Procurement continues in 2022 to secure commitments for equipment pricing and delivery
VANCOUVER, British Columbia, May 16, 2022 (GLOBE NEWSWIRE) -- Sabina Gold & Silver Corp. ("Sabina") or (the "Company") (SBB – TSX/ SGSVF - OTCQX) provides an update on advancements of the Goose Mine development at the Company's 100% owned Back River Gold District in Nunavut, Canada. The Goose Mine is the Company's first mine on the 80 km long Back River Gold District, a multi-generational mining district already with a high-grade world class gold endowment.
The first quarter of 2022 culminated in one of the most important milestones for the Company to date. Debt, streaming and equity financings were completed with a total of over C$800 million arranged, well in excess of the requirements of the 2021 Updated Feasibility Study ("UFS").
More importantly, with financing in hand, pre-construction, logistical and procurement activities have accelerated. In anticipation of the financing, Sabina had prepared tender documents and purchase orders which enabled the Company to quickly procure critical components necessary for this year's sealift.
The UFS CAPEX estimate was C$610 million. Of that, approximately C$218 million was identified as direct equipment and materials purchases. Since last year, Sabina has procured, or has committed agreements to procure, just over 70% of all direct purchases identified in the UFS. Reconciliation on purchases have seen an average overall inflationary escalation of 14% since March of 2021, with a 20% escalation on the purchases made in 2022. Efforts now focus on securing the remaining 30% (C$62 million) of materials and equipment.
Earthworks at the plant site are ~67% complete, which reflects an overall Project civil works completion rate of ~40%. To date, the Project is trending an ~10% quantity reduction from UFS estimates.
"Inflation and global supply chain issues have impacted all new capital investment projects and Sabina continues to monitor these potential impacts as we develop the Goose Mine," said Bruce McLeod, President & CEO. "We are fortunate that our strategy of pre-planning and accelerating procurement efforts has reduced our exposure to inflationary impacts."
Advancement Highlights and Schedule and Cost De-risking Events
Engineering
- FLSmidth ("FLS") has been chosen to supply the key equipment for the Goose Mine processing flowsheet. The equipment package is valued at approximately US$39 million and is due to be delivered by mid-2023, for implementation ahead of the mine start-up date of Q1, 2025;
- CGT Industrial ("CGT") has provided Sabina with a fixed priced proposal of C$130 million, with an agreed rise and fall mechanism, for materials and consumables for the process plant. These components make up approximately 85% of the direct works on site. The proposal is comparable to within 5% of the feasibility study estimate;
- The team is preparing to move on to the design concept for the Echo open pit, which is intended to be pre-mined to enable initial tailings storage. The advanced mining of the Echo and Umwelt pits will also result in approximately two years of stock-piled feed for the mill prior to commencement of operations; and
- Detail engineering is reaching 85% complete project wide with remaining engineering activities focused on vendor data updates as procurement activity progresses.
Procurement
Approximately C$157 million of C$218 million (72%) of materials and equipment required for the project (per UFS) has already been procured.
Purchased or committed items include:
- 90% of mining fleet;
- Entire process plant equipment at 4000 TPD;
- Permanent accommodation complex (500 units) with kitchen and recreation center;
- 95% of building envelope steel (by weight) and cladding;
- 100% of project explosives required for construction;
- Cranes and major construction support equipment;
- 95% project cement & rebar – with concrete batch plant available on site;
- 80% of secondary structural steel for the process plant and process piping;
- 100% of all tailing, reclaim and freshwater piping for the project (~11.5Km of piping);
- All conveyor galleries and arctic corridors;
- Electrical E-houses complete with MCC and VFD (5 of 6 will be on 2022 sealift);
- Electrical switch gear for the Powerhouse;
- Water, sewer and waste systems;
- HVAC unit and Dust collections systems;
- Fuel dispensing and offloading system for Goose & Port sites;
- All equipment for double heading winter ice road construction on site;
- Fully functional aggregate crusher and washer unit on site;
- 24 MW (N+2 configuration) Power plant cogeneration system with boilers and ancillary equipment from Toromont;
- One ten-million and one five-million liter fuel storage tanks at each of Goose and Port sites, respectively; and
- Liner requirements for all water management structures procured.
