location and geometry of the mineralization at the Prew is well defined and should provide a good starting point for mining operations. Four more holes are planned in this area aiming at extensions of stopes and gaps between designed stopes. On completion of the drilling at the Prew zone, the rig will move up to Big Missouri to conduct additional drilling in that area.

勘探計劃於2023年6月21日開始,當時一個鑽機被動員到Premier礦床的Prew區。前九個鑽孔已經完成,截獲了非常接近預期深度和相應採場位置的可視硫化物礦化。至少在一個鑽孔中截獲了可見的黃金。看來,Prew礦化的位置和幾何形狀已經確定,應該為採礦作業提供一個良好的起點。計劃在該地區再打四個洞,以擴大采場範圍和設計採場之間的空隙。在Prew區完成鑽探後,鑽井平臺將向上移動到大密秀克裡州,在該地區進行額外的鑽探。

The ground geophysical induced polarization ("IP") survey commenced on June 26, 2023 and is now approximately 70% complete. The crew completed two grids, one near the Premier mill targeting the western extension of the Sebakwe Zone that yielded very good exploration results last year. The grid has been designed to cover approximately 1,000 metres of strike extent to the west of the drilling in 2022. It is not known if the Sebakwe Zone extends further west and if so, where it is located in terms of northing. The mineralization at Premier shows very well in induced polarization data and preliminary results are highly anticipated.

地面地球物理激電調查於2023年6月26日開始,現已完成約70%。工作人員完成了兩個網格,其中一個位於Premier Mill附近,目標是Sebakwe區的西部延伸,去年產生了非常好的勘探結果。該網格的設計覆蓋了2022年鑽井以西約1000米的走向範圍。目前還不知道塞巴奎地區是否進一步向西延伸,如果是的話,它在北向的位置。激發極化數據很好地顯示了Premier的礦化作用,初步結果令人高度期待。

The second grid was completed around the Dilworth deposit in the northern part of the property. The geology of this area is not as well understood as Premier and Big Missouri and the exploratory induced polarization data should help with effective targeting of prospective areas. A third grid is currently being laid out at the northern extension of the Day Zone. This area has yielded very good exploration results in the last two years and mineralization remains open towards the north and south. The strike extent to the north could potentially connect the Day Zone with the Martha Ellen deposit further north. The results from the IP survey will be utilized for drill targeting in the second half of the 2023 field season.

第二個網格是圍繞著地產北部的迪爾沃斯礦藏完成的。這一地區的地質情況不如密秀克裡州首府和大密秀克裡州,探索性的激發極化數據應該有助於有效定位遠景地區。第三個網格目前正在日區的北部延伸部分鋪設。近兩年來,該地區取得了很好的勘探效果,礦化仍向南北開放。北部的罷工範圍可能會將Day Zone與更靠北的Martha Ellen礦床連接起來。IP調查的結果將用於2023年下半個野外賽季的鑽探目標。

FINANCIAL RESULTS FOR THE THREE MONTHS ENDED JUNE 30, 2023

截至2023年6月30日的三個月的財務業績

The Company reported a net loss of $3,073 for Q2 2023 compared to $1,054 for Q2 2022. The higher net loss in current quarter is driven by a $2,262 loss on extinguishment of convertible debt.

該公司報告2023年第二季度淨虧損3,073美元,而2022年第二季度淨虧損1,054美元。本季度較高的淨虧損是由可轉換債券清償造成的2262美元虧損推動的。

LIQUIDITY AND CAPITAL RESOURCES

流動資金和資本資源

As at June 30, 2023, the Company had cash & cash equivalents of $119,324 and working capital of $103,147. In H1 2023, the Company issued 120,048,007 common shares, no vested warrants, 613,334 stock options, 32,665 deferred share units, no restricted share units and no performance share units. Also, 520,250 stock options expired and 55,530 stock options, 352,006 deferred share units and 683,398 restricted share units were exercised in H1 2023.

截至2023年6月30日,公司的現金及現金等價物為119,324美元,營運資本為103,147美元。於2023年上半年,本公司發行了120,048,007股普通股、無既得認股權證、613,334份股票期權、32,665份遞延股份單位、無限制性股份單位及無履約股份單位。此外,520,250份股票期權於2023年上半年到期,55,530份股票期權、352,006份遞延股份單位及683,398份限制性股份單位於2023年上半年獲行使。

As at August 11, 2023, the Company had 555,909,153 common shares outstanding, 23,822,382 stock options, 13,710,500 vested share purchase warrants, 1,557,071 deferred share units, 3,796,930 restricted share units and 108,108 performance share units outstanding. Also, 25,767,777 unvested Prepayment Warrants issued to Nebari are outstanding.

