TORONTO, ON / ACCESSWIRE / February 9, 2022 / Galway Metals Inc. (TSXV:GWM)(OTCQB:GAYMF) (the "Company" or "Galway") is pleased to announce new drill results and an update on its 100%-owned, approximately 20,000-hectare Estrades zinc-gold property in the Abitibi of western Quebec. Breakwater Resources Ltd. spent CDN$20 million in 1990 developing Estrades, including the installation of a 200-metre deep by 150-metre along strike decline, a ventilation raise and associated infrastructure. Production in 1990-91 totalled 174,946 tonnes grading 12.9% Zn, 6.4 g/t Au, 1.1% Cu and 172.3 g/t Ag. Breakwater closed the mine amid sharp declines in metal prices.

安大略省多伦多/ACCESSWIRE/2022年2月9日/高威金属公司(多伦多证券交易所股票代码:GWM)(OTCQB: GAYMF)(“公司” 或 “高威”)欣然宣布新的钻探结果及其位于魁北克西部阿比蒂比的约20,000公顷的100%持股的Estrades锌金矿产的最新情况。防波堤资源有限公司在1990年花费了2,000万加元开发Estrades,包括沿着罢工坡道安装深200米、150米深的隧道、通风架和相关的基础设施。1990-91年的总产量为174,946吨,品位为12.9%的锌,6.4克/吨的金,1.1%的铜和172.3克/吨的银。在金属价格急剧下跌的情况下,防波堤关闭了矿山。

Robert Hinchcliffe, President and CEO of Galway Metals, said, "Estrades has many high priority copper source vent and other VMS targets that have excellent potential to create significant value for shareholders. As such, the company has raised its rig count to three from one in order to conduct the current 25,000-meter drill program. The potential high-grade copper source vent targets are below and on the east and west sides of the Estrades resource. Other strong VMS targets exist along the Newiska horizon. Galway has begun drilling several of these targets along both the Estrades and Newiska horizons. The company also plans to continue its environmental and engineering studies, including metallurgical and ore sorting tests. As Estrades currently stands, there aren't many zinc-gold deposits with such high precious metals grades in the world - and even fewer that are as close to being shovel ready."

高威金属总裁兼首席执行官罗伯特·欣奇克利夫说, “Estrades有许多高优先级的铜源排气口和其他VMS目标,这些目标具有为股东创造巨大价值的巨大潜力。因此,该公司已将其钻机数量从一台增加到三台,以执行目前的25,000米钻探计划。潜在的高品位铜源排气目标位于Estrades资源的东侧和西侧的下方。Newiska地平线上还有其他强大的VMS目标。高威已经开始在埃斯特拉德斯和纽斯卡地平线上钻探其中几个目标。该公司还计划继续进行环境和工程研究,包括冶金和矿石分选测试。就Estrades目前的情况而言,世界上贵金属等级如此高的锌金矿床并不多,接近准备就绪的锌金矿床就更少了。”

Drilling Highlights - Metallurgical and Ore Sorting Holes

钻探亮点-冶金和矿石分拣孔

The wide, PQ-sized holes drilled for ore sorting/metallurgical testing purposes highlight near-surface results received in various zones from the middle to the western edge of the resource. Galway has previously released results from this program from the middle to the eastern edge, with highlights returning 19.8 g/t AuEq or 36.4% ZnEq over 5.65m, plus 11.6 g/t AuEq over 5.2m in hole 56, 1.6 g/t Au, 130.8 g/t Ag, 4.6% Zn, and 5.7% Cu over 1.85m in hole 49, and 22.2% ZnEq over 4.7m in hole 50. Refer to Figure 1 for details.

为矿石分选/冶金测试目的钻出的 PQ 大小的宽孔突显了从资源中部到西部边缘的各个区域获得的近地表结果。高威此前已经公布了该项目的中部到东部边缘的结果,其中565米以上的亮点回报了19.8克/吨的AuEq或36.4%的ZneQ,56号洞超过52万颗的AuEq,1.6克/吨的金,130.8克/吨的银,4.6%的锌和5.7%的铜在50号洞超过470米。有关详细信息,请参阅图 1。

  • GWM-21E-85: 28.0 g/t AuEq or 51.5% ZnEq over 5.3m (14.3 g/t Au, 192.2 g/t Ag, 18.1% Zn, 0.2% Cu, and 1.6% Pb), plus 14.0 g/t AuEq or 25.7% ZnEq over 3.85m (7.5 g/t Au, 121.7 g/t Ag, 6.6% Zn, 0.2% Cu, and 1.7% Pb), at vertical depths of 194m, and 186m below surface; both are Massive Sulphide zones, with a mine opening between
  • GWM-21E-82: 17.9 g/t AuEq or 32.9% ZnEq over 5.6m (6.9 g/t Au, 271.2 g/t Ag, 8.3% Zn, 1.3% Cu, and 0.9% Pb, plus 15.6 g/t AuEq or 28.7% ZnEq over 0.7m (4.3 g/t Au, 240.8 g/t Ag, 11.1% Zn, 0.7% Cu, and 1.3% Pb), plus 21.6% ZnEq over 1.35m (0.7 g/t Au, 92.8 g/t Ag, 16.0% Zn, and 0.6% Cu) 200m, 192m, and 228m below surface; all are Massive Sulphide zones
  • GWM-21E-84: 35.9% ZnEq over 4.3m (2.6 g/t Au, 254.5 g/t Ag, 19.3% Zn, 1.1% Cu, and 1.9% Pb) at a vertical depth of 217m below surface; this is a Massive Sulphide zone
  • GWM-21E-83A: 8.3% ZnEq over 4.3m (1.0 g/t Au, 67.4 g/t Ag, 3.4% Zn, 0.3% Cu, and 0.4% Pb), including 3.9 g/t Au, 146.9 g/t Ag, 15.4% Zn, 0.3% Cu, and 1.5% Pb over 0.7m) at a vertical depth of 217m below surface; this is a Massive Sulphide zone
  • GWM-21E-54: 15.2% ZnEq over 8.3m (1.8 g/t Au, 67.9 g/t Ag, 7.0% Zn, 0.7% Cu, and 1.1% Pb) at a vertical depth of 36m below surface; this is a Massive Sulphide zone
  • GWM-21E-85:28.0 g/t AuEq 或 51.5% ZneQ,超过 530 万克/吨(14.3 g/t Ag、18.1% 锌、0.2% 铜和 1.6% Pb),再加上垂直深度超过 385 米(7.5 g/t 金、121.7 g/t 银、6.6% 锌、0.2% 铜和 1.7% Pb)以上 14.0 g/t AuEq 或 25.7% ZnEq 194 米,地表以下 186 米;两者都是块状硫化物区域,中间有一个矿洞
  • GWM-21E-82:17.9 g/t AuEq 或 32.9% ZneQ 超过 560 万(6.9 g/t Ag、271.2 g/t Ag、8.3% Zn、1.3% Cu 和 0.9% Pb,再加上 0.7m 以上 15.6 g/t AuEq 或 28.7% ZnEq,超过 0.7% AuEq,240.8 g/t Ag,11.1% Zn,0.7% Cu 和 1.3% Pb),再加上 21.6% ZneQ 超过 1.35 米(0.7 g/t Au、92.8 g/t Ag、16.0% Zn 和 0.6% Cu),地表以下 200 米、192m 和 228 米;均为块状硫化物区域
  • GWM-21E-84:在地表以下 217m 的垂直深度超过 430 米(2.6 g/t Au、254.5 g/t Ag、19.3% Zn、1.1% Cu 和 1.9% Pb)上的 ZneQ 超过 35.9%;这是一个块状硫化物区域
  • GWM-21E-83A:在地表以下 217m 的垂直深度下,超过 430 万克的 ZnEq(1.0 g/t Ag、67.4 g/t Ag、3.4% Zn、0.3% Cu 和 0.4% Pb)以上,包括 3.9 g/t Au、146.9 g/t Ag、15.4% Zn、0.3% Cu 和 1.5% Pb(0.7m 以上)
  • GWM-21E-54:在地表以下 36m 的垂直深度下 830m(1.8 g/t Au、67.9 g/t Ag、7.0% Zn、0.7% Cu 和 1.1% Pb)超过 830m 的 ZneQ 15.2%;这是一个块状硫化物区域

