Silver Tiger Provides Update on Progress of Pre-Feasibility Study

Silver Tiger Provides Update on Progress of Pre-Feasibility Study

Silver Tiger 提供預可行性研究的最新進展情況
Accesswire ·  02/22 07:00

HALIFAX, NS / ACCESSWIRE / February 22, 2024 / Silver Tiger Metals Inc. (TSXV:SLVR)(OTCQX:SLVTF) ("Silver Tiger" or the "Company") is pleased to provide an update on the Company's ongoing Pre-feasibility Study ("PFS") drilling program on the Stockwork gold deposit on its El Tigre Project in Sonora, Mexico. The Company continues to advance and de-risk the Stockwork Deposit. A 25,000 metre drilling program focused on Mineral Resource expansion and classification, metallurgical and geotechnical as it progresses from an exploration to a development project. The value-added PFS progresses on schedule for publication in H2-2024.

新澤西州哈利法克斯/ACCESSWIRE/2024年2月22日/銀虎金屬公司(多倫多證券交易所股票代碼:SLVR)(OTCQX: SLVTF)(“Silver Tiger” 或 “公司”)很高興提供該公司正在進行的墨西哥索諾拉El Tigre項目Stockwork金礦牀預可行性研究(“PFS”)鑽探計劃的最新情況。公司繼續推進股票存款並降低其風險。一項長達 25,000 米的鑽探計劃側重於礦產資源的擴張和分類、冶金和岩土工程,以及從勘探項目向開發項目的進展。增值的 PFS 正在按計劃進行,將在 H2-2024 中發佈。

Goals of the PFS drilling programs are to:

PFS 鑽探計劃的目標是:

a) de-risk the project with enhanced metallurgical and geotechnical review;
b) increase confidence of the Mineral Resource with in-fill drilling in the near-surface 'Starter Pit'; and
c) expand the known Mineral Resource through targeted drilling.
a) 通過加強冶金和岩土工程審查來降低項目風險;
b) 通過在近地表 “Starter Pit” 進行填埋鑽探,增強對礦產資源的信心;以及
c) 通過有針對性的鑽探擴大已知的礦產資源。

During the PEA review, it was observed that three main areas of the Stockwork mineralization lacked adequate drilling and had potential for expansion: a) the footwall, b) the hanging wall and c) bottom 'keel'. Now, after releasing the first 15 drill holes of the program, the Company is pleased to announce conversion, expansion and de-risking of the potential 'Starter Pit'.

在PEA審查期間,觀察到Stockwork礦化的三個主要區域缺乏足夠的鑽探,並且有擴張的潛力:a) 腳下,b) 懸掛牆和 c) 底部 “龍骨”。現在,在發佈該項目的前15個鑽孔之後,該公司很高興地宣佈對潛在的 “Starter Pit” 進行改造、擴建並降低風險。

Silver Tiger's CEO, Glenn Jessome, stated, "We are excited to announce that initial results are both confirming and expanding the near-surface potential 'Starter Pit'. These promising assay results help to further de-risk the project in conjunction with the underway PFS-level geotechnical and metallurgical studies." Mr. Jessome further stated, "We also continue the work to deliver a PEA for the permitted underground MRE during H2-2024."

銀虎首席執行官格倫·傑索姆表示:“我們很高興地宣佈,初步結果既證實了又擴大了近地表潛力的'Starter Pit'。這些令人鼓舞的化驗結果與正在進行的PFS級岩土工程和冶金研究相結合,有助於進一步降低該項目的風險。”傑索姆進一步表示:“在 H2-2024 期間,我們還繼續努力爲允許的地下地下地下地下地下危險地雷提供預先許可協議。”

Near-surface, Stockwork Zone, seen in below highlighted intercepts:

近地表庫存區域,見下方突出顯示的截距:

  • Drill hole ET-23-479: 54.0 metres grading 0.85 g/t gold equivalent or 63.7 g/t silver equivalent or from 22.0 metres to 76.0 metres, consisting of 10.1 g/t silver and 0.71 g/t gold and 53.5 metres grading 110.0 g/t 1.47 g/t gold equivalent or silver equivalent from 96.5 metres to 150.0 metres consisting of 19.5 g/t silver and 1.21 g/t gold including 22.1 metres grading 2.06 g/t gold equivalent or 154.4 g/t silver equivalent from 97.9 metres to 120.0 metres consisting of 5.9 g/t silver and 1.98 g/t gold in the Stockwork Zone;
  • Drill hole ET-23-486: 79.0 metres grading 0.86 g/t gold equivalent or 64.5 g/t silver equivalent from 104.0 metres to 183.0 metres, consisting of 31.3 g/t silver and 0.44 g/t gold including 26.0 metres grading 1.60 g/t gold equivalent or 119.7 g/t silver equivalent from 158.0 metres to 184.0 metres consisting of 85.2 g/t silver and 0.46 g/t gold in the Stockwork Zone;
  • Drill hole ET-23-489: 89.5 metres grading 0.89 g/t gold equivalent or 67.1 g/t silver equivalent from 101.0 metres to 190.5 metres, consisting of 22.3 g/t silver and 0.60 g/t gold including 10.0 metres grading 1.50 g/t gold equivalent or 112.6 g/t silver equivalent from 110.0 metres to 120.0 metres consisting of 4.1 g/t silver and 1.45 g/t gold in the Stockwork Zone; and
  • Drill hole ET-23-494: 78.1 metres grading 0.75 g/t gold equivalent or 56.5 g/t silver equivalent from 0.0 metres to 78.1 metres, consisting of 22.9 g/t silver and 0.45 g/t gold including 15.3 metres grading 0.93 g/t gold equivalent or 70.1 g/t silver equivalent from 3.0 metres to 18.3 metres consisting of 28.1 g/t silver and 0.56 g/t gold in the Stockwork Zone.
  • ET-23-479 鑽孔:54.0 米,品位爲 0.85 g/t 黃金當量或 63.7 g/t 銀當量或從 22.0 米到 76.0 米,包括 10.1 g/t 銀和 0.71 g/t 金,品位爲 110.0 g/t 1.47 g/t 金當量的 53.5 米,從 96.5 米到 150.0 米的銀當量包括 19.5 g/t 的銀當量和 1.21 g/t 的金,包括品位爲 2.06 g/t 金當量的 22.1 米或從97.9米到120.0米的154.4克/噸白銀當量,包括庫存區的5.9克/噸白銀和1.98克/噸的黃金;
  • ET-23-486 鑽孔:從 104.0 米到 183.0 米的 79.0 米品位爲 0.86 克/噸的黃金當量或 64.5 克/噸的銀當量,包括 31.3 克/噸的銀和 0.44 克/噸的金,包括 26.0 米品位爲 1.60 克/噸金當量或從 158.0 米到 184.0 米的 119.7 克/噸銀當量,包括 85.2 克/噸的白銀和庫存區的 0.46 克/噸黃金;
  • ET-23-489 鑽孔:從 101.0 米到 190.5 米的 89.5 米品位爲 0.89 克/噸黃金當量或 67.1 克/噸白銀當量,包括 22.3 克/噸的銀和 0.60 克/噸的金,包括 10.0 米品位爲 1.50 克/噸金當量或從 110.0 米到 120.0 米的 112.6 克/噸銀當量,包括 4.1 克/噸的白銀和 1.45 克/噸的黃金;以及
  • ET-23-494 鑽孔:從 0.0 米到 78.1 米的 78.1 米品位爲 0.75 克/噸的黃金當量或 56.5 克/噸的銀當量,包括 22.9 克/噸的銀和 0.45 克/噸的黃金,包括 15.3 米品位爲 0.93 克/噸金當量或從 3.0 米到 18.3 米的 70.1 克/噸銀當量,包括 28.1 克/噸的銀當量和 0.56 克/噸的黃金。