Sabina has approximately C$62 million remaining to be spent on procurement (based on the UFS) which will have exposure to the current inflationary environment. These items include:
- Platework, pumps and tanks insulation -materials for which engineering is completed and quotes are being finalized;
- Electrical bulks and cable tray;
- Electrical miscellaneous equipment (process plant and powerplant);
- PLC controls systems;
- Instrumentation for the project; and
- Communication systems.
Supply chain and Sealift
Supply chain resilience will continue to require expertise, novel solutions and strong collaboration among Sabina and its suppliers. Key strategies include diversification of suppliers, monitoring production capabilities and transportation processes, as well as finding alternative materials and nontraditional partnerships. To this end, Sabina has implemented the following:
- Ensuring dedicated internal resources, including specialized expeditors, to monitor progress on fabrication of equipment procured;
- Co-ordinating with CGT during the procurement phase of all critical fabrication items to de-risk the construction schedule at site;
- Reviewing fuel supply proposals for 2022 sealift;
- Securing sealift carriers at both East and West transport/consolidation points for the 2022 sealift program; and
- Completing the installation of a fully functional hard wall camp at Port to support activities in 2022.
Although supply chain issues have impacted delivery dates, through advance planning, all major equipment required is anticipated to arrive in time for this year's sealift.
Civil Works & Logistics
Considerable pre-development activities have already been completed at the Goose and Port sites. This work includes:
- ~40% of overall project and ~67% of plant site civil works;
- Construction of two 10 million-liter fuel tanks constructed (Port and Goose);
- ~20km of all weather roads completed at Project;
- Pads complete for permanent camp, plant and fuel storage;
- Approx. 25,000m2 of additional laydown area created at the Port;
- New hard wall camp at Port and forward camps established;
- Esker harvesting and placement for sub-base prep along winter ice road route to improve future construction campaigns; and
- 700 meters of underground exploration ramp completed at Umwelt.
With surface construction season commencing, Sabina is preparing to mobilize crews to further advance civil works on site. Budgeting and scheduling is nearing completion and will be announced in the coming weeks.
Planning is well underway for the marshalling of procured equipment and supplies, at both East and West transport locations, for the 2022 sealift campaign in the late summer of this year.
SABINA GOLD & SILVER CORP
Sabina Gold & Silver Corp. is an emerging gold mining company that owns 100% of the district scale, advanced, high grade Back River Gold District in Nunavut, Canada.
Sabina filed an Updated Feasibility Study (the "UFS") on its first mine on the district, the Goose Mine, which presents a project that will produce ~223,000 ounces of gold a year (first five years average of 287,000 ounces a year with peak production of 312,000 ounces in year three) for ~15 years with a rapid payback of 2.3 years, with a post-tax IRR of ~28% and NPV5% of C$1.1B at a gold price of $1,600 USD. See "National Instrument (NI) 43-101 Technical Report – 2021 Updated Feasibility Study for the Goose Project at the Back River Gold District, Nunavut, Canada" dated March 3, 2021.
The Project has received all major permits and authorizations for construction and operations.
The Company has arranged a comprehensive project financing package comprised of:
- A US$425 million senior secured debt facility, gold prepay and stream package with Orion Mine Finance and Wheaton Precious Metals Corp.; and
- US$221 million in equity including Zhaojin's participation.
The Company is also very committed to its Inuit stakeholders, with Inuit employment and
opportunities a focus. The Company has signed a 20-year renewable land use agreement with
the Kitikmeot Inuit Association and has committed to various sustainability initiatives under the
agreement.
