Account Info
Log Out
English
Back
Log in to access Online Inquiry
Back to the Top

Delay in Chip Production Equipment Delivery Puts Samsung and TSMC on Alert.

$Taiwan Semiconductor(TSM.US)$ $SAMSUNG EL 144(SSNGY.US)$ $ASML Holding(ASML.US)$ Delivery times have increased sharply as demand for high-performance semiconductor production equipment is increasing due to surging demand for high-end chips amid a prolonged shortage of parts for semiconductor equipment production. SEMI predicted that the global semiconductor equipment investment will reach US$103 billion in 2022.

In January, the figure increased by US$5 billion from a previous estimate. Lead time from ordering a product to delivery expanded from three to four months in 2019 to 10 to 12 months in 2021.

Samsung Electronics, TSMC and UMC dispatched their officials to equipment makers to discuss ways to advance equipment delivery dates, according to Nikkei Asia.

The biggest issue in the semiconductor industry is to secure extreme ultraviolet (EUV) lithography equipment essential to semiconductor microfabrication. EUV lithography equipment is exclusively produced by ASML. Chipmakers around the world are focusing their efforts on securing EUV lithography equipment. ASML’s annual production stood at only 42 pieces of equipment as of 2021.

It is conceivable that production equipment has such a large impact on semiconductors
Disclaimer: Community is offered by Moomoo Technologies Inc. and is for educational purposes only. Read more
5
+0
Translate
Report
55K Views
Comment
Sign in to post a comment
    378Followers
    22Following
    924Visitors
    Follow