Dominion Energy Achieves Another Major Milestone for Coastal Virginia Offshore Wind With Installation of the First Monopile Foundation

Dominion Energy Achieves Another Major Milestone for Coastal Virginia Offshore Wind With Installation of the First Monopile Foundation

Dominion Energy通过安装第一个单桩基金会,实现了弗吉尼亚沿海海上风电的又一个重要里程碑
道明尼资源 ·  05/22 00:00
  • Coastal Virginia Offshore Wind (CVOW) remains on budget and on schedule with construction expected to conclude in late 2026
  • DEME Group's heavy lift vessel, the Orion, erects the first of 176 monopile foundations
  • Coastal Virginia Offshore Wind (CVOW)仍然按预算和时间表进行建设,预计于2026年底竣工。
  • DEME集团的重型起重船Orion竖立了第1根176个单桩基础。

RICHMOND, Va., May 22, 2024 /PRNewswire/ -- Dominion Energy announced today the first monopile foundation for the 2.6-gigawatt Coastal Virginia Offshore Wind (CVOW), the largest offshore wind farm under construction in the United States, was installed approximately 29 miles off the Virginia Beach coast. The monopile was installed by the Orion, DEME Group's heavy lift vessel.

弗吉尼亚州里士满,2024年5月22日 / - Dominion Energy今天宣布,2.6吉瓦的Coastal Virginia Offshore Wind (CVOW)的第一个单桩基础已经安装在距离弗吉尼亚海滩约29英里的地方,它是美国正在建设的最大离岸风电场。单桩基础是由Orion起重船安装的,它是DEME集团的重型起重船。PRNewswire尽管重型起重船Orion有很多优势,但它也有一些缺点。Orion,DEME集团的重型起重船。

Once complete in late 2026, CVOW will consist of 176 turbines that will generate enough clean, renewable energy to power up to 660,000 homes and is expected to generate fuel savings of $3 billion for customers during the first 10 years of operation.

一旦在2026年底完工,CVOW将有176个涡轮机,可以产生足够的清洁可再生能源,以为多达660,000个家庭供电,并预计在运营的前10年为客户产生30亿美元的燃料节省。

"This is a monumental day for the Coastal Virginia Offshore Wind team, who have worked tirelessly to keep this project on budget and on schedule to provide our customers with reliable, affordable and increasingly clean energy," said Robert M. Blue, Dominion Energy's chair, president and chief executive officer. "We are taking extensive precautions to ensure this project is fully protective of the environment and to protect marine species."

“对于一直努力保持此项目按预算和时间表进行的Coastal Virginia Offshore Wind团队来说,这是一个具有里程碑意义的日子,以为我们的客户提供可靠,实惠和越来越清洁的能源,” Dominion Energy的主席,总裁兼首席执行官Robert M. Blue说。“我们正在采取全面的预防措施,以确保这个项目完全保护环境并保护海洋物种。”

"We are proud to partner with Dominion Energy on this landmark project," said Bill White, President DEME Offshore US. "DEME's Orion vessel, equipped with industry-leading Vibro Hammer technology, is uniquely designed to efficiently install CVOW's massive monopiles, all weighing over 1,000 tons. Our talented project team will include skilled American union pile drivers, creating a robust and prepared workforce. We look forward to working with our consortium partner Prysmian to help deliver Virginia-made energy to the Commonwealth.

“我们很自豪能够与Dominion Energy合作进行这个标志性的项目,”DEME Offshore US总裁Bill White说。“DEME的Orion船配备了具有行业领先的振动锤技术,独特地设计为有效地安装CVOW的大型单桩基础,所有单桩基础重量均超过1,000吨。我们才华横溢的项目团队将包括技术娴熟的美国工会打桩手,创建一个强大而有准备的工作力量。我们期待与我们的联合体合作伙伴普瑞斯米恩,帮助向科莫威尔斯创造的能源。

The monopile foundations, which are being staged at Portsmouth Marine Terminal, are single vertical, steel cylinders manufactured by global leader EEW SPC and are being installed into the sea floor to support the wind turbine generators. Consistent with the project construction schedule, Dominion Energy will continue to install monopiles through the fall of 2024 and resume installations in May 2025.

单桩基础正在Portsmouth Marine Terminal进行分段,是由全球领先的EEW SPC制造的单个垂直钢筒,安装在海床上,以支撑风力涡轮机组。根据项目建设时间表,Dominion Energy将继续通过2024年秋季安装单桩基础,并于2025年5月恢复安装。

To be protective of the endangered North Atlantic right whale, no monopiles will be installed between November 1 and April 30, the time that the whales are expected to be migrating past the project area. Additional measures to protect whales and other aquatic life include the use of bubble curtains – perforated hoses that have air pumped through them – to create a wall of bubbles around the monopiles during installation to reduce soundwaves underwater. Vessels will also be staffed by Protected Species Observers and will adhere to speed restrictions to avoid collisions with protected species.

为了保护濒危的北大西洋露脊鲸,不会在11月1日至4月30日的时间安装单桩基础,这是鲸鱼预计会迁徙过项目区域的时间。为了保护鲸鱼和其他水生生物,还采取了其他措施,包括使用气泡帘 - 穿孔的软管,将空气泵入其中 - 在安装过程中在单桩基础周围产生一堵气泡墙以减少水下声波。船只也将配备受保护物种观察员,并遵守速度限制,以避免与受保护物种发生碰撞。

Offshore wind's economic development and jobs benefits are transformative for Hampton Roads and the Commonwealth. More than 800 Virginia-based workers – nearly 670 in the Hampton Roads region – have been engaged on the CVOW project or with other businesses supporting CVOW. This work includes redevelopment activities at the Portsmouth Marine Terminal, construction of the offshore wind Monitoring and Coordination Center, maritime provisioning, ship upkeep, heavy lift and rigging, cyber security, food service and hospitality. More than 1,000 local jobs will be needed to support ongoing operations and maintenance of this facility after the project begins commercial operation.

离岸风电的经济发展和就业利益对于汉普顿路和联邦有所裨益。在CVOW项目或支持CVOW的其他企业上,已经有超过800名基于弗吉尼亚的工人 - 接近于汉普顿道路地区的670名 - 参与了这项工作。这项工作包括端口口岸的重新开发活动,离岸风电监测和配合中心的建设,海上补给,船只维护,重型起重和索具,网络安全,餐饮服务和酒店业。在项目开始商业运营后,还需要超过1,000个当地工作来支持持续的操作和维护。

About Dominion Energy
About 6 million customers in 15 states energize their homes and businesses with electricity or natural gas from Dominion Energy (NYSE: D), headquartered in Richmond, Va. The company is committed to providing reliable, affordable, and increasingly clean energy every day and to achieving Net Zero emissions by 2050. Please visit DominionEnergy.com to learn more.

SOURCE Dominion Energy