截至2023年8月11日,公司擁有555,909,153股已發行普通股、23,822,382份股票期權、13,710,500份既有認股權證、1,557,071份遞延股份單位、3,796,930股限制性股份單位及108,108份已發行業績股份單位。此外,向內巴裡發行的25,767,777份未歸屬預付款認股權證尚未完成。

MANAGEMENT'S OUTLOOK FOR 2023

管理層對2023年的展望

With the financing package closed on January 19, 2023 and refinancing of the existing convertible debt on June 28, 2023, the Company is focusing on the completion of construction of the Project and achieving first gold production in early 2024. The key activities for remainder of 2023 include:

隨著融資方案於2023年1月19日結束,現有可轉債於2023年6月28日進行再融資,公司正專注於完成該專案的建設,並於2024年初實現首次黃金生產。2023年剩餘時間的主要活動包括:

  • Construction of the processing plant and associated surface infrastructure such that the plant is expected to be in pre-commissioning by the end of 2023

  • Completion of the tailings dam improvements and start up of the new water treatment plant by Q4 2023

  • Advancement of the Premier portal and underground development and additional underground development of the Big Missouri mine, as well as initial production stoping to provide mill feed for commissioning.

  • Maintaining a Health and Safety record of zero lost time incidents and achieving the 2023 goals outlined in the Company's 2022 Sustainability Report

  • Advancing the recruitment of site personnel in line with the site personnel plan by the end of 2023

  • Maintaining permitting and environmental compliance so that there are no delays in the project construction schedule

  • More exploration and infill drilling north and west of existing resources at the Premier Northern Light and Day zone resources areas

  • 建造加工廠和相關的地面基礎設施,以使工廠預計在2023年底前投入試運行

  • 在2023年第四季度前完成尾礦庫改善工程和新濾水廠的投產

  • 推進Premier門戶和地下開發,以及大型密秀克裡州礦山的額外地下開發,以及初步生產停產,為投產提供磨礦原料。

  • 保持零損失時間事故的健康和安全記錄,實現公司2022年可持續發展報告中概述的2023年目標

  • 按照現場人員計劃在2023年底前提前招聘現場人員

  • 維護許可和環境合規性,使專案施工進度不會出現延誤

  • 在Premier Northern Light and Day區域資源區現有資源的北部和西部進行更多勘探和加密鑽探

Qualified Person

有資格的人

John Kiernan, P.Eng., Chief Operating Officer of the Company is the Company's Qualified Person (QP) as defined by National Instrument 43-101 and has reviewed and approved the technical contents of this news release.

公司首席運營官John Kiernan,P.Eng是國家儀器43-101定義的公司合格人員(QP),並已審查和批准了本新聞稿的技術內容。

On behalf of the Board of Directors of Ascot Resources Ltd.
"Derek C. White"
President & CEO

我代表愛思高資源有限公司董事會發言。
“德里克·C·懷特”
總裁兼首席執行官

For further information contact:

如需進一步資訊,請聯繫:

David Stewart, P.Eng.
VP, Corporate Development & Shareholder Communications
dstewart@ascotgold.com
778-725-1060 ext. 1024

David·斯圖爾特,P.
企業發展和股東公關副總裁
郵箱:dstewart@ascotGold.com
778-725-1060分機1024

About Ascot Resources Ltd.

關於阿斯科特資源有限公司

Ascot is a Canadian junior exploration and development company focused on re-starting the past producing Premier gold mine, located on Nisga'a Nation Treaty Lands, in British Columbia's prolific Golden Triangle. Ascot shares trade on the TSX under the ticker AOT. Concurrent with progressing the development of Premier, the Company continues to successfully explore its properties for additional high-grade underground resources. Ascot is committed to the safe and responsible development of Premier in collaboration with Nisga'a Nation as outlined in the Benefits Agreement.

ASCOT是一家加拿大初級勘探和開發公司,專注於重新啟動位於尼斯島的Premier金礦的過去生產G一個國家條約土地,在不列顛哥倫比亞省多產的金三角。Ascot的股票在多倫多證交所交易,股票代碼為AOT。在推進Premier開發的同時,該公司繼續成功地勘探其物業,以獲得更多的高品位地下資源。ASCOT致力於與Nisga‘a Nisga Nation合作,安全和負責任地發展Premier,正如福利協定中概述的那樣。

For more information about the Company, please refer to the Company's profile on SEDAR+ at  or visit the Company's web site at , or for a virtual tour visit  under Ascot Resources.

有關公司的更多資訊,請參閱公司在SEDAR+上的簡介,或訪問公司的網站,或訪問Ascot Resources下的虛擬參觀訪問。