Figure 1 : Stockwork Zone - Plan View

圖 1:庫存區域-平面圖視圖

Figure 2: Stockwork Zone-Cross Section 4100N

圖 2:庫存區橫截面 4100N

Highlights from the on-going Pre-feasibility Study Drilling Program include the following:

正在進行的預可行性研究鑽探計劃的亮點包括以下內容:

  • Expanding known mineralization by 10-15%; to the footwall and hanging wall zones, as well as the higher-grade 'keel' at PEA pit bottom associated with the El Tigre and SK Veins;
  • Converting first three years of material in the potential 'Starter Pit' from Indicated Mineral Resource to Measured;
  • Converting a significant portion of the 2km strike length 'ultimate' PEA pit-constrained Inferred Resource to Indicated;
  • Completion of enhanced PFS Metallurgical Drilling, with samples underway comminution and leach testing; and
  • Completion of enhanced PFS Geotechnical Drilling, with samples undergoing testing.
  • 將已知的礦化範圍擴大 10-15%;延伸到腳下和懸壁區,以及與 El Tigre 和 SK 礦脈相關的 PEA 礦坑底部更高品位的 “龍骨”;
  • 將潛在的 “初始礦井” 中的前三年材料從指定礦產資源轉換爲實測資源;
  • 將受礦坑限制的 2 千米攻擊長度 “極限” PEA 礦坑限制的推斷資源中的很大一部分轉換爲指示資源;
  • 完成增強型 PFS 冶金鑽探,樣品正在進行粉碎和滲濾測試;以及
  • 完成增強型 PFS 岩土工程鑽探,樣品正在測試中。

Mineral Resource Drilling

礦產資源鑽探

P&E Mining Consultants ("P&E") of Brampton, Ontario completed the intial MRE in 2017. In late 2023, P&E released an the updated El Tigre Project MRE with a pit-constrained Indicated Mineral Resource totaling 43.0 million tonnes containing 818 thousand ounces AuEq grading 0.59 g/t AuEq; and a pit-constrained Inferred Mineral Resource of 11.5 million tonnes containing 267 thousand ounces AuEq grading 0.72 g/t AuEq (see update MRE press release dated September 12th 2023).

安大略省布蘭普頓的P&E礦業顧問(“P&E”)於2017年完成了最初的MRE。2023 年底,P&E 發佈了更新後的 El Tigre 項目 MRE,其礦坑受限的指示礦產資源總量爲 4,300 萬噸,含有 81.8 萬盎司 AuEQ 品位爲 0.59 g/t auEQ;礦坑受限的推斷礦產資源爲 1150 萬噸,含有 26.7 萬盎司 auEQ,品位爲 0.72 g/t auEQ(參見 9 月 12 日更新 MRE 新聞稿)第四 2023)。

PEA-level bench optimization of the Pit-constrained Mineral Resource highlighted the higher-grade (~0.80 gpt AuEq), low strip ratio (~0.3) potential Starter Pit which contains 5.7 million tons of ore material (see PEA press release dated November 1st 2023). Recommendations of the PEA-level study included increasing Mineral Resource confidence in potential 'Starter Pit' and additional exploratory drilling to target the 1) footwall, 2) hanging wall and 3) 'keel' areas of the Stockwork Zone. P&E were again retained to lead the current El Tigre PFS-level study with 17,000m of the program complete (Figure 1). Complete and final assay results from the first fifteen (15) drill holes are listed in Table 1.

對礦坑受限的礦產資源進行PEA級別的基準優化凸顯了更高品位(約0.80 gpt auEq)、低開採率(約0.3)的潛在起始礦坑,其中含有570萬噸礦石材料(見PEA於11月1日發佈的新聞稿)st 2023)。PEA級別研究的建議包括提高礦產資源對潛在 “初級礦坑” 的信心,以及進行額外的勘探性鑽探,以瞄準庫區的 1) 腳牆、2) 懸掛牆和 3) “龍骨” 區域。P&E再次獲聘領導當前的El Tigre PFS級研究,該項目已完成1.7萬億英鎊(圖1)。表 1 中列出了前十五 (15) 個鑽孔的完整和最終化驗結果。

Below, highlighted intersections are enumerated with reference to the three (3) zones targeted:

下面,重點列舉了針對的三 (3) 個區域的交叉點:

  • Drill hole ET-23-479: Confirms higher-grade Tiger Vein area in starter pit, and expands HW and FW (Fig. 2);
  • Drill hole ET-23-486: Downhole intersection expands 'keel' associated with Tiger and SK veins at bottom of PEA pit floor;
  • Drill hole ET-23-489: Downhole intersection expands 'keel' associated with Tiger and SK veins at bottom of PEA pit floor; and
  • Drill hole ET-23-494: Shows at surface in 'Starter Pit'.
  • ET-23-479 鑽孔:確認起始礦坑中更高等級的虎脈區域,並擴展 HW 和 FW(圖 2);
  • 鑽孔 ET-23-486:井下交叉路口擴大 PEA 坑底部與 Tiger 和 SK 礦脈相關的 “龍骨”;
  • 鑽孔 ET-23-489:井下交叉路口擴大 PEA 坑底部與 Tiger 和 SK 礦脈相關的 “龍骨”;以及
  • 鑽孔 ET-23-494:顯示在 “起動坑” 的表面上。

Metallurgical Studies

冶金研究

The Company retained D.E.N.M. Engineering Ltd. (DENM), of Burlington, Ontario for the PFS-level metallurgical test work. After review of the PEA-level metallurgical studies completed, DENM recommended drilling six (6) new PQ-sized drill holes over a one-kilometre strike length of the designed PEA Stockwork (Figure 1). DENM selected McClelland Laboratories Inc. of Sparks, Nevada complete the independent PFS metallurgical testing of the gold and silver mineralization at the El Tigre project. Over 3,000 kg of mineralized material from six (6) 85 mm PQ drill holes were shipped to the laboratory for metallurgical testing with column leach testing underway. All metallurgical holes were subsequently assayed were appropriate to be included in PFS-level updated MRE with results listed in Table 2.

該公司聘請了位於安大略省伯靈頓的D.E.N.M. 工程有限公司(DENM)進行PFS級別的冶金測試工作。在完成對PEA級冶金研究的審查後,DENM建議在設計的PEA庫存一千米的走向長度上鑽探六(6)個新的PQ大小的鑽孔(圖1)。DENM選擇了位於內華達州斯帕克斯的麥克萊蘭實驗室公司完成了對El Tigre項目金銀礦化的獨立PFS冶金測試。來自六 (6) 個 85 mm PQ 鑽孔的 3,000 多千克礦化材料被運往實驗室進行冶金測試,柱浸測試正在進行中。隨後對所有冶金孔進行了檢測,均適合納入PFS級別的更新MRE,結果列於表2。

Geotechnical Studies

岩土工程研究

The company retained Golder/WSP for the PFS-level Stockwork design criteria. After an extensive desktop review and site visit, Golder recommended drilling thirteen (13) HQ-sized oriented drill holes in the western and eastern slopes over a two-kilometre strike length of the designed PEA Stockwork (Figure 1). Geotechnical drilling is completed with point load testing underway. All geotechnical holes will be assayed were appropriate to be included in PFS-level updated MRE.

該公司保留了Golder/WSP作爲PFS級別的Stockwork設計標準。經過廣泛的桌面審查和實地考察,Golder建議在設計的PEA Stockwork的兩千米的走向長度內,在西部和東部斜坡鑽探十三 (13) 個總部大小的定向鑽孔(圖 1)。岩土工程鑽探已經完成,點負荷測試正在進行中。將對所有岩土工程洞進行檢測,以確定是否適合包含在 PFS 級別更新的 MRE 中。

Upcoming Mining Conference Attendance

即將舉行的礦業會議出席人數

  • Silver Tiger will also be attending the BMO Global Metals, Mining and Critical Metals Conference from February 25 to February 28, 2024 in Hollywood, Florida.
  • Silver Tiger will also be attending PDAC in Toronto from March 3 to March 6, 2024. Our booth number will be 3206.
  • Silver Tiger還將參加2024年2月25日至2月28日在佛羅里達州好萊塢舉行的BMO全球金屬、礦業和關鍵金屬會議。
  • 銀虎還將參加2024年3月3日至3月6日在多倫多舉行的PDAC。我們的展位號將是 3206。

Underground Mineral Resource to Preliminary Economic Assessment - H2-2024

地下礦產資源到初步經濟評估-H2-2024

The Corporation will also continue to work on this substantial, permitted underground Mineral Resource Estimate and advance this towards a Preliminary Economic Assessment by H2-2024. The Indicated Out-of-Pit Mineral Resource at El Tigre is 21 Moz AgEq grading 279 g/t AgEq contained in 2.3 Mt and the Inferred Mineral Resource is 70 Moz AgEq grading 235 g/t AgEq contained in 9.2 Mt. For higher grade sensitivity cases refer to the Company's updated MRE press release dated September 12, 2023.

該公司還將繼續進行這項允許的大量地下礦產資源估算,並將其推向 H2-2024 的初步經濟評估。El Tigre的標明礦物資源爲21 Moz AgeQ,品位爲279 g/t AgeQ,包含在230萬噸中,推斷的礦產資源爲70 Moz AgeQ,品位爲235克/噸AgeQ。有關更高級別的敏感案例,請參閱公司於2023年9月12日發佈的最新MRE新聞稿。

Table 1-Mineral Resource Drill Hole Results

表 1-礦產資源鑽孔結果

AuEq Total (2)

AgEq Total (2)

Drill Hole ID

Comment

From

To

Length(1)