Drilling Highlights - Exploration Holes

钻探亮点-勘探孔

The first bullet below is a follow-up, 80m above a gold-rich zone identified in 2018 in hole 31, which returned 26.6 g/t AuEq over 1.6m, plus 7.0 g/t AuEq over 2.1m located near the middle of the resource. The remaining exploration holes highlight new results from holes and wedges located 146m to 343m below the east side of the resource where Galway believes this copper-rich zone might lead to the discovery of a wider, high-grade source vent at depth. This area, as well as several others along both the Estrades and Newiska horizons, coincide with a strong TITAN IP/MT geophysical target.

下面的第一颗子弹是后续项目,比2018年在第31号洞发现的富金区高出80米,返回了超过160万的26.6克/吨AuEq,再加上位于资源中间的超过210米的7.0克/吨AuEq。剩余的勘探孔突显了位于资源东侧下方146米至343米的孔洞和楔子的新结果,戈尔韦认为,这个富铜区域可能会导致在深度发现更宽的高品位源喷口。该区域以及埃斯特拉德斯和纽斯卡地平线上的其他几个区域与强大的TITAN IP/MT地球物理目标相吻合。

  • GWM-21E-86: **24.0 g/t AuEq over 2.95m (22.3 grams per tonne (g/t) Au, 46.2 g/t Ag, 1.3% Zn, and 0.2% Cu), plus **16.1 g/t AuEq over 3.0m (13.9 g/t Au, 50.7 g/t Ag, 1.1% Zn, and 0.5% Cu), plus 20.8 g/t AuEq over 1.0m (18.5 g/t Au, 70.7 g/t Ag, 1.4% Zn and 0.3% Cu), at vertical depths of 377m, 401m, and 423m below surface; all 3 are Massive Sulphide zones
  • GWM-21E-60W1: 3.2% Cu, 0.8 g/t Au, 46.5 g/t Ag, and 0.7% Zn over 2.1m, plus 14.4% Zn over 0.55m, plus 1.9% Cu over 0.6m, plus 0.4% Cu, 0.2 g/t Au, 6.6 g/t Ag, and 0.4% Zn over 4.0m of massive sulphides, at vertical depths of 514m, 520m, 559m, and 530m below surface, respectively. The 3.2% Cu copper zone is 146m below the closest hole that's in the resource
  • GWM-21E-59AW4: 1.2% Cu, 0.5 g/t Au, and 6.3 g/t Ag over 7.3m, including 4.8% Cu over 0.5m and 2.7% Cu over 0.5m, and 5.3 g/t Au over 0.5m, plus 4.3% Cu, 1.1 g/t Au, and 69.0 g/t Ag over 0.6m, plus 1.4 g/t Au, 1.7% Zn, and 6.6 g/t Ag over 2.0m, at vertical depths of 625m, 579m, and 584m below surface, respectively. The 1.2% copper zone is 240m below the closest hole that's in the resource
  • GWM-21E-59AW3: 0.92% Cu, and 5.3 g/t Ag over 18.0m, including 2.1% Cu over 2.5m, at a vertical depth of 637m below surface. This copper zone is 252m below the closest hole that's in the resource
  • GWM-21E-59A: 0.7% Cu, 0.3 g/t Au, 21.5 g/t Ag, and 0.7% Zn, over 5.0m, at a vertical depth of 727m below surface. This copper zone is 343m below the closest hole that's in the resource
  • GWM-21E-86:**24.0 g/t AuEq 超过 295 米(22.3 克每吨 (g/t) Au、46.2 g/t Ag、1.3% Zn 和 0.2% Cu),再加上 3.0 米(13.9 g/t 金、50.7 g/t 银、1.1% 锌和 0.5% 铜)以上 20.8 g/t AuEq,超过 1.0 米(18.5 g/t 金、70.7 g/t Ag、1.4% Zn 和 0.3% Cu),垂直深度为地表以下 377 米、401 米和 423 米;这三个区域均为块状硫化物区域
  • GWM-21E-60W1:2.1m 以上 3.2% 铜、0.8 g/t 金、46.5 g/t Ag 和 0.7% Zn,0.5m 以上外加 14.4% 锌,0.6m 以上 1.9% 铜,0.2 g/t Au,6.6 g/t Ag 和 0.4% 的块状硫化物,垂直深度为 514m、520m、559m 和 530m 以下分别是表面。3.2% 的铜区位于资源中最近的孔洞下方 146 米
  • GWM-21E-59AW4:超过73米的铜含量为1.2%,0.5克/吨金和6.3克/吨银,包括0.5米以上为4.8%的铜和超过0.5米的2.7%的铜,0.5米以上为5.3克/吨金,0.6米以上为69.0克/吨金和69.0克/吨银,2.0米以上为1.4克/吨金,1.7%锌和6.6克/吨银,垂直深度为625米,57米分别位于地表以下 9 米和 584 米处。1.2% 的铜区位于资源中最近的孔洞下方 240 米
  • GWM-21E-59AW3:在地表以下垂直深度为637米处,铜含量为0.92%,超过180米处的银含量为5.3克/吨,其中2.5米以上铜含量为2.1%。该铜区位于资源中最近的孔洞下方252米处
  • GWM-21E-59A:0.7% 铜、0.3 g/t 金、21.5 g/t Ag 和 0.7% Zn,超过 5.0 米,垂直深度为地表以下 727 米。该铜区位于资源中最近的孔洞下方343米处

** previously released. For equivalence calculations, refer to the notes under Table 1. Equivalents are provided when the underlying Au and/or Zn metal content is above 25% of the intersect value.

** 之前发布的。有关等效性计算,请参阅表 1 下的注释。当底层金和/或锌金属含量高于相交值的25%时,将提供等效物。

Engineering of Estrades is Progressing, Along With the Company's ESG Efforts

Estrades的工程设计正在取得进展,公司的ESG工作也在进行中

Galway has contracted the services of Peter Gula, P. Eng. to oversee all engineering and processing test work for the Estrades Project. Peter brings 30+ years of mining experience to the Galway team in both operations and management.