The Company continues to advance exploration and project optimization, including advancing the planned plant expansion to 4,000 tpd from Year two to initial startup.
All news releases and further information can be found on the Company's website at or on SEDAR at . All technical reports have been filed on
For further information please contact:
Nicole Hoeller, Vice-President, Communications: 1 888 648-4218
nhoeller@sabinagoldsilver.com
Forward Looking Information
This news release contains "forward-looking information" within the meaning of applicable securities laws (the "forward-looking statements"), including, but not limited to, statements related to the expected use of proceeds of the Offering and the projections and assumptions of the results of the UFS. These forward-looking statements are made as of the date of this news release. Readers are cautioned not to place undue reliance on forward-looking statements, as there can be no assurance that the future circumstances, outcomes or results anticipated in or implied by such forward-looking statements will occur or that plans, intentions or expectations upon which the forward-looking statements are based will occur. While we have based these forward-looking statements on our expectations about future events as at the date that such statements were prepared, the statements are not a guarantee that such future events will occur and are subject to risks, uncertainties, assumptions and other factors which could cause events or outcomes to differ materially from those expressed or implied by such forward-looking statements. Such factors and assumptions include, among others, the uncertainty of production, development plans and costs estimates for the Back River Gold Project; discrepancies between actual and estimated mineral reserves and mineral resources, between actual and estimated development and operating costs; the interpretation of drill, metallurgical testing and other exploration results; the ability of the Company to retain its key management employees and skilled and experienced personnel; exploration, development and mining risks and the inherently dangerous nature of the mining industry, and the risk of inadequate insurance or inability to obtain insurance to cover these risks and other risks and uncertainties; property and mineral title risks including defective title to mineral claims or property; the effects of general economic conditions, commodity prices, changing foreign exchange rates and actions by government and regulatory authorities; and misjudgments in the course of preparing forward-looking statements. In addition, there are known and unknown risk factors which could cause our actual results, performance or achievements to differ materially from any future results, performance or achievements expressed or implied by the forward-looking statements. Known risk factors include risks associated with exploration and project development; the need for additional financing; the calculation of mineral resources and reserves; operational risks associated with mining and mineral processing; fluctuations in metal prices; title matters; government regulation; obtaining and renewing necessary licenses and permits; environmental liability and insurance; reliance on key personnel; the potential for conflicts of interest among certain of our officers or directors; the absence of dividends; currency fluctuations; labour disputes; competition; dilution; the volatility of the our common share price and volume; future sales of shares by existing shareholders; and other risks and uncertainties, including those relating to the Back River Project and general risks associated with the mineral exploration and development industry described in our Annual Information Form, financial statements and MD&A for the fiscal period ended December 31, 2021 filed with the Canadian Securities Administrators and available at . Although we have attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. We are under no obligation to update or alter any forward-looking statements except as required under applicable securities laws.
Bruce McLeod, President & CEO
1800-555 Burrard Street, Two Bentall Centre
Vancouver, BC V7X 1M9
Tel 604 998-4175 Fax 604 998-1051
2022年には、設備の定価と交付への約束を確保するために調達を継続する
バンクーバー,ブリティッシュコロンビア州,2022年5月16日(Global Newswire)-Sabina Gold&Silver Corp.(“Sabina”)または(“Company”)(SBB-TSX/SGSVF-OTQX)は,カナダヌナブトに全資所有するBack River黄金区Goose鉱開発の最新の進展を提供している。Goose鉱は、80キロの長さの後河金鉱区にある会社の最初の鉱であり、これは多世代の鉱区であり、すでに高品位な世界的な黄金資源を持っている。
2022年第1四半期は会社のこれまでで最も重要なマイルストーンの一つだ。債務、ストリーミングメディアと株式融資はすでに完成し、手配した資金総額は8億カナダドルを超え、2021年の更新後の実行可能性研究(UFS)の要求をはるかに超えている。
さらに重要なのは、融資が手に入るにつれて、前期建設、後方勤務、調達活動が加速したことだ。融資の予想では、Sabinaは入札書類と調達注文を用意しており、会社が今年の海運に必要なキー部品を迅速に調達できるようにしている。
UFS資本支出は6.1億カナダドルと見積もられている。このうち、約2.18億カナダドルが直接設備や材料調達として決定されている。昨年以来、SabinaはUFSによって決定されたすべての直接調達の70%以上を購入または約束した。2021年3月以降、仕入残高全体のインフレは平均14%上昇し、このうち2022年の購入量は20%上昇した。現在の努力は残りの30%(6200万カナダドル)の材料と設備を確保することに重点を置いている。
工場現場の土方工事は約67%完了しており,プロジェクト全体の土建工事完成率は約40%であることが反映されている。これまで,このプロジェクトの数はUFS見積りの数より約10%減少している.