Gold

Silver

m

m

m

g/t

g/t

g/t

g/t

ET-23-479 STOCKWORK ZONE

22.0

76.0

54.0

0.71

10.1

0.85

63.7

STOCKWORK ZONE

96.5

150.0

53.5

1.21

19.5

1.47

110.0

including

97.9

120.0

22.1

1.98

5.9

2.06

154.4

including

132.0

147.0

15.0

0.96

29.9

1.36

101.8

and

166.9

173.5

6.6

0.18

172.5

2.48

186.0

ET-23-482 STOCKWORK ZONE

44.0

120.0

76.0

0.30

14.8

0.50

37.3

including

56.0

65.0

9.0

0.29

56.6

1.04

78.3

including

93.0

120.0

27.0

0.49

11.0

0.64

47.7

ET-23-483 STOCKWORK ZONE3

18.0

70.5

52.5

0.58

16.4

0.79

59.6

Including

12.0

29.0

17.0

0.70

16.3

0.92

68.9

STOCKWORK ZONE

121.0

129.0

8.0

0.49

1.1

0.50

37.9

STOCKWORK ZONE

157.5

170.0

12.5

0.76

1.4

0.78

58.3

ET-23-484 STOCKWORK ZONE

45.0

110.5

65.5

0.34

32.0

0.77

57.4

Including

91.5

107.5

16.0

0.58

104.3

1.97

147.6

ET-23-485 STOCKWORK ZONE

65.0

136.0

71.0

0.72

2.8

0.76

56.9

Including

114.0

136.0

22.0

0.89

3.3

0.93

69.9

Mining VOID

136.9

141.0

4.1

*

*

*

*

ET-23-486 STOCKWORK ZONE4

104.0

183.0

79.0

0.44

31.3

0.86

64.5

Mining VOID

155.0

158.0

3.0

*

*

*

*

Including

158.0

184.0

26.0

0.46

85.2

1.60

119.7

ET-23-487 STOCKWORK ZONE

0.0

23.0

23.0

0.35

15.7

0.56

42.2

STOCKWORK ZONE

45.0

49.0

4.0

1.80

7.3

1.89

141.9

STOCKWORK ZONE5

62.0

84.5

22.5

0.20

15.2

0.40

30.1

Mining VOID

69.5

70.5

1.0

*

*

*

*

ET-23-488 STOCKWORK ZONE

4.5

23.4

18.9

0.59

3.1

0.63

47.2

STOCKWORK ZONE

36.0

100.1

64.1

0.40

15.0

0.60

45.1

including

49.5

61.5

12.0

0.74

29.9

1.14

85.5

Mining VOID

100.1

102.0

1.9

*

*

*

*

STOCKWORK ZONE

114.6

142.5

27.9

0.68

12.8

0.85

63.7

ET-23-489 STOCKWORK ZONE6

101.0

190.5

89.5

0.60

22.3

0.89

67.1

Including

110.0

120.0

10.0

1.45

4.1

1.50

112.6

Including

142.5

151.4

8.9

1.69

14.3

1.88

141.0

Mining VOID

173.9

174.6

0.7

*

*

*

*

ET-23-490 STOCKWORK ZONE

1.3

45.0

43.7

0.45

27.8

0.83

61.9

Including

32.0

43.5

11.5

0.49

75.8

1.50

112.4

STOCKWORK ZONE

66.0

94.5

28.5

0.09

36.3

0.57

43.0

Including

83.5

90.5

7.0

0.19

103.0

1.56

117.3

ET-23-491 STOCKWORK ZONE7

20.0

101.0

81.0

0.50

9.5

0.62

46.7

Mining VOID

95.2

96.7

1.5

*

*

*

*

STOCKWORK ZONE

118.1

130.1

12.0

0.59

59.8

1.39

104.3

ET-23-492 STOCKWORK ZONE

16.0

67.5

51.5

0.53

8.2

0.63

47.6

Including

36.5

49.1

12.6

0.86

2.0

0.88

66.2

Including

59.0

67.5

8.5

0.91

6.3

1.00

74.9

ET-23-493 Footwall Vein

8.2

12.0

3.8

0.17

22.4

0.47

35.1

El Tigre Vein

48.0

53.0

5.0

1.03

2.4

1.07

79.9

SK Vein

67.5

73.5

6.0

1.21

53.8

1.92

144.2

ET-23-494 STOCKWORK ZONE

0.0

78.1

78.1

0.45

22.9

0.75

56.5

including

3.0

18.3

15.3

0.56

28.1

0.93

70.1

including

67.0

75.0

8.0

0.67

69.8

1.60

120.2

Mining VOID

78.1

81.7

3.6

*

*

*

*

ET-23-495 STOCKWORK ZONE

0.0

27.0

27.0

0.29

15.9

0.50

37.6

Mining VOID

61.5

62.8

1.3

*

*

*

*

STOCKWORK ZONE

62.8

77.1

14.3

0.16

38.8

0.68

50.9

auEQ 總計 (2)

AgeQ 總計 (2)

鑽孔 ID

評論

來自

長度(1)