高威已与工程师彼得·古拉签订了服务合同,负责监督Estrades项目的所有工程和加工测试工作。Peter 在运营和管理方面为高威团队带来了 30 多年的采矿经验。

  • Galway is evaluating alternative variations of long hole mining methods that could be applied to potentially reduce development and operating costs, materially improving project economics. Estrades has good continuity vertically and horizontally (sheet of mineralization). It is vertical, and at near 90 degrees dip is ideal for long-hole mining methods.
  • Galway is dedicated to reducing the mine's environmental footprint; custom milling options are being explored. This would eliminate the need to construct a mill and tailings facility, reduce site power requirements, streamline the permitting process and lead times to restart production.
  • Galway has commenced initial test work for the application of Ore Sorting Technology to reject waste rock dilution. If successful, this process will reduce transportation and mill costs as well as decrease the volume of tailings being created, thus reducing the overall environmental footprint.
  • In addition to ore sorting, Galway has completed the drilling of large PQ-size core across the different metal zones for metallurgical test work to be conducted later this year. Estrades was an operating mine with concentrates produced via toll milling at Matagami, located 128 km by road to the east. Recovery rates using conventional methods of crushing, grinding, gravity, flotation and cyanidization were 93% Zn, 90% Cu, 86% Pb, 78% Au and 63% Ag. After milling was completed, Breakwater transported the concentrates 290 km south to Rouyn-Noranda for smelting. Galway will attempt to improve on these results during this year's metallurgical testing program.
  • Galway will conduct geochemistry testing on waste rock after the drilling campaign.
  • Galway will conduct line cutting and subsequent geophysics this winter for expanded target generation as follow-up to anomalies defined in a previous FALCON gravity survey by CGG Canada Services Ltd., and as follow-up to a TITAN24 survey by Quantec Geoscience - primarily along the current Estrades resource, along extensions east and west of the resource, and along the Newiska horizon to find VMS vent areas.
  • 高威正在评估长孔开采方法的替代变体,这些方法可用于潜在地降低开发和运营成本,从而显著改善项目经济性。Estrades 在垂直和水平方向上具有良好的连续性(矿化层)。它是垂直的,倾角接近 90 度,是长孔采矿方法的理想选择。
  • 高威致力于减少矿山的环境足迹;正在探索定制铣削选项。这将消除建造磨机和尾矿设施的需要,减少场地电力需求,简化许可流程和重启生产的交货时间。
  • 高威已经开始了应用矿石分选技术来拒绝废石稀释的初步测试工作。如果成功,该过程将降低运输和磨机成本,并减少产生的尾矿量,从而减少总体环境足迹。
  • 除了矿石分拣外,Galway还完成了跨不同金属区的大型PQ尺寸岩心钻探,将于今年晚些时候进行冶金测试工作。埃斯特拉德斯是一座正在运营的矿山,其精矿是通过收费铣削生产的,位于向东128公里处的马塔加米公路上。使用传统的破碎、研磨、重力、浮选和氰化方法的回收率为93%的锌,90%的铜,86%的铅,78%的金和63%的银。研磨完成后,防波堤将精矿向南运送了290公里处的鲁安-诺兰达进行熔炼。高威将在今年的冶金测试计划中努力改善这些结果。
  • 钻探活动结束后,高威将对废岩进行地球化学测试。
  • 戈尔韦将在今年冬天进行线路切割和随后的地球物理学研究,以扩大目标生成,以此作为对CGG加拿大服务有限公司先前FALCON重力调查中定义的异常的后续行动,以及Quantec Geoscience进行的 TITAN24 调查的后续行动——主要沿着当前的埃斯特拉德资源、该资源的东部和西部的延伸部分以及沿着纽斯卡地平线寻找VMS通风区。

Galway has contracted an environmental consultant to oversee and further flora/fauna studies, water sampling, and native consultations; Gail Amyot, Eng. has extensive experience regarding environmental affairs and community relations with the mining industry in Quebec and elsewhere in the world.

Galway已与一名环境顾问签约,负责监督和进一步开展动植物研究、水质采样和本地咨询;Gail Amyot,Eng. 在环境事务以及与魁北克和世界其他地方采矿业的社区关系方面拥有丰富的经验。

  • Galway has initiated the baseline data collection with surface water sampling
  • Galway has installed foundations of a relationship with the Pikogan community by giving work mandates to a local enterprise.
  • 高威已开始通过地表水采样收集基准数据
  • 高威通过向当地企业提供工作授权,为与皮科根社区的关系奠定了基础。

Drill Results Summary

钻探结果摘要

Holes were drilled for ore sorting and metallurgical test work into 4 areas of the 1.6 km long deposit. Holes 82 and 85 are located directly below the workings (where the ramp was intersected in hole 85). 28.0 g/t AuEq or 51.5% ZnEq over 5.3m, and 14.0 g/t AuEq or 25.7% ZnEq over 3.85m were intersected on both sides of the mine opening, and 17.9 g/t AuEq or 32.9% ZnEq over 5.6m was intersected just east of that. Holes 83A and 84 are located in the vicinity of previously-reported hole 57 that returned 35.1 g/t AuEq or 64.5% ZnEq over 2.7m (10.7 g/t Au, 423 g/t Ag, 22.8% Zn, 2.8% Cu, and 2.6% Pb). Holes 83A and 84 returned 4.3m of 8.3% ZnEq and 35.9% ZnEq, respectively. Previously-reported metallurgical/ore sorting results in two other zones - located in the central and eastern areas of the deposit - include 19.8 g/t AuEq or 36.4% ZnEq over 5.65m (5.2 g/t Au, 176.2 g/t Ag, 19.6% Zn, 1.9% Pb, and 0.3% Cu), plus 11.6 g/t AuEq over 5.2m (8.5 g/t Au, 57 g/t Ag, and 4.2% Zn) in hole 56, 1.6 g/t Au, 130.8 g/t Ag, 4.6% Zn, and 5.7% Cu over 1.85m in hole 49, and 22.2% ZnEq over 4.7m (1.8 g/t Au, 81.8 g/t Ag, 10.3% Zn, 2.0% Cu, and 0.4% Pb) in hole 50. A new metallurgical/ore sorting result from hole 54 returned 15.2% ZnEq over 8.3m.

在 1.6 千米长的矿床的 4 个区域钻了孔,用于矿石分选和冶金测试工作。82 号和 85 号洞位于矿井正下方(坡道在 85 号洞相交的地方)。超过 5.3 米的 28.0 g/t auEq 或 51.5% 的 zneQ,超过 3.85 米的 14.0 g/t auEq 或 25.7% 的 ZneQ 相交于矿洞两侧,17.9 g/t auEq 或 32.9% 的 ZneQ 超过 56m 就在那以东。83A和84号孔位于先前报告的57号孔附近,该洞在27米以上(10.7克/吨金、423克/吨银、22.8%锌、2.8%铜和2.6%铅)返回了35.1克/吨的AuEq或64.5%的ZnEq。83A和84号洞的回报率分别为8.3%的ZneQ和35.9%的ZneQ的430万英镑。此前报告的另外两个区域(位于矿床的中部和东部地区)的冶金/矿石分选结果包括超过565米(5.2克/吨金、176.2克/吨银、19.6%的锌、1.9%的铅和0.3%的铜)的19.6克/吨AuEq或超过52万克的11.6克/吨AuEq或36.4% 56 号孔 4.2% 的锌),1.6 g/t Au,130.8 g/t Ag,4.6% Zn,4.6% 在 49 号洞 185 米处有 5.7% 的铜,超过 47m(1.8 g/t Au、81.8 g/t Ag、10.3% Zn、2.0% Cu 和 0.4% Pb)的 ZneQ(1.8 g/t Ag、10.3% Zn、2.0% Cu 和 0.4% Pb)。来自54号孔的新冶金/矿石分选结果返回了超过830万英镑的15.2%的ZneQ。

Exploration drill hole 86 was drilled to follow-up a strong intersect drilled in 2018 - hole 31, which was the deepest intersect in the middle of the deposit and returned 26.6 g/t AuEq over 1.6m (21.9 g/t Au + 113.1 g/t Ag + 5.6% Zn), plus 7.0 g/t AuEq over 2.1m (4.3 g/t Au Au + 154.8 g/t Ag + 0.9% Zn). Hole 86 was drilled in a gap located 80m above hole 31, and intersected 3 massive sulphide horizons, returning 24.0 g/t AuEq over 2.95m, plus 16.1 g/t AuEq over 3.0m, plus 20.8 g/t AuEq over 1.0m.