ブルース·マクラウド総裁は“インフレとグローバル·サプライチェーン問題はすべての新しい資本投資プロジェクトに影響を与えており、私たちがガチョウ鉱を開発する過程で、サビーナはこれらの潜在的な影響を監視し続ける”と述べた。“私たちの事前計画と調達作業を加速させる戦略は、インフレの影響を受けるリスクを減らすことができて幸運です”
進展点とスケジュールとコスト削減活動
工学.工学
- フォルステッド社(“FLS”)はガチョウ加工プロセスのキー設備サプライヤーに選ばれている。プラントは約3900万ドルの価値があり、2025年第1四半期の開鉱日までに実施するため、2023年年に交付される予定だ
- CGT工業会社(“CGT”)はSabinaに1.3億カナダドルの固定価格見積と、加工工場の材料や消耗品のために合意された上昇メカニズムを提供している。これらの部品は現場直接工事の約85%を占めている。実現可能性研究の概算の5%以内と比較できます
- 同チームはEcho露天鉱の設計概念を引き続き研究しようとしており、この露天鉱は予備採掘を行い、初期尾鉱貯蔵を実現することを目的としている。Echo坑とUmWelt坑の先進的な採掘は、工場の運営開始前に約2年間の堆積飼料を提供する
- 調達活動の進展に伴い,詳細工事はプロジェクト範囲の85%を達成しており,残りの工事活動はサプライヤーデータの更新に重点を置いている。
買い付ける
このプロジェクトに必要な2.18億カナダドル(72%)の材料と設備のうち,約1.57億カナダドル(UFSによる)の調達が完了している。
購入したり約束したりするものは
- 90%の採鉱船団が
- 全工場の設備生産量は4000トン/日である
- 永久宿泊総合体(500セット)、キッチンと娯楽センター付き
- 95%の建築被覆構造鋼材(重量で)および被覆;
- 100%工事に必要な工事爆薬;
- クレーンと主な施工支援装置
- セメントおよび鉄筋の95%は現場でコンクリート撹拌装置を使用することができる
- 加工工場およびプロセスパイプの80%のための第2段構造鋼;
- 100%尾鉱、再生および淡水管(管長約11.5キロ)
- 全てのベルトコンベア回廊と北極回廊
- MCCとVFDを搭載した電気E-house(6個中5個は2022年に海上輸送)
- 発電所の電気開閉装置
- 水下水道廃水システム
- 空調ユニットと除塵システムを設置し
- ガチョウと港現場の燃料分配·陸揚げシステム
- 2頭冬季氷路現場工事のすべての設備
- 現場全機能骨材破砕機及び洗浄機ユニット
- Toromontからのボイラーおよび補助装置を含む24メガワット(N+2構成)発電所コージェネレーションシステム
- GooseとPortサイトにそれぞれ1000万リットルと500万リットルの燃料貯蔵タンクを設置した
- すべての水管理構造のライナー要求を購入した。
Sabinaは、現在のインフレ環境にさらされる調達(UFSベース)のために約6200万カナダドルの残りの資金を持っている。これらのプロジェクトには
- 板材、ポンプ、およびタンク絶縁--工事が完了し、見積もりが最終的に決定されている材料
- 電気部品とケーブルブリッジ
- 電気雑設備(加工工場と発電所);
- PLC制御システム;
- このプロジェクトの機器は
- 通信システムです。
サプライチェーンと海運
サプライチェーンの弾力性は、Sabinaとそのサプライヤー間の専門知識、斬新な解決策、強力な協力を引き続き必要とするだろう。重要な戦略はサプライヤーの多様化、生産能力と輸送プロセスのモニタリング、及び代替材料と非伝統的なパートナー関係を探すことを含む。そのため、Sabinaは以下の措置を実施した