黃金

m

m

m

g/t

g/t

g/t

g/t

ET-23-479 庫存區

22.0

76.0

54.0

0.71

10.1

0.85

63.7

庫存區

96.5

150.0

53.5

1.21

19.5

1.47

110.0

包括

97.9

120.0

22.1

1.98

5.9

2.06

154.4

包括

132.0

147.0

15.0

0.96

29.9

1.36

101.8

166.9

173.5

6.6

0.18

172.5

2.48

186.0

ET-23-482 庫存區

44.0

120.0

76.0

0.30

14.8

0.50

37.3

包括

56.0

65.0

9.0

0.29

56.6

1.04

78.3

包括

93.0

120.0

27.0

0.49

11.0

0.64

47.7

ET-23-483 庫存區3

18.0

70.5

52.5

0.58

16.4

0.79

59.6

包括

12.0

29.0

17.0

0.70

16.3

0.92

68.9

庫存區

121.0

129.0

8.0

0.49

1.1

0.50

37.9

庫存區

157.5

170.0

12.5

0.76

1.4

0.78

58.3

ET-23-484 庫存區

45.0

110.5

65.5

0.34

32.0

0.77

57.4

包括

91.5

107.5

16.0

0.58

104.3

1.97

147.6

ET-23-485 庫存區

65.0

136.0

71.0

0.72

2.8

0.76

56.9

包括

114.0

136.0

22.0

0.89

3.3

0.93

69.9

挖礦 VOID

136.9

141.0

4.1

*

*

*

*

ET-23-486 庫存區4

104.0

183.0

79.0

0.44

31.3

0.86

64.5

挖礦 VOID

155.0

158.0

3.0

*

*

*

*

包括

158.0

184.0

26.0

0.46

85.2

1.60

119.7

ET-23-487 庫存區

0.0

23.0

23.0

0.35

15.7

0.56

42.2

庫存區

45.0

49.0

4.0

1.80

7.3

1.89

141.9

庫存區5

62.0

84.5

22.5

0.20

15.2

0.40

30.1

挖礦 VOID

69.5

70.5

1.0

*

*

*

*

ET-23-488 庫存區

4.5

23.4

18.9

0.59

3.1

0.63

47.2

庫存區

36.0

100.1

64.1

0.40

15.0

0.60

45.1

包括

49.5

61.5

12.0

0.74

29.9

1.14

85.5

挖礦 VOID

100.1

102.0

1.9

*

*

*

*

庫存區

114.6

142.5

27.9

0.68

12.8

0.85

63.7

ET-23-489 庫存區6

101.0

190.5

89.5

0.60

22.3

0.89

67.1

包括

110.0

120.0

10.0

1.45

4.1

1.50

112.6

包括

142.5

151.4

8.9

1.69

14.3

1.88

141.0

挖礦 VOID

173.9

174.6

0.7

*

*

*

*

ET-23-490 庫存區

1.3

45.0

43.7

0.45

27.8

0.83

61.9

包括

32.0

43.5

11.5

0.49

75.8

1.50

112.4

庫存區

66.0

94.5

28.5

0.09

36.3

0.57

43.0

包括

83.5

90.5

7.0

0.19

103.0

1.56

117.3

ET-23-491 庫存區7

20.0

101.0

81.0

0.50

9.5

0.62

46.7

挖礦 VOID

95.2

96.7

1.5

*

*

*

*

庫存區

118.1

130.1

12.0

0.59

59.8

1.39

104.3

ET-23-492 庫存區

16.0

67.5

51.5

0.53

8.2

0.63

47.6

包括

36.5

49.1

12.6

0.86

2.0

0.88

66.2

包括

59.0

67.5

8.5

0.91

6.3

1.00

74.9

ET-23-493 Footwall Vein

8.2

12.0

3.8

0.17

22.4

0.47

35.1

El Tigre Vein

48.0

53.0

5.0

1.03

2.4

1.07

79.9

SK Vein

67.5

73.5

6.0

1.21

53.8

1.92

144.2

ET-23-494 庫存區

0.0

78.1

78.1

0.45

22.9

0.75

56.5

包括

3.0

18.3

15.3

0.56

28.1

0.93

70.1

包括

67.0

75.0

8.0

0.67

69.8

1.60

120.2

挖礦 VOID

78.1

81.7

3.6

*

*

*

*

ET-23-495 庫存區

0.0

27.0

27.0

0.29

15.9

0.50

37.6

挖礦 VOID

61.5

62.8

1.3

*

*

*

*

庫存區

62.8

77.1

14.3

0.16

38.8

0.68

50.9

Notes:

注意事項:

  1. Not true width.
  2. Silver Equivalent ("AgEq") ratios are based on a silver to gold price ratio of 75:1 (Au:Ag).
  3. Excludes 2.7m of Mining VOID
  4. Excludes 3.0m of Mining VOID
  5. Excludes 1.0m of Mining VOID
  6. Excludes 0.7m of Mining VOID
  7. Excludes 1.5m of Mining VOID
  1. 不是真正的寬度。
  2. 白銀當量(“AgeQ”)比率基於白銀與黃金的價格比率爲 75:1(Au: Ag)。
  3. 不包括 270 萬的採礦空白
  4. 不包括 300 萬英鎊的採礦空白
  5. 不包括 1.0 萬英鎊的採礦空白
  6. 不包括70萬的採礦空白
  7. 不包括 150 萬的採礦空白

Table 2-Metallurgical Drill Hole Results

表 2-冶金鑽孔結果

AuEq Total (2)

AgEq Total (2)

Drill Hole ID

Comment

From

To

Length(1)

Gold

Silver

m

m

m

g/t

g/t

g/t

g/t

ET-23-475 STOCKWORK ZONE

37.0

51.0

14.0

0.34

2.4

0.37

27.8

STOCKWORK ZONE

101.0

104.0

3.0

0.63

2.5

0.66

49.8

STOCKWORK ZONE

121.3

143.3

22.0

0.25

25.1

0.59

44.1

including

121.3

123.2

1.9

1.03

80.4

2.10

157.8

including

141.2

143.3

2.1

0.36

155.9

2.44

183.1

Mining Void

153.5

156.2

2.7

*

*

*

*

ET-23-476 STOCKWORK ZONE

33.0

40.1

7.1

0.28

5.8

0.36

27.1

STOCKWORK ZONE

66.5

92.4

25.9

0.28

11.2

0.43

32.5

including

69.5

88.5

19.0

0.33

13.4

0.51

38.3

Mining Void

92.4

94.5

2.1

*

*

*

*

STOCKWORK ZONE

106.5

173.0

66.5

0.56

1.9

0.59

44.0

including

106.5

126.0

19.5

1.19

1.6

1.22

91.2

including

119.0

126.0

7.0

2.52

2.0

2.55

191.2

Mining Void

142.5

143.7

1.2

*

*

*

*

ET-23-477 STOCKWORK ZONE

45.0

109.0

64.0

0.33

15.1

0.53

40.0

including

92.5

108.0

15.5

0.50

34.6

0.96

72.2

including

92.5

96.7

4.2

1.24

7.7

1.34

100.8

and

169.2

175.0

5.8

0.09

134.7

1.88

141.1

ET-23-478 STOCKWORK ZONE

0.0

34.7

34.7

0.77

14.3

0.96

72.4

including

4.5

28.2

23.7

0.95

18.2

1.19

89.1

STOCKWORK ZONE

57.7

130.2

72.5

0.40

10.7

0.54

40.5

including

58.7

93.0

34.3

0.64

5.8

0.72

53.8

including

128.2

130.2

2.0

0.36

72.5

1.32

99.2

ET-23-480 STOCKWORK ZONE

19.0

65.0

46.0

0.32

3.5

0.37

27.6

STOCKWORK ZONE

86.0

117.3

31.3

0.40

14.5

0.59

44.6

including

88.0

113.0

25.0

0.47

16.4

0.69

51.4

ET-23-481 STOCKWORK ZONE

139.0

162.0

23.0

0.88

43.8

1.46

109.5

including

140.0

145.5

5.5

1.36

43.7

1.94

145.6

including

151.0

152.9

1.9

3.14

301.0

7.16

536.9

auEQ 總計 (2)

AgeQ 總計 (2)

鑽孔 ID

評論

來自

長度(1)