86号勘探钻孔是为了跟进2018年钻探的强劲交叉点——第31号洞,这是矿床中间最深的交叉点,在1.6米(21.9克/吨金 + 113.1 克/吨银 + 5.6% 锌)上返回了26.6克/吨的AuEq,超过2.1米(4.3克/吨金 + 154.8 g/t Ag + 0.9% Zn)。86号洞是在第31号孔上方80米处的缝隙中钻出的,与3个块状硫化物地平线相交,在2.95米处返回24.0 g/t AuEq,在3.0米处返回16.1 g/t AuEq,在1.0米处返回20.8 g/t AuEq。

Drill holes and wedges 59A, 59AW3, 59AW4, and 60W1 host intersections of copper over good widths located in the copper-rich eastern portion of the deposit. Previous Galway drilling returned grades up to 7.4% Cu over 1.9m at -309m vertical in hole 5, and the deepest hole at -392m returned 9.3% Cu over 0.9m. The new holes/wedges returned wide zones of up to 18.0m (0.9% Cu), and grades to 4.8% Cu over 0.5m. Previous results returned copper stringer zones to 9.0m wide and with grades up to 5.2% Cu over 0.5m, within 1.9% Cu over 3.75m in wedge hole 59AW1, and 4.1 g/t AuEq over 9.05m (1.2 g/t Au, 11.9 g/t Ag, 1.0% Zn, and 1.3% Cu) from hole 60A. All these are located 146m to 343m below the deepest resource hole that returned 9.3% Cu over 0.9m as noted above.

钻孔和楔子 59A、59AW3、59AW4 和 60W1 位于矿床富含铜的东部,在宽度上有铜的交叉点。此前的高威钻探在5号井的垂直度为-309米处的19米处返回了高达7.4%的铜品位,而在-3.92米处的最深孔在0.9米处返回了9.3%的铜。新的钻孔/楔形钻孔返回的宽区域可达180米(0.9%铜),超过0.5米的铜等级为4.8%。先前的结果显示,铜纵梁区域的宽度为9.0米,0.5米以上的铜品位高达5.2%,楔形孔 59AW1 中的铜品位在3.75米以内,在3.75米以内,铜含量在1.9%以内,从60A孔(1.2克/吨金,11.9克/吨银,1.0%锌和1.3%铜)以上。所有这些都位于最深的资源孔下方146米至343米处,如上所述,该资源孔在0.9米处返回了9.3%的铜。