- 専門の加速員を含め、専門の内部資源を確保し、調達設備の製造進展状況を監視する
- すべての重要な製造プロジェクトの調達段階でCGTと協調して、現場施工進捗のリスクを低減する
- 2022年の海運燃料供給提案を審査します
- 2022年海上輸送計画東西輸送·集配の海運運送業者の安全を確保し、
- 2022年の活動を支援するため、港に設置機能の整ったハードウォールキャンプを完成させる。
サプライチェーン問題は交付日に影響を与えているにもかかわらず、事前計画により、必要なすべての主要設備が今年の海運に速やかに到着することが予想される。
土木と物流
GooseとPort地点ではかなり多くの開発前活動が完了している。この仕事には
- 約40%の全体工事と約67%の工場現場土建工事
- 2つの1000万リットルの燃料タンクを作ります
- プロジェクトが完了したすべての気象道路は約20キロ
- 永久キャンプ、工場、燃料貯蔵のためのマット
- おおむね25,000 m2港に追加の敷設区域を作り
- 港と前方に新しいハードウォールキャンプを設立した
- 今後の建設活動を改善するために、冬季氷路沿線の次基地準備作業を採取·配置した
- ウムヴェルトは700メートルの地下探査坂道を完成させた。
地上工事シーズンの開始に伴い,Sabinaは作業員を動員して現場の土建をさらに推進しようとしている。予算とスケジュールはもうすぐ完成され、今後数週間以内に発表されるだろう。
今年の夏末の2022年海運運動のため、東西輸送先の調達設備や用品の調達作業が順調に進められている。
サビーナ金銀会社
Sabina Gold&Silver Corp.はカナダのヌナ武地区の規模が先進的で、品位の高い後河金鉱区の100%の権益を持つ新興の金鉱会社である。
Sabinaは、この地域の最初の鉱山であるGoose鉱について最新のフィージビリティスタディ(UFS)を提出し、~15年以内に毎年約223,000オンスの金(前5年の平均年間生産量は287,000オンス、3年目のピーク生産量は312,000オンス)、急速回収期間は2.3年、税後内部収益率は~28%、NPV 5%は11億カナダドル、金価格は1,600ドルのプロジェクトを提案した。“NI 43-101技術報告-カナダヌナ武特後河金鉱区Gooseプロジェクト2021年の最新実行可能性研究”を参照し、日付は2021年3月3日である。
そのプロジェクトは建設と運営のすべての主要な許可と許可を得た。
同社は包括的なプロジェクト融資プログラムを手配している
- オリオン鉱業金融会社とウェトン貴金属会社と4.25億ドルの優先保証債務手配、金前払いと流動一括計画を達成した
- 2.21億ドルの株式は、募集の参加を含む。
会社はイヌイットの利害関係者やイヌイット人を雇うことにも取り組んでいます
チャンスがポイントです。同社は以下の会社と20年間の再生可能土地使用協定に調印した
キティクメッテ·イヌイット人協会は
合意する。
同社は計画中の工場拡張を翌年から最初に操業する1日4,000トンに早めるなど、探査とプロジェクトの最適化を進めている。
すべてのプレスリリースおよびさらなる情報は、会社のウェブサイトまたはSEDARサイトで見つけることができます。全ての技術報告書は
もっと情報を知りたいなら、連絡してください
副社長のニコール·ホラー:1 888 648-4218
