Bellevue Gold (ASX:BGL) has entered into a toll treating agreement with a subsidiary of Genesis Minerals (ASX:GMD).

Bellevue Gold (ASX: BGL) 已与Genesis Minerals (ASX: GMD) 的子公司签订了通行费处理协议。

This agreement will enable Bellevue to generate early cash flow by processing material from its Vanguard open pit at Genesis's Gwalia processing facility. The agreement marks a significant milestone for Bellevue as it progresses towards the commissioning of its own processing plant in the December 2023 quarter.

该协议将使Bellevue能够通过加工位于Genesis的Gwalia加工设施的Vanguard露天矿的材料来产生早期的现金流。该协议对贝尔维尤来说是一个重要的里程碑,因为它将在2023年12月的季度投入使用自己的加工厂。

The toll treating agreement entails the transportation and processing of Vanguard ore at Genesis's Gwalia facility, located approximately 170km south of the Bellevue Gold Mine. This strategic arrangement allows Bellevue to commence cash flow generation in the September 2023 quarter, ahead of the scheduled processing at its own facility.

收费处理协议要求在位于贝尔维尤金矿以南约170公里的Gwalia工厂运输和加工Vanguard矿石。这一战略安排使Bellevue能够在2023年9月的季度开始产生现金流,然后再在自己的工厂进行预定处理。

Currently, mining operations are underway at the Vanguard pit, with stockpiling of ore taking place during the pre-production period at the Bellevue Gold Mine.

目前,Vanguard矿的采矿作业正在进行中,矿石储存是在贝尔维尤金矿的预生产期间进行的。

The pit is being mined and stockpiled due to its location within the boundary of the tailings storage facility. The waste material derived from the pit mining is being utilised in constructing the tailings dam wall. The open pit mining and construction of the tailings storage facility are progressing well, thanks to the efforts of NRW Holdings Limited (ASX:NWH), the surface mining contractor.

由于矿坑位于尾矿储存设施的边界内,因此正在开采和储存。矿坑开采产生的废物被用于建造尾矿大坝墙。露天采矿和尾矿储存设施的建设进展顺利,这要归功于露天采矿承包商NRW Holdings Limited(ASX: NWH)的努力。

Under the toll treating agreement, MLG Oz (ASX:MLG) will transport the open pit material to Genesis's Gwalia processing facility.

根据通行费处理协议,MLG Oz(ASX: MLG)将把露天矿材料运送到Genesis的Gwalia加工设施。

It is estimated that approximately 100,000 tonnes of ore, with an average gold grade of approximately 3g/t, will be processed as part of this agreement. By executing this agreement, Bellevue anticipates a positive NPV impact on the overall project, as the open pit material would have otherwise remained on the stockpile until later in the mine life.

据估计,作为该协议的一部分,将加工约100,000吨矿石,平均黄金品位约为3g/t。通过执行该协议,Bellevue预计将对整个项目产生积极的净现值影响,因为否则露天矿材料本来会留在库存中,直到矿山寿命的后期。

Meanwhile, the construction of Bellevue's processing facility is proceeding as scheduled and within the allocated budget. The plant is expected to be ready for commissioning with underground ore in the December 2023 quarter. The underground mine development is also on track, with the fourth and final jumbo rig being commissioned on-site.

同时,贝尔维尤加工设施的建设正在按计划进行,预算不超出预算。该工厂预计将在2023年12月的季度准备好投入使用地下矿石进行调试。地下矿山开发也已步入正轨,第四台也是最后一台巨型钻机正在现场调试。