Galway's 2022 Drill Program at Estrades Has Many VMS and Copper Source Targets

高威在埃斯特拉德斯实施的2022年钻探计划有许多VMS和铜源目标

  1. 24m of massive sulphides with zinc grades as high as 11.4% (hole 64A - 16.1m true width; see photos; on the copper-rich eastern portion of the Estrades resource area. At 1km vertical, hole 64A represents the deepest intersection drilled on the property in its history. At 16.1m true width, this intersection is far wider than the typical 1-7 metre width of the resource. This hole targeted a strong TITAN anomaly (IP/MT), which may indicate the presence of a nearby source vent. Massive sulphides tend to widen in proximity to source vents. Drilling will target where it is open below, west, and east.
  2. New hole 86 intersected 3 massive sulphide horizons, with two previously-reported returning 24.0 g/t AuEq over 2.95m (22.3 g/t Au, 46.2 g/t Ag, 1.3% Zn, and 0.2% Cu), plus 16.1 g/t AuEq over 3.0m (13.9 g/t Au, 50.7 g/t Ag, 1.1% Zn, and 0.5% Cu), plus the third just received returning 20.8 g/t AuEq over 1.0m (18.5 g/t Au, 70.7 g/t Ag, 1.4% Zn, and 0.3% Cu). Drilling will target where it is open below.
  3. Previous Galway discovery in a zinc-rich area east of the cross fault will target extensions to strong massive sulphides intersected in holes 27, 57 and 48. Hole 27 returned 39.1% ZnEq over 3.3m (28.5% Zn, 2.2 g/t Au, 181.0 g/t Ag, 0.3% Cu, and 0.9% Pb) (2.1m TW), plus 26.2% ZnEq over 2.6m (18.6% Zn, 0.3 g/t Au, 190.7 g/t Ag, 0.5% Cu, and 0.5% Pb) (1.7m TW) that is open below; The intersections in holes 57 and 48 are the upper-most holes and open to surface. Hole 57 returned 35.1 g/t AuEq or 64.5% ZnEq over 2.7m (10.7 g/t Au, 473 g/t Ag, 22.8% Zn, 2.8% Cu, and 2.6% Pb) and hole 48 intersected 7.1m grading 14.3 g/t AuEq or 26.3% ZnEq (4.3 g/t Au, 155.2 g/t Ag, 11.0% Zn, 0.8% Cu, and 0.9% Pb). Drilling will target areas where it is open below and above.
  4. A copper-rich area, located approximately 400m east of and above the 24m of massive sulphides encountered in hole 64A in search of vent sources: Galway will target extensions to 5.1% Cu and 62.0 g/t Ag over 1.65m (1.2m TW), including 12.9% Cu and 159.0 g/t Ag over 0.55m (0.4m TW), and7.4% Cu over 1.9m. These intersections overlie recently-reported copper stringer zones in hole 59AW1 that are up to 9.0m wide and with grades up to 5.2% Cu over 0.5m; drilling will target where it is open below.
  5. A copper-rich area in search of vent sources: Galway will target extensions to 1.7% Cu over 8.9m in the far west side of the resource, below the bottom of the resource and mine ramp.
  6. A zinc-rich deep target (TITAN targets identified by geophysics):10.8% ZnEq over 17.7m (4.2% Zn, 1.1 g/t Au, 95.2 g/t Ag, 0.6% Cu, and 0.3% Pb), including 22.3% ZnEq over 4.5m (9.7% Zn, 1.7 g/t Au, 190.9 g/t Ag, 1.3% Cu, and 0.5% Pb), and 15.2% ZnEq over 2.0m (8.3% Zn, 1.0 g/t Au, 147.6 g/t Ag, 0.2% Cu, and 0.6% Pb) (unknown TW); drilling will target where it is open below.
  7. The Newiska VMS horizon to the south (Au-Ag-Zn-Cu-Pb), home to the former producing Telbel gold mine (1.1 million ounces at 6.6 g/t Au in 5.2 million tonnes), and the former producing Joutel and Poirier VMS mines, all located approximately 20 km to the east (Figure 2): Galway will target extensive copper stringer zones over 132m (Figure 3). This area also hosts 1.1% Cu over 9.4m including 2.0% Cu over 1.5m, 1.2% Cu over 7.1m including 4.1% Cu over 0.6m, 2.1% Cu, 6.7% Zn, and 145 g/t Ag over 0.6m, 0.5% Cu over 22.0m including 4.2% Cu over 0.7m, and 1.6% Cu and 1.9 g/t Au over 1.0m. These intersections are located above, east, and west of strong conductors delineated from TITAN geophysics with co-incident gravity high anomalies in the host rhyolite. Rhyolites typically have a gravity low signature; the gravity high indicates the presence of massive sulphides.
  8. The Newiska VMS horizon, south of the Estrades mine along the Newiska horizon will be targeted to follow up on a TITAN conductor (Figure 4). Previous Galway drilling intersected 3.1m of massive sulphide (all pyrite) within rhyolite (host of VMS deposits at Estrades and elsewhere in the area). Massive pyrite is present above some VMS deposits; Galway plans to drill deeper, below the pyrite. Also in this western area of the Newiska horizon, Galway plans on following up on 5 historic drill holes that returned up to 4.7% Cu over 0.6m (these 5 holes returned individual narrow intervals of 1.7% Cu, 1.8% Cu, 2.0% Cu, 3.0% Cu, and 4.7% Cu).
  1. 24m 块状硫化物,锌品位高达 11.4%(孔洞真实宽度为 16.1m;见照片;位于埃斯特拉德资源区的东部)。64A 号钻孔垂直 1 千米,是该物业历史上钻探的最深十字路口。该交叉点的实际宽度为 16.1 米,远远超过资源的典型宽度 1-7 米。该洞的目标是强烈的泰坦异常(IP/MT),这可能表明附近存在源喷口。块状硫化物往往会在源头喷口附近扩大。钻探将瞄准下方、西部和东部的空地处。
  2. 新的 86 号洞穿过 3 个块状硫化物地平层,先前报告的两个回收量超过 2.95 米(22.3 g/t Au、46.2 g/t Ag、1.3% Zn 和 0.2% Cu),外加超过 3.0 米(13.9 g/t Au、50.7 g/t Ag、1.1% Zn 和 0.5% Cu)返回 16.1 g/t AuEq(13.9 g/t Au、50.7 g/t Ag、1.1% Zn 和 0.5% Cu)20.8 g/t AuEq 超过 1.0 米(18.5 g/t Au、70.7 g/t Ag、1.4% Zn 和 0.3% Cu)。钻探将瞄准下方空旷的地方。
  3. 戈尔韦先前在交叉断层以东富锌区域的发现将瞄准与27、57和48洞相交的强块状硫化物的延伸。27号洞(28.5% 锌、2.2 g/t Au、181.0 g/t Ag、0.3% Cu 和 0.9% Pb)(210万吨重量)(210万吨重量)上方回报了 39.1% 的ZnEq(18.6% 锌、0.3 g/t Au、190.7 g/t Ag、0.5% Cu 和 0.5% Pb)(170万吨重量)(170万吨重量),下方开启的交叉点在57号和48号洞中是最上方的洞,并且是向表面开放的。第 57 洞返回了 35.1 g/t auEq 或 64.5% 的 zneQ 超过 270 米(10.7 g/t Ag、22.8% Zn、2.8% Cu 和 2.6% Pb),48 洞相交 71m,品位为 14.3 g/t AuEq 或 26.3% ZneQ(4.3 g/t Au、155.2 g/t Ag、11.0% Zn、0.8% Cu 和 0.9% Pb)b)。钻探将瞄准下方和上方空旷的区域。
  4. 一个富含铜的区域,位于64A号孔中为寻找喷口源而遇到的块状硫化物的24米处和上方约400米处:戈尔韦的目标是延伸至超过165米(120万总重量)的5.1%铜和62.0克/吨银,包括超过0.55米(0.4万总重量)的12.9%的铜和159.0克/吨的银,超过190万吨的铜和7.4%的铜。这些交叉点覆盖了最近报告的 59AW1 孔中的铜纵梁区域,该区域的宽度可达 9.0 米,0.5 米以上的铜品位高达 5.2%;钻探将瞄准下方的空地带。
  5. 一个富含铜的区域寻找喷口源:高威的目标是将资源最西端、资源底部和矿山坡道底部以下 1.7% 的铜含量延伸至890万以上。
  6. 富含锌的深层目标(地球物理学确定的 TITAN 目标):超过 177m 的 ZnEq 10.8%(4.2% Zn、1.1 g/t Au、95.2 g/t Ag、0.6% Cu 和 0.3% Pb),包括超过 45m 的 22.3% 的 ZnEq(9.7% 锌、1.7 g/t Ag、1.3% Cu 和 0.5% Pb),以及 15.2% 的ZneQ q超过200米(8.3%的锌,1.0克/吨的金,147.6克/吨的银,0.2%的铜和0.6%的铅)(未知的重量);钻探的目标是下方空旷的地方。
  7. 位于南部的Newiska VMS地平线(Au-Ag-Zn-Cu-Pb)是以前生产的特尔贝尔金矿(按520万吨计算,金含量为110万盎司,重量为6.6克/吨)以及前生产的Joutel和Poirier VMS矿的所在地,均位于向东约20公里处(图2):高威将瞄准132米以上的大片铜矿区(图3)。该区域还含有超过940万吨的1.1%的铜,超过150万的铜含量为2.0%,超过710万的铜含量为1.2%,超过60万的铜含量为4.1%,超过60万的铜含量为6.7%,超过0.6万克的145克铜含量超过220万克的0.5%,超过1.0米的1.6%的铜和1.9克/吨的金。这些交叉点位于泰坦地球物理学中描绘的强导体的上方、东部和西部,宿主流纹岩中同时出现了重力高异常。流纹岩通常具有低重力特征;重力高表示存在块状硫化物。
  8. 位于埃斯特拉德斯矿以南沿纽斯卡地平线的Newiska VMS地平线将作为后续跟踪泰坦导体的目标(图4)。之前的戈尔韦钻探在流纹岩(Estrades和该地区其他地方的VMS矿床)内横穿了3.1米的块状硫化物(全部为黄铁矿)。一些VMS矿床上方存在大量黄铁矿;高威计划在黄铁矿下方钻得更深。同样在纽斯卡地平线的西部区域,高威计划对5个历史钻孔进行后续研究,这些钻孔在0.6米以上的回收率高达4.7%(这5个钻孔返回的铜含量很小,分别为1.7%、铜1.8%、铜2.0%、铜3.0%和铜4.7%)。

Estrades Resources

Estrades 资源

An NI 43-101 Technical Report on the "Mineral Resource Estimate for the Estrades Project, Northwestern Quebec, Canada" dated November 5, 2018, with an amended date of March 15, 2019, was prepared by Roscoe Postle Associates (RPA). Full details are available on the Company's website at or SEDAR profile at . From gold and zinc equivalent perspectives, the Estrades mine contains:

Roscoe Postle Associates(RPA)于2018年11月5日编写了NI 43-101关于 “加拿大魁北克省西北部埃斯特拉德斯项目的矿产资源估算” 的技术报告,修订日期为2019年3月15日。完整的详细信息可在公司的网站上或SEDAR的个人资料中找到。从黄金和锌当量的角度来看,埃斯特拉德斯矿包含:

Zinc Equivalent

锌当量

  • Indicated Resources of 1.5 mm tonnes, hosting 685 million ZnEq lb grading 20.8%, plus
  • Inferred Resources of 2.2 mm tonnes, hosting 656 million ZnEq lb grading 13.5%
  • 指示资源为 150 万吨,容纳 6.85 亿个 ZneQ 磅,品位为 20.8%,外加
  • 推断资源为 220 万吨,容纳 6.56 亿 ZneQ 磅,品位为 13.5%

Gold Equivalent

黄金等价物

  • Indicated Resources of 1.5 mm tonnes, hosting 543,051 AuEq oz at 11.3 g/t AuEq, plus
  • Inferred Resources of 2.2 mm tonnes, hosting 520,430 AuEq oz at 7.4 g/t AuEq
  • 指示资源为 150 万吨,容纳 543,051 盎司 aUeQ,每吨 11.3 g/t auEq,外加
  • 推断资源为 220 万吨,容纳 520,430 auEq 盎司,每吨 7.4 g/t auEq

Notes:

注意事项:

  1. CIM definitions were followed for Mineral Resources.
  2. No Mineral Reserves are present.
  3. All metal prices, the US$/CDN$ exchange rate and cut-off grade were provided by RPA.
  4. Mineral Resources are estimated at long-term metal prices (USD) as follows: Zn $1.15/lb, Cu $3.50/lb, Pb $1.00/lb, Au $1,450/oz, and
    Ag $21.00/oz.
  5. Mineral Resources are estimated using an average long-term foreign exchange rate of US$0.80 per CDN$1.00.
  6. Mineral Resources are estimated at a cut-off grade of CDN$140/tonne NSR, which included provisions for metallurgical recoveries, freight, mining, milling, refining and G&A costs, smelter payables for each metal and applicable royalty payments.
  7. A minimum mining width of approximately 1.5 m was used.
  8. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
  9. Numbers may not add due to rounding.
  1. 矿产资源遵循了 CIM 的定义。
  2. 没有矿产储量。
  3. 所有金属价格、美元/加元汇率和截止等级均由RPA提供。
  4. 矿产资源按长期金属价格(美元)估算如下:锌1.15美元/磅,铜3.50美元/磅,铅1.00美元/磅,澳元1,450美元/盎司,以及
    价格为21.00美元/盎司。
  5. 矿产资源的估算采用的平均长期外汇汇率为每1.00加元0.80美元。
  6. 据估计,矿产资源的截止等级为140加元/吨NSR,其中包括冶金回收、运费、采矿、研磨、炼油和并购成本、每种金属的冶炼厂应付账款和适用的特许权使用费。
  7. 使用了大约 1.5 米的最小采矿宽度。
  8. 不是矿产储量的矿产资源没有表现出经济可行性。
  9. 由于四舍五入,数字可能无法相加。

Table 1: Drill Result Highlights

表 1:钻探结果亮点

Hole ID

From

(m)

To

(m)

Intercept

(m)

TW

(m)

Au Eq*

(g/t)

Zn Eq*

(%)

Au

(g/t)

Ag

(g/t)

Zn

(%)

Cu

(%)

Pb

(%)

Type**

GWM-21E-86

311.70

314.30

2.60

1.20

0.2

18.6

1.2

DSS

343.00

343.75

0.75

0.30

0.2

1.5

DSS

392.80

395.80

3.00

1.30

16.1

13.9

50.7

1.1

0.5

MSS

incl.

393.30

393.80

0.50

0.20

45.5

43.1

87.5

0.55

MSS

395.80

397.30

1.50

0.70

0.7

16.7

0.2

0.3

DSS

408.50

419.40

10.90

4.90

1.3

6.1

0.8

DSS

419.40

422.35

2.95

1.30

24.0

22.3

46.2

1.3

0.2

MSS

443.40

444.40

1.00

0.50

20.8

18.5

70.7

1.4

0.3

MSS

GWM-21E-60W1

541.60

544.80

3.20

1.70

0.7

35.9

0.7

2.4

DSS

incl.

542.70

544.80

2.10

1.10

0.8

46.5

0.8

3.2

DSS

548.30

548.80

0.50

0.30

0.1

4.8

1.9

0.5

DSS

549.25

549.80

0.55

0.30

15.5

0.4

4.1

14.4

0.1

DSS

560.10

564.10

4.00

2.30

0.2

6.6

0.4

0.4

MSS

590.65

591.25

0.60

0.30

0.1

4.0

1.9

DSS

GWM-21E-59AW4

597.20

597.80

0.60

0.40

1.1

69

0.6

4.3

DSS

599.70

600.70

0.60

0.40

1.35

9.4

2.6

0.3

0.3

DSS

603.00

605.00

2.00

1.20

1.44

6.6

1.7

DSS

incl.

603.00

604.00

1.00

0.60

1.33

6.6

2.6

0.2

DSS

620.00

635.00

15.00

8.80

0.5

8.2

1.1

DSS

incl.

634.00

635.00

1.00

0.60

5.2

DSS

635.00

636.00

1.00

0.60

0.9

DSS

638.00

639.00

1.00

0.60

0.5

DSS

640.70

641.40

0.70

0.40

1.2

DSS

642.90

643.70

0.80

0.50

1.7

DSS

645.20

652.50

7.30

4.60

0.5

6.3

1.2

DSS

incl.

645.70

646.20

0.50

0.30

5.3

2.3

incl.

649.20

649.70

0.50

0.30

0.5

20.9

2.7

DSS

incl.

652.00

652.50

0.50

0.30

0.2

16.6

4.8

DSS

GWM-21E-59A

750.00

755.00

5.00

2.50

0.3

21.5

0.7

0.7

DSS

755.00

763.00

8.00

4.00

0.2

13.2

0.44

DSS

GWM-21E-85

192.10

195.95

3.85

1.80

14.0

25.7

7.5

121.7

6.6

0.2

1.7

MSS

200.00

205.30

5.30

2.50

28.0

51.5

14.3

192.2

18.1

0.2

1.6

MSS

GWM-21E-82

199.50

200.20

0.70

0.30

15.6

28.7

4.3

240.8

11.1

0.74

1.3

DSS

208.00

213.55

5.55

2.60

17.9

32.9

6.9

271.2

8.3

1.3

0.9

MSS

237.90

239.25

1.35

0.60

21.6

0.7

92.8

16.0

0.6

DSS

GWM-21E-84

310.50

314.80

4.30

3.60

35.9

2.6

254.5

19.3

1.1

1.9

MSS

GWM-21E-83A

268.40

272.70

4.30

3.10

8.3

1

67.4

3.4

0.3

0.4

MSS

incl

269.50

270.20

0.70

0.50

15.6

28.8

3.93

146.9

15.4

0.3

1.5

MSS

GWM-20E-56

89.00

93.50

4.50

2.80

0.61

12.5

1.9

0.4

DSS

GWM-21E-54

51.00

59.30

8.30

6.10

15.2

1.8

67.9

7.0

0.7

1.1

MSS

60.70

61.20

0.50

0.40

21.3

11.6

65.7

0.2

5.2

0.1

MSS

61.70

62.30

0.50

0.40

1.7

18.0

1.6

MSS

71.00

73.00

2.00

1.50

23.0

3.8

0.3

DSS

GWM-21E-59AW3

657.00

675.00

18.00

11.30

0.9

DSS

incl

664.50

667.00

2.50

1.60

2.1

DSS

洞 ID

来自

(m)

(m)

拦截

(m)

TW

(m)

Au Eq*

(g/t)

锌方程*

(%)

Au

(g/t)

Ag

(g/t)

(%)

(%)

Pb

(%)