黃金

m

m

m

g/t

g/t

g/t

g/t

ET-23-475 庫存區

37.0

51.0

14.0

0.34

2.4

0.37

27.8

庫存區

101.0

104.0

3.0

0.63

2.5

0.66

49.8

庫存區

121.3

143.3

22.0

0.25

25.1

0.59

44.1

包括

121.3

123.2

1.9

1.03

80.4

2.10

157.8

包括

141.2

143.3

2.1

0.36

155.9

2.44

183.1

採礦空洞

153.5

156.2

2.7

*

*

*

*

ET-23-476 庫存區

33.0

40.1

7.1

0.28

5.8

0.36

27.1

庫存區

66.5

92.4

25.9

0.28

11.2

0.43

32.5

包括

69.5

88.5

19.0

0.33

13.4

0.51

38.3

採礦空洞

92.4

94.5

2.1

*

*

*

*

庫存區

106.5

173.0

66.5

0.56

1.9

0.59

44.0

包括

106.5

126.0

19.5

1.19

1.6

1.22

91.2

包括

119.0

126.0

7.0

2.52

2.0

2.55

191.2

採礦空洞

142.5

143.7

1.2

*

*

*

*

ET-23-477 庫存區

45.0

109.0

64.0

0.33

15.1

0.53

40.0

包括

92.5

108.0

15.5

0.50

34.6

0.96

72.2

包括

92.5

96.7

4.2

1.24

7.7

1.34

100.8

169.2

175.0

5.8

0.09

134.7

1.88

141.1

ET-23-478 庫存區

0.0

34.7

34.7

0.77

14.3

0.96

72.4

包括

4.5

28.2

23.7

0.95

18.2

1.19

89.1

庫存區

57.7

130.2

72.5

0.40

10.7

0.54

40.5

包括

58.7

93.0

34.3

0.64

5.8

0.72

53.8

包括

128.2

130.2

2.0

0.36

72.5

1.32

99.2

ET-23-480 庫存區

19.0

65.0

46.0

0.32

3.5

0.37

27.6

庫存區

86.0

117.3

31.3

0.40

14.5

0.59

44.6

包括

88.0

113.0

25.0

0.47

16.4

0.69

51.4

ET-23-481 庫存區

139.0

162.0

23.0

0.88

43.8

1.46

109.5

包括

140.0

145.5

5.5

1.36

43.7

1.94

145.6

包括

151.0

152.9

1.9

3.14

301.0

7.16

536.9

Notes:

注意事項:

  1. Not true width.
  2. Silver Equivalent ("AgEq") ratios are based on a silver to gold price ratio of 75:1
  1. 不是真正的寬度。
  2. 白銀等價物(“AgeQ”)比率基於白銀與黃金的價格比率 75:1

Table 3-Drill Hole Locations

表 3-鑽孔位置

Drill Hole ID

Easting (UTM)

Northing (UTM)

Elevation (masl)

Azimuth (o)

Dip

(o)

Length

(m)

ET-23-475

671,036.0

3,384,546.1

2097.7

90

-60

176.0

ET-23-476

671,085.8

3,384,317.5

1978.3

90

-45

175.1

ET-23-477

671,111.8

3,384,070.9

1958.3

90

-45

176.0

ET-23-478

671,136.2

3,383,846.2

1893.8

90

-45

150.7

ET-23-479

671,082.8

3,384,128.3

1943.8

90

-45

190.0

ET-23-480

671,153.3

3,383,764.8

1931.7

90

-45

122.3

ET-23-481

671,188.6

3,383,604.5

2033.1

90

-50

202.0

ET-23-482

671,116.3

3,384,091.7

1971.0

90

-45

120.0

ET-23-483

671,146.1

3,384,143.4

1983.3

90

-50

170.0

ET-23-484

671,112.3

3,384,070.5

1958.3

90

-45

180.0

ET-23-485

671,054.7

3,384,175.7

1921.0

90

-51

141.0

ET-23-486

671,045.6

3,384,070.9

1951.2

90

-45

212.0

ET-23-487

671,146.1

3,383,927.6

1868.4

90

-45

111.0

ET-23-488

671,094.7

3,384,222.9

1939.9

90

-57

165.0

ET-23-489

671,042.9

3,384,049.3

1942.6

90

-45

220.0

ET-23-490

671,121.6

3,383,922.4

1862.3

90

-45

123.0

ET-23-491

671,089.4

3,384,190.6

1932.6

90

-45

180.0

ET-23-492

671,181.1

3,384,050.9

1949.4

90

-47

170.0

ET-23-493

671,206.1

3,383,925.4

1893.8

90

-45

120.0

ET-23-494

671,136.7

3,384,022.2

1931.8

90

-50

122.0

ET-23-495

671,152.4

3,383,948.0

1881.8

90

-46

130.5

鑽孔 ID

東部 (UTM)

北方 (UTM)

海拔(面具)

方位角(o)

(o)

長度

(m)

ET-23-475

671,036.0

3,384,546.1

2097.7

90

-60

176.0

ET-23-476

671,085.8

3,384,317.5

1978.3

90

-45

175.1

ET-23-477

671,111.8

3,384,070.9

1958.3

90

-45

176.0

ET-23-478

671,136.2

3,383,846.2

1893.8

90

-45

150.7

ET-23-479

671,082.8

3,384,128.3

1943.8

90

-45

190.0

ET-23-480

671,153.3

3,383,764.8

1931.7

90

-45

122.3

ET-23-481

671,188.6

3,383,604.5

2033.1

90

-50

202.0

ET-23-482

671,116.3

3,384,091.7

1971.0

90

-45

120.0

ET-23-483

671,146.1

3,384,143.4

1983.3

90

-50

170.0

ET-23-484

671,112.3

3,384,070.5

1958.3

90

-45

180.0

ET-23-485

671,054.7

3,384,175.7

1921.0

90

-51

141.0

ET-23-486

671,045.6

3,384,070.9

1951.2

90

-45

212.0

ET-23-487

671,146.1

3,383,927.6

1868.4

90

-45

111.0

ET-23-488

671,094.7

3,384,222.9

1939.9

90

-57

165.0

ET-23-489

671,042.9

3,384,049.3

1942.6

90

-45

220.0

ET-23-490

671,121.6

3,383,922.4

1862.3

90

-45

123.0

ET-23-491

671,089.4

3,384,190.6

1932.6

90

-45

180.0

ET-23-492

671,181.1

3,384,050.9

1949.4

90

-47

170.0

ET-23-493

671,206.1

3,383,925.4

1893.8

90

-45

120.0

ET-23-494

671,136.7

3,384,022.2

1931.8

90

-50

122.0

ET-23-495

671,152.4

3,383,948.0

1881.8

90

-46

130.5

Figure 3: El Tigre - Conceptual Cross-Section Showing Mineralization Styles

圖 3:El Tigre-顯示礦化風格的概念橫截面

Figure 4: El Tigre-Longitudinal Projection Showing Exploration Potential

圖 4:顯示勘探潛力的 El Tigre-縱向投影

About Silver Tiger and the El Tigre Historic Mine District

關於 Silver Tiger 和 El Tigre 歷史礦區

Silver Tiger Metals Inc. is a Canadian company whose management has more than 25 years' experience discovering, financing and building large hydrothermal silver projects in Mexico. Silver Tiger's 100% owned 28,414 hectare historic El Tigre Mining District is located in Sonora, Mexico. Principled environmental, social and governance practices are core priorities at Silver Tiger.