メール:nhoeller@sabinagoldsilver.com
前向き情報
本プレスリリースには、証券法の適用(“前向きに陳述する)は、発行収益の予想される用途および共同財務報告結果の予測および仮定に関する陳述を含むが、これらに限定されない。このような展望的な陳述は本プレスリリースの日に行われた。展望性表現に過度に依存しないように読者を戒める。展望性表現中の期待或いは暗示の未来状況、結果或いは結果が必ず発生することを保証できないため、展望性表現が根拠とする計画、意図或いは期待が必ず発生することも保証できない。これらの展望的陳述は、私たちがこのような陳述を作成する日の未来の事件の予想に基づいているが、これらの陳述は、将来このような事件が発生することを保証しておらず、リスク、不確実性、仮説および他の要素の影響を受け、これらのリスク、不確実性、仮説および他の要素は、事件または結果をもたらす可能性があり、そのような前向き陳述の明示または暗示の内容とは大きく異なる。これらの要素と仮定には、Back River金鉱プロジェクトの生産、開発計画とコスト推定の不確定性、実際と推定された鉱物埋蔵量と鉱物資源の間の差異、実際と推定された開発と運営コストの間の差異、掘削、冶金テストとその他の探査結果の解釈、会社は肝心な管理従業員及び熟練と経験のある人員の能力を維持する;探査、開発と採鉱リスク及び採鉱業固有の危険性質、及び保険不足或いは保険を受けられない或いはこれらのリスクとその他のリスクと不確定要素をカバーするリスク;財産及び鉱業権リスク、鉱業権又は財産権の欠陥を含む;一般経済条件、商品価格の影響, 外国為替レートの変化と政府と規制機関の行動;そして展望性陳述の準備過程における誤判断。そのほか、既知と未知のリスク要素が存在し、著者らの実際の結果、業績或いは業績は展望性陳述中の明示或いは暗示の任意の未来の結果、業績或いは成果と大きく異なることを招く可能性がある。既知のリスク要因には,探査やプロジェクト開発に関連するリスク,追加融資が必要であること,鉱物資源と埋蔵量の計算,採鉱や鉱物加工に関連する経営リスク,金属価格変動,所有権問題,政府規制,必要な許可証と許可証の取得と更新,環境責任と保険,キーパーソンへの依存,いくつかの役員や役員間の潜在的な利益衝突,配当なし,通貨変動,労使紛争,競争,希釈,我々の普通株価格と取引量の変動,既存株主の将来の株売却;その他のリスクや不確実性には,Back Riverプロジェクトに関するリスクと鉱物探査·開発業界に関する一般的なリスクが含まれており,これらのリスクは,カナダ証券管理人に提出された2021年12月31日までの財政期間の年次情報テーブル,財務諸表,MD&Aに記載されており,実際の行動、イベント、または結果が前向き陳述に記載されているものとは大きく異なる可能性のある重要な要素を見つけることを試みたが、行動、イベントまたは結果が予想、推定、または予想と異なることをもたらす他の要素がある可能性がある。展望的な陳述が正確であることが証明されることは保証されない, 実際の結果と未来の事件は、このような声明で予想されているものとは大きく異なるかもしれないからだ。したがって、読者は前向きな陳述に過度に依存してはいけない。適用された証券法の要求がない限り、私たちはどんな前向きな陳述を更新したり変更したりする義務がない。
ブルース·マクラウド社長CEO
バラド街一千八百五十五番地、ベントールセンター二番地
バンクーバー、BC V 7 X 1 M 9
電話番号604 998-4175ファックス604 998-1051