类型**

GWM-21E-86

311.70

314.30

2.60

1.20

0.2

18.6

1.2

DSS

343.00

343.75

0.75

0.30

0.2

1.5

DSS

392.80

395.80

3.00

1.30

16.1

13.9

50.7

1.1

0.5

MSS

包括。

393.30

393.80

0.50

0.20

45.5

43.1

87.5

0.55

MSS

395.80

397.30

1.50

0.70

0.7

16.7

0.2

0.3

DSS

408.50

419.40

10.90

4.90

1.3

6.1

0.8

DSS

419.40

422.35

2.95

1.30

24.0

22.3

46.2

1.3

0.2

MSS

443.40

444.40

1.00

0.50

20.8

18.5

70.7

1.4

0.3

MSS

GWM-21E-60W1

541.60

544.80

3.20

1.70

0.7

35.9

0.7

2.4

DSS

包括。

542.70

544.80

2.10

1.10

0.8

46.5

0.8

3.2

DSS

548.30

548.80

0.50

0.30

0.1

4.8

1.9

0.5

DSS

549.25

549.80

0.55

0.30

15.5

0.4

4.1

14.4

0.1

DSS

560.10

564.10

4.00

2.30

0.2

6.6

0.4

0.4

MSS

590.65

591.25

0.60

0.30

0.1

4.0

1.9

DSS

GWM-21E-59AW4

597.20

597.80

0.60

0.40

1.1

69

0.6

4.3

DSS

599.70

600.70

0.60

0.40

1.35

9.4

2.6

0.3

0.3

DSS

603.00

605.00

2.00

1.20

1.44

6.6

1.7

DSS

包括。

603.00

604.00

1.00

0.60

1.33

6.6

2.6

0.2

DSS

620.00

635.00

15.00

8.80

0.5

8.2

1.1

DSS

包括。

634.00

635.00

1.00

0.60

5.2

DSS

635.00

636.00

1.00

0.60

0.9

DSS

638.00

639.00

1.00

0.60

0.5

DSS

640.70

641.40

0.70

0.40

1.2

DSS

642.90

643.70

0.80

0.50

1.7

DSS

645.20

652.50

7.30

4.60

0.5

6.3

1.2

DSS

包括。

645.70

646.20

0.50

0.30

5.3

2.3

包括。

649.20

649.70

0.50

0.30

0.5

20.9

2.7

DSS

包括。

652.00

652.50

0.50

0.30

0.2

16.6

4.8

DSS

GWM-21E-59A

750.00

755.00

5.00

2.50

0.3

21.5

0.7

0.7

DSS

755.00

763.00

8.00

4.00

0.2

13.2

0.44

DSS

GWM-21E-85

192.10

195.95

3.85

1.80

14.0

25.7

7.5

121.7

6.6

0.2

1.7

MSS

200.00

205.30

5.30

2.50

28.0

51.5

14.3

192.2

18.1

0.2

1.6

MSS

GWM-21E-82

199.50

200.20

0.70

0.30

15.6

28.7

4.3

240.8

11.1

0.74

1.3

DSS

208.00

213.55

5.55

2.60

17.9

32.9

6.9

271.2

8.3

1.3

0.9

MSS

237.90

239.25

1.35

0.60

21.6

0.7

92.8

16.0

0.6

DSS

GWM-21E-84

310.50

314.80

4.30

3.60

35.9

2.6

254.5

19.3

1.1

1.9

MSS

GWM-21E-83A

268.40

272.70

4.30

3.10

8.3

1

67.4

3.4

0.3

0.4

MSS

包含

269.50

270.20

0.70

0.50

15.6

28.8

3.93

146.9

15.4

0.3

1.5

MSS

GWM-20E-56

89.00

93.50

4.50

2.80

0.61

12.5

1.9

0.4

DSS

GWM-21E-54

51.00

59.30

8.30

6.10

15.2

1.8

67.9

7.0

0.7

1.1

MSS

60.70

61.20

0.50

0.40

21.3

11.6

65.7

0.2

5.2

0.1

MSS

61.70

62.30

0.50

0.40

1.7

18.0

1.6

MSS

71.00

73.00

2.00

1.50

23.0

3.8

0.3

DSS

GWM-21E-59AW3

657.00

675.00

18.00

11.30

0.9

DSS

包含

664.50

667.00

2.50

1.60

2.1

DSS

Notes:

注意事项:

* Au (Eq g/t) and Zn (Eq %) represent the in-situ metal content expressed as Au and Zn equivalents.

* 金(Eq g/t)和锌(Eq%)代表以金和锌当量表示的原位金属含量。

** previously-released

** 之前发布的

Equivalents are not provided when the underlying Au and/or Zn metal content is below 25% of the intersect value.

当底层金和/或锌金属含量低于相交值的25%时,不提供等效物。

Preliminary analysis indicates that no metal is dominant; however, Au and Zn are the largest contributors to the Estrades resource.

初步分析表明,没有金属占主导地位;但是,金和锌是Estrades资源的最大贡献者。

Equivalencies are calculated using the following metal prices (US$) and exchange rate (US$/C$) provided by RPA:

等值使用RPA提供的以下金属价格(美元)和汇率(美元/加元)计算:

Au $1,450/oz, Ag $21.00/oz, Zn $1.15/lb, Cu $3.50/lb, Pb $1.00/lb, US$0.80/C$1.00.

澳元1,450美元/盎司,银21.00美元/盎司,锌1.15美元/磅,铜3.50美元/磅,铅1.00美元/磅,0.80美元/加元。

MSS = massive sulphide, SMS = semi-massive sulphide DSS = disseminated and stringer sulphides.

MSS = 块状硫化物,SMS = 半块状硫化物 DSS = 浸染硫化物和串烧硫化物。

Holes were not drilled in sequential numerical order.

钻孔不是按顺序排列的。

If true width (TW) is not specified, the orientation of the zone is unknown at this time.

如果未指定真宽度 (TW),则此时区域的方向未知。

Estrades, Newiska, and Casa Berardi Geology and Mineralization

Estrades、Newiska 和 Casa Berardi 的地质和矿化

Information on Geology and Mineralization can be found on the Estrades project page of our website at along with a complete Table of Drill Results released to date.

有关地质和矿化的信息可以在我们网站的Estrades项目页面上找到,以及迄今为止发布的完整钻探结果表。

Review by Qualified Person, Quality Control and Reports

合格人员审查、质量控制和报告

In compliance with National Instrument 43-101, Mr. Kamil Khobzi, P.Eng., is the Qualified Person responsible for the accuracy of this news release. Mr Reno Pressacco, P. Geo., is the Qualified Person responsible for preparation and disclosure of the Estrades Mineral Resource estimate, and is independent of Galway. The drill core is sawn in half with one half of the core sample shipped to Swastika Laboratories situated in Swastika, ON, which has accreditation of ISO/IEC 17025. The other half of the core is retained for future assay verification. Other QA/QC measures includes the insertion of certified reference standards (gold and polymetallics) and blanks into the sample stream, and the regular re-assaying of pulps and rejects at alternate certified labs. Gold analysis is conducted by fire assay using atomic absorption or gravimetric finish for samples greater than 10 g/t gold. Other Metals (Ag, Cu, Pb, Zn, Co, As) have full acid digestion and analyzed by AAS; with over limits (5000 ppm) analyzed by AAS using method dilutions, and the Silver (Ag) over limits (200 ppm) analyzed by fire assay (FA) & gravimetric finish. The laboratory re-assays at least 10% of all samples and additional checks may be run on anomalous values.