Silver Tiger Metals Inc. 是一家加拿大公司,其管理層在墨西哥發現、融資和建設大型熱液銀項目方面擁有超過25年的經驗。Silver Tiger 100% 擁有佔地 28,414 公頃的歷史悠久的埃爾蒂格雷礦區,位於墨西哥索諾拉。有原則的環境、社會和治理實踐是Silver Tiger的核心優先事項。

The El Tigre historic mine district is located in Sonora, Mexico and lies at the northern end of the Sierra Madre silver and gold belt which hosts many epithermal silver and gold deposits, including Dolores, Santa Elena and Las Chispas at the northern end. In 1896, gold was first discovered on the Property in the Gold Hill area and mining started with the Brown Shaft in 1903. The focus soon changed to mining silver veins in the area with production coming from 3 parallel veins the El Tigre Vein, the Seitz Kelley Vein and the Sooy Vein. Underground mining on the middle El Tigre Vein extended 1,450 metres along strike and was mined on 14 levels to a depth of approximately 450 metres. The Seitz Kelley Vein was mined along strike for 1 kilometre to a depth of approximately 200 metres. The Sooy Vein was only mined along strike for 250 metres to a depth of approximately 150 metres. Mining abruptly stopped on all 3 of these veins when the price of silver collapsed to less than US20¢ per ounce with the onset of the Great Depression. By the time the mine closed in 1930, it is reported to have produced a total of 353,000 ounces of gold and 67.4 million ounces of silver from 1.87 million tons (Craig, 2012). The average grade mined during this period was over 2 kilograms silver equivalent per ton.

埃爾蒂格雷歷史礦區位於墨西哥索諾拉,位於馬德雷山脈銀金帶的北端,那裏有許多超熱銀和金礦牀,包括北端的多洛雷斯、聖埃琳娜和拉斯奇斯帕斯。1896年,金山地區的該地產首次發現了黃金,1903年從棕礦井開始開採。重點很快轉向了開採該地區的銀礦脈,產量來自三條平行礦脈,即埃爾蒂格雷礦脈、塞茨凱利礦脈和蘇伊礦脈。埃爾蒂格雷脈中部的地下采礦沿着走向延伸了1,450米,在14層進行了地下采礦,深度約爲450米。Seitz Kelley Vein 沿着走向地雷開採了 1 千米,深度約爲 200 米。Sooy Vein 僅在攻擊沿線 250 米處埋設地雷,深度約爲 150 米。隨着大蕭條的開始,白銀價格跌至每盎司20美分以下,這三個礦脈的採礦突然停止了。據報道,到1930年該礦關閉時,它從187萬噸中總共生產了35.3萬盎司黃金和6,740萬盎司白銀(Craig,2012年)。在此期間開採的平均品位超過每噸2千克白銀當量。

The El Tigre silver and gold deposit is related to a series of epithermal veins controlled by a north-south trending structure cutting across the andesitic and rhyolitic tuffs of the Sierra Madre Volcanic Complex within a broad silver and gold mineralized prophylitic alteration zone developed in the El Tigre Formation that can be up to 150 metres wide. The veins dip steeply to the west and are typically 0.5 metre wide; however, locally can be up to 5 metres in width. The veins, structures and mineralized zones outcrop on surface and have been traced for 5.3 kilometres along strike in our brownfield exploration area. Historical mining and exploration activities focused on a 1.6 kilometre portion of the southern end of the deposits, principally on the El Tigre, Seitz Kelly and Sooy veins. The under explored Caleigh, Benjamin, Protectora and the Fundadora exposed veins continue north for more than 3 kilometres. Silver Tiger has delivered its updated NI 43-101 compliant Mineral Resource Estimate and PEA, and is currently drilling to update its Mineral Resource Estimate and publish a PFS.

埃爾蒂格雷銀金礦牀與一系列超熱礦脈有關,該礦脈由南北向結構控制,該結構橫跨馬德雷山脈火山群的安第斯巖和流紋凝灰岩,位於埃爾蒂格雷組開發的寬闊的銀金礦化預生蝕變帶內,寬度可達150米。靜脈向西陡峭地傾斜,寬度通常爲 0.5 米;但是,局部靜脈的寬度可達 5 米。礦脈、結構和礦化帶在地表露出,沿着我們的棕地勘探區域走向進行了5.3公里的追蹤。歷史上的採礦和勘探活動集中在礦牀南端1.6公里處,主要是埃爾蒂格雷、塞茨凱利和蘇伊礦脈。未開發的卡利、本傑明、Protectora和Fundadora裸露的礦脈向北延伸了3公里以上。Silver Tiger已經發布了符合NI 43-101標準的最新礦產資源估算和PEA,目前正在進行鑽探,以更新其礦產資源估算併發布PFS。

VRIFY Slide Deck and 3D Presentation - Silver Tiger's El Tigre Project

VRIFY 幻燈片和 3D 演示文稿——Silver Tiger 的 El Tigre 項目

VRIFY is a platform being used by companies to communicate with investors using 360° virtual tours of remote mining assets, 3D models and interactive presentations. VRIFY can be accessed by website and with the VRIFY iOS and Android apps.

VRIFY是公司使用的平台,通過遠程採礦資產的360°虛擬導覽、3D模型和交互式演示與投資者進行溝通。VRIFY 可以通過網站訪問,也可以通過 VRIFY iOS 和 Android 應用程序訪問。

Access the Silver Tiger Metals Inc. Company Profile on VRIFY at:

在 VRIFY 上訪問 Silver Tiger Metals Inc. 公司簡介,網址爲:

The VRIFY Slide Deck and 3D Presentation for Silver Tiger Metals Inc. can be viewed at: and on the Corporation's website at: .

Silver Tiger Metals Inc. 的 VRIFY Slide Deck 和 3D 演示文稿可以在以下網址查看:也可以在公司的網站上查看:。

Procedure, Quality Assurance / Quality Control and Data Verification

程序、質量保證/質量控制和數據驗證

The diamond drill core (HQ size) is geologically logged, photographed and marked for sampling. When the sample lengths are determined, the full drill core is sawn with a diamond blade drill core saw with one half of the drill core being bagged and tagged for assay. The remaining half portion is returned to the drill core trays for storage and/or for metallurgical test work.

金剛石鑽芯(HQ 尺寸)經過地質記錄、拍照並標記以供採樣。確定樣品長度後,使用金剛石刀片鑽芯鋸切割整個鑽芯,將一半的鑽芯裝袋並標記進行化驗。剩餘的一半將返回鑽芯托盤進行儲存和/或進行冶金測試工作。

The sealed and tagged drill core sample bags are transported to the Bureau Veritas facility in Hermosillo, Mexico. Bureau Veritas crushes the samples (Code PRP70-250) and prepares 200-300 gram pulp samples with ninety percent passing Tyler 200 mesh (Code PUL85). The pulps are assayed for gold using a 30-gram charge by fire assay (Code FA630) and over limits greater than 10 grams per tonne are re-assayed using a gravimetric finish (Code FA530). Silver and multi-element analysis is completed using total digestion (Code MA200 Total Digestion ICP). Over limits greater than 100 grams per tonne silver are re-assayed using a gravimetric finish (Code FA530).

密封並貼有標籤的鑽芯樣品袋被運送到墨西哥埃莫西約的必維集團工廠。必維國際檢驗集團壓碎樣品(代碼 PRP70-250),製備 200-300 克紙漿樣品,百分之九十通過泰勒 200 目(代碼 PUL85)。使用30克的電荷通過火法試驗(代碼 FA630)對紙漿進行金檢測,超過每噸10克的限值使用重量法完成(代碼 FA530)重新測定。銀和多元素分析使用全消化(代碼 MA200 總消化 ICP)完成。對於超過限值的每噸 100 克的銀,使用重量法進行重新分析(代碼 FA530)。

Quality assurance and quality control ("QA/QC") procedures monitor the chain-of-custody of the samples and includes the systematic insertion and monitoring of appropriate reference materials (certified reference materials, blanks and duplicates) into the sample strings. The results of the assaying of the QA/QC material included in each batch are tracked to ensure the integrity of the assay data. All results stated in this announcement have passed Silver Tiger's QA/QC protocols.

質量保證和質量控制(“QA/QC”)程序對樣品的監管鏈進行監管,包括系統地將適當的參考材料(經認證的參考材料、空白和副本)插入樣本串並進行監測。跟蹤每批中包含的質量保證/質量控制材料的分析結果,以確保分析數據的完整性。本公告中列出的所有結果均已通過Silver Tiger的質量保證/質量控制協議。

Qualified Person

合格人員

David R. Duncan, P. Geo., V.P. Exploration of the Corporation, is the Qualified Person for Silver Tiger as defined under National Instrument 43-101. Mr. Duncan has reviewed and approved the scientific and technical information in this press release.

根據國家儀器43-101的定義,公司勘探副總裁David R. Duncan,P. Geo.,是銀虎合格人士。鄧肯先生審查並批准了本新聞稿中的科學和技術信息。

For further information, please contact:

欲了解更多信息,請聯繫:

Glenn Jessome
President and CEO
902 492 0298
jessome@silvertigermetals.com

Glenn Jessome
總裁兼首席執行官
902 492 0298
jessome@silvertigermetals.com

CAUTIONARY STATEMENT:

警示聲明:

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

多倫多證券交易所風險投資交易所及其監管服務提供商(該術語在多倫多證券交易所風險交易所的政策中定義)均不對本新聞稿的充分性或準確性承擔責任。

This News Release includes certain "forward-looking statements". All statements other than statements of historical fact included in this release, including, without limitation, statements regarding potential mineralization, Mineral Resources and Mineral Reserves, the ability to convert Inferred Resources to Indicated Resources, the ability to complete future drilling programs and infill sampling, the ability to extend Mineral Resource blocks, the similarity of mineralization at El Tigre to Delores, Santa Elena and Chispas, exploration results, and future plans and objectives of Silver Tiger, are forward-looking statements that involve various risks and uncertainties. Forward-looking statements are frequently characterized by words such as "may", "is expected to", "anticipates", "estimates", "intends", "plans", "projection", "could", "vision", "goals", "objective" and "outlook" and other similar words. Although Silver Tiger believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, there can be no assurance that such statements will prove to be accurate and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from Silver Tiger's expectations include risks and uncertainties related to exploration, development, operations, commodity prices and global financial volatility, risk and uncertainties of operating in a foreign jurisdiction as well as additional risks described from time to time in the filings made by Silver Tiger with securities regulators.

本新聞稿包括某些 “前瞻性陳述”。除本新聞稿中包含的歷史事實陳述外,所有陳述,包括但不限於有關潛在礦化、礦產資源和礦產儲量、將推斷資源轉換爲指示資源的能力、完成未來鑽探計劃和填充採樣的能力、擴展礦產資源區塊的能力、埃爾蒂格雷礦化與德洛雷斯、聖埃琳娜和奇斯帕斯的相似之處、勘探結果以及銀虎未來的計劃和目標的陳述,均爲前瞻性陳述這樣的陳述涉及各種風險和不確定性。前瞻性陳述通常以 “可能”、“預期”、“預期”、“估計”、“打算”、“計劃”、“預測”、“可能”、“願景”、“目標”、“目標” 和 “展望” 等詞語以及其他類似詞語來表徵。儘管Silver Tiger認爲此類前瞻性陳述中表達的預期是基於合理的假設,但無法保證此類陳述會被證明是準確的,實際結果和未來事件可能與此類陳述中的預期存在重大差異。可能導致實際業績與銀虎預期存在重大差異的重要因素包括與勘探、開發、運營、大宗商品價格和全球金融波動相關的風險和不確定性、在外國司法管轄區經營的風險和不確定性,以及銀虎向證券監管機構提交的文件中不時描述的其他風險。

SOURCE: Silver Tiger Metals Inc.

來源:銀虎金屬公司