根据国家仪器43-101的规定,工程师Kamil Khobzi先生是负责本新闻稿准确性的合格人员。P. Geo. Reno Pressacco先生是负责编制和披露Estrades矿产资源估算的合格人士,独立于高威。钻芯被锯成两半,岩心样本的一半运往位于安大略省斯瓦斯蒂卡的Swastika实验室,该实验室获得了ISO/IEC 17025的认证。核心的另一半将保留以备将来的化验验证。其他质量保证/质量控制措施包括在样品流中插入经认证的参考标准(金和多金属)和空白,以及定期在其他认证实验室对纸浆和废弃物进行重新检测。对于金含量大于 10 g/t 的样品,金分析采用原子吸收或重量法进行火法分析。其他金属(Ag、Cu、Pb、Zn、Co、As)经过充分的酸消化并通过 AAS 进行分析;AAS 使用方法稀释分析超限(5000 ppm),而银(Ag)超限值(200 ppm)则通过火法试验(FA)和重量法完成分析。实验室重新分析所有样本的至少 10%,并可能对异常值进行额外检查。

Table 2: Drill Hole Coordinates

表 2:钻孔坐标

Hole ID

Azimuth

Dip

Northing

Easting

Hole Length (m)

GWM-21E-86

170

-73

5494903

654770

499.2

GWM21E-60W1

286

-75

5494893

655773

339.0

GWM21E-59AW4

280

-80

5494894.9

655762.5

381

GWM21E -59A

280

-80

5494894.9

655762.5

882

GWM21E -85

171

-75

5494931

654127

207

GWM21E -82

171

-75

5494931

654127

261

GWM21E -84

179

-55

5495041

654559.9

225

GWM21E -83A

179

-54

5495041

654559.9

300

GWM20E -56

186

-62

5494904

654882.5

219

GWM20E -54

150

-54

5494899

654882.5

100.5

GWM21E -59AW3

280

-80

5494894.9

655762.5

384

洞 ID

方位角

北方

向东

孔长 (m)

GWM-21E-86

170

-73

5494903

654770

499.2

GWM21E-60W1

286

-75

5494893

655773

339.0

GWM21E-59AW4

280

-80

5494894.9

655762.5

381

GWM21E -59A

280

-80

5494894.9

655762.5

882

GWM21E -85

171

-75

5494931

654127

207

GWM21E -82

171

-75

5494931

654127

261

GWM21E -84

179

-55

5495041

654559.9

225

GWM21E -83A

179

-54

5495041

654559.9

300

GWM20E -56

186

-62

5494904

654882.5

219

GWM20E -54

150

-54

5494899

654882.5

100.5

GWM21E -59AW3

280

-80

5494894.9

655762.5

384

Figure 1 - Estrades Long Section

图 1-Estrades 长截面

Figure 2 - Estrades Plan Map

图 2-Estrades 平面图

Figure 3 - Newiska Titan Anomaly

图 3-Newiska Titan 异常

Figure 4 - Estrades South Titan Anomaly (on Newiska Horizon)

图 4-Estrades South Titan 异常(在 Newiska Horizon 上)

About the Company

关于本公司

Galway Metals is well capitalized with two projects in Canada: Clarence Stream, an emerging gold district in New Brunswick, and Estrades, the former producing, high-grade VMS mine in Quebec. The Company began trading on January 4, 2013, after its successful spinout to existing shareholders from Galway Resources following the completion of the US$340 million sale of that company. With substantially the same management team and Board of Directors, Galway Metals is keenly intent on creating similar value as it had with Galway Resources.

高威金属拥有充足的资金,在加拿大有两个项目:新不伦瑞克省新兴的金矿区克拉伦斯溪和位于魁北克的前高品位VMS矿Estrades。该公司在完成对高威资源3.4亿美元的出售后,成功从高威资源分拆给现有股东,于2013年1月4日开始交易。由于管理团队和董事会基本相同,Galway Metals热切希望创造与高威资源相似的价值。

Should you have any questions and for further information, please contact (toll free):

如果您有任何疑问或想了解更多信息,请联系(免费电话):

Galway Metals Inc.
Robert Hinchcliffe
President & Chief Executive Officer
1-800-771-0680
Website:
Email: info@galwaymetalsinc.com
Look us up on Facebook, Twitter or LinkedIn

高威金属公司
罗伯特·欣奇克利夫
总裁兼首席执行官
1-800-771-0680
网站:
电子邮件:info@galwaymetalsinc.com
在脸书、推特或领英上关注我们

CAUTIONARY STATEMENT: Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy of this news release. No stock exchange, securities commission or other regulatory authority has approved or disapproved the information contained herein.

警示声明:多伦多证券交易所风险交易所及其监管服务提供商(该术语在多伦多证券交易所风险交易所的政策中定义)均不对本新闻稿的充分性承担责任。证券交易所、证券委员会或其他监管机构均未批准或不批准此处包含的信息。

This news release contains forward-looking information, which is not comprised of historical facts. Forward-looking information involves risks, uncertainties and other factors that could cause actual events, results, performance, prospects and opportunities to differ materially from those expressed or implied by such forward-looking information. Forward-looking information in this news release includes statements made herein with respect to, among other things, the Company's objectives, goals or future plans, potential corporate and/or property acquisitions, exploration results, potential mineralization, exploration and mine development plans, timing of the commencement of operations, and estimates of market conditions. Factors that could cause actual results to differ materially from such forward-looking information include, but are not limited to, exploration results being less favourable than anticipated, capital and operating costs varying significantly from estimates, delays in obtaining or failures to obtain required governmental, environmental or other project approvals, political risks, uncertainties relating to the availability and costs of financing needed in the future, changes in equity markets, inflation, changes in exchange rates, fluctuations in commodity prices, delays in the development of projects, risks associated with the defence of legal proceedings and other risks involved in the mineral exploration and development industry, as well as those risks set out in the Company's public disclosure documents filed on SEDAR. Although the Company believes that management's assumptions used to develop the forward-looking information in this news release are reasonable, including that, among other things, the Company will be able to identify and execute on opportunities to acquire mineral properties, exploration results will be consistent with management's expectations, financing will be available to the Company on favourable terms when required, commodity prices and foreign exchange rates will remain relatively stable, and the Company will be successful in the outcome of legal proceedings, undue reliance should not be placed on such information, which only applies as of the date of this news release, and no assurance can be given that such events will occur in the disclosed time frames or at all. The Company disclaims any intention or obligation to update or revise any forward-looking information contained herein, whether as a result of new information, future events or otherwise, except as required by applicable securities laws.

本新闻稿包含前瞻性信息,这些信息不包含历史事实。前瞻性信息涉及风险、不确定性和其他因素,这些因素可能导致实际事件、结果、业绩、前景和机会与此类前瞻性信息所表达或暗示的存在重大差异。本新闻稿中的前瞻性信息包括此处就公司的目标、目标或未来计划、潜在的公司和/或财产收购、勘探结果、潜在的矿化、勘探和矿山开发计划、开始运营的时间以及市场状况估计等内容所做的陈述。可能导致实际结果与此类前瞻性信息存在重大差异的因素包括但不限于勘探结果不如预期、资本和运营成本与估计值相差很大、延迟获得或未能获得所需的政府、环境或其他项目批准、政治风险、与未来所需融资的可用性和成本相关的不确定性、股票市场的变化、通货膨胀、汇率变化、大宗商品价格的波动,项目开发的延迟、与法律诉讼辩护相关的风险以及矿产勘探和开发行业涉及的其他风险,以及公司在SEDAR上提交的公开披露文件中列出的风险。尽管公司认为管理层用于开发本新闻稿中前瞻性信息的假设是合理的,包括除其他外,公司将能够发现并抓住收购矿产的机会,但勘探结果将符合管理层的预期,公司将在需要时以优惠条件获得融资,大宗商品价格和外汇汇率将保持相对稳定,公司将成功获得法律结果诉讼,不应过分依赖此类信息,这些信息仅适用于本新闻稿发布之日,并且无法保证此类事件将在披露的时间范围内发生,或者根本无法保证。除非适用的证券法另有要求,否则公司不打算或没有义务更新或修改此处包含的任何前瞻性信息,无论是由于新信息、未来事件还是其他原因。

SOURCE: Galway Metals Inc.

来源:高威金属公司


View source version on accesswire.com:
在 accesswire.com 上查看源代码版本:

声明:本内容仅用作提供资讯及教育之目的,不构成对任何特定投资或投资策略的推荐或认可。 更多信息
    